Preparing the hardware of the CMS Electromagnetic Calorimeter control and safety systems for LHC Run 2
The Detector Control System of the CMS Electromagnetic Calorimeter has undergone significant improvements during the first LHC Long Shutdown. Based on the experience acquired during the first period of physics data taking of the LHC, several hardware projects were carried out to improve data accurac...
Gespeichert in:
Veröffentlicht in: | Journal of instrumentation 2016-01, Vol.11 (1), p.C01020-C01020 |
---|---|
Hauptverfasser: | , , , , , , , , |
Format: | Artikel |
Sprache: | eng |
Schlagworte: | |
Online-Zugang: | Volltext |
Tags: |
Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
|
Zusammenfassung: | The Detector Control System of the CMS Electromagnetic Calorimeter has undergone significant improvements during the first LHC Long Shutdown. Based on the experience acquired during the first period of physics data taking of the LHC, several hardware projects were carried out to improve data accuracy, to minimise the impact of failures and to extend remote control possibilities in order to accelerate recovery from problematic situations. This paper outlines the hardware of the detector control and safety systems and explains in detail the requirements, design and commissioning of the new hardware projects. |
---|---|
ISSN: | 1748-0221 1748-0221 |
DOI: | 10.1088/1748-0221/11/01/C01020 |