An innovative approach for constrained resource scheduling

Most large construction projects are scheduled using a critical path method (CPM) or similar, in which the project duration is calculated assuming unlimited resources. However, with "ranked positional weight method" (RPWM) it is possible to determine a project duration based on limited pro...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Veröffentlicht in:Proceedings of the Institution of Civil Engineers. Civil engineering 1999-05, Vol.132 (2-3), p.85-95
Hauptverfasser: TAM, P. W. M, DISSANAYAKE, P. B. G
Format: Artikel
Sprache:eng
Schlagworte:
Online-Zugang:Volltext
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
Beschreibung
Zusammenfassung:Most large construction projects are scheduled using a critical path method (CPM) or similar, in which the project duration is calculated assuming unlimited resources. However, with "ranked positional weight method" (RPWM) it is possible to determine a project duration based on limited provision of resources. Compares results obtained from RPWM with those from proprietary CPM software, and shows that RPWM to be much easier to apply than CPM. A relatively complex construction programme (the Kwai Chung Terminal, Hong Kong) is included as an example of the application of RPWM. (Original abstract - amended)
ISSN:0965-089X
1751-7672
DOI:10.1680/icien.1999.31733