Scheduling ordered open shops
We examine special cases of the open-shop problem to further define the boundary between “easy” and “hard” versions of the problem. A polynomial algorithm to minimize the sum of completion times in a preemptive open shop with ordered jobs is presented. A modification of this algorithm also minimizes...
Gespeichert in:
Veröffentlicht in: | Computers & operations research 1987, Vol.14 (3), p.257-264 |
---|---|
Hauptverfasser: | , |
Format: | Artikel |
Sprache: | eng |
Schlagworte: | |
Online-Zugang: | Volltext |
Tags: |
Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
|
Zusammenfassung: | We examine special cases of the open-shop problem to further define the boundary between “easy” and “hard” versions of the problem. A polynomial algorithm to minimize the sum of completion times in a preemptive open shop with ordered jobs is presented. A modification of this algorithm also minimizes tardiness in an agreeable open shop. We then show that minimizing makespan in an ordered three-machine open shop is NP-complete, which implies many other open-shop problems are also NP-complete. Finally, we show that slightly different assumptions can change a “hard” problem to an “easy” one. This is illustrated by the problem of minimizing makespan in a three-machine open shop with ordered machines, which is NP-complete. However, by further assuming the job with longest processing time on machine one is different from the job having the longest processing time on the second machine, a polynomial algorithm exists. |
---|---|
ISSN: | 0305-0548 1873-765X 0305-0548 |
DOI: | 10.1016/0305-0548(87)90029-3 |