Scheduling: Agreement graph vs resource constraints

We investigate two scheduling problems. The first is scheduling with agreements (SWA) that consists in scheduling a set of jobs non-preemptively on identical machines in a minimum time, subject to constraints that only some specific jobs can be scheduled concurrently. These constraints are represent...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Veröffentlicht in:European journal of operational research 2015-01, Vol.240 (2), p.355-360
Hauptverfasser: Cherif, W. Ramdane, Rahmani, Younes, Ramdane, Wahiba, Kovalyov, Mikhail, Soukhal, Ameur, Bendraouche, Mohamed, Boudhar, Mourad, Oulamara, Ammar
Format: Artikel
Sprache:eng
Schlagworte:
Online-Zugang:Volltext
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
Beschreibung
Zusammenfassung:We investigate two scheduling problems. The first is scheduling with agreements (SWA) that consists in scheduling a set of jobs non-preemptively on identical machines in a minimum time, subject to constraints that only some specific jobs can be scheduled concurrently. These constraints are represented by an agreement graph. We extend the NP-hardness of SWA with three distinct values of processing times to only two values and this definitely closes the complexity status of SWA on two machines with two fixed processing times. The second problem is the so-called resource-constrained scheduling. We prove that SWA is polynomially equivalent to a special case of the resource-constrained scheduling and deduce new complexity results of the latter.