Approximability results for the resource-constrained project scheduling problem with a single type of resources
In this paper, we consider the well-known resource-constrained project scheduling problem. We give some arguments that already a special case of this problem with a single type of resources is not approximable in polynomial time with an approximation ratio bounded by a constant. We prove that there...
Gespeichert in:
Veröffentlicht in: | Annals of operations research 2014-02, Vol.213 (1), p.115-130 |
---|---|
Hauptverfasser: | , , |
Format: | Artikel |
Sprache: | eng |
Schlagworte: | |
Online-Zugang: | Volltext |
Tags: |
Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
|
Zusammenfassung: | In this paper, we consider the well-known resource-constrained project scheduling problem. We give some arguments that already a special case of this problem with a single type of resources is not approximable in polynomial time with an approximation ratio bounded by a constant. We prove that there exist instances for which the optimal makespan values for the non-preemptive and the preemptive problems have a ratio of
O
(log
n
), where
n
is the number of jobs. This means that there exist instances for which the lower bound of Mingozzi et al. has a bad relative error of
O
(log
n
), and the calculation of this bound is an NP-hard problem. In addition, we give a proof that there exists a type of instances for which known approximation algorithms with polynomial time complexity have an approximation ratio of at least equal to
, and known lower bounds have a relative error of at least equal to
O
(log
n
). This type of instances corresponds to the single machine parallel-batch scheduling problem 1|
p
−
batch
,
b
=∞|
C
max
. |
---|---|
ISSN: | 0254-5330 1572-9338 |
DOI: | 10.1007/s10479-012-1106-5 |