Measurement of AT electric railway system currents at power-supply frequency and validation of a multiconductor transmission-line model

An electric traction system supplied at 2 /spl times/ 25 kV with autotransformers (ATs) is considered. The conductors' arrangement is that of the new European High Speed Railway Line (HSRL) under construction: The overhead supply conductors in contact with the train pantograph are connected to...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Veröffentlicht in:IEEE transactions on power delivery 2006-07, Vol.21 (3), p.1721-1726
Hauptverfasser: Cella, R., Giuseppe Giangaspero, Mariscotti, A., Montepagano, A., Pozzobon, P., Ruscelli, M., Vanti, M.
Format: Artikel
Sprache:eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
Beschreibung
Zusammenfassung:An electric traction system supplied at 2 /spl times/ 25 kV with autotransformers (ATs) is considered. The conductors' arrangement is that of the new European High Speed Railway Line (HSRL) under construction: The overhead supply conductors in contact with the train pantograph are connected to a symmetrical circuit (the feeder) with the purpose of current balancing; the traction return current flows from the rolling stock axles back to the supply (i.e., substation) through the traction rails and additional return conductors. The test campaign carried on the Rome-Naples HSRL allowed the validation of the multiconductor transmission line model used for system analysis. Measurements were performed in normal system configuration (2 /spl times/ 25-kV supply) and degraded configuration (1 /spl times/ 25 kV with AT and feeder not operating). Metrological issues (accuracy and consistency) are detailed for the presented results.
ISSN:0885-8977
1937-4208
DOI:10.1109/TPWRD.2006.874109