Exact method for the two-machine flow-shop problem with time delays

We address the two-machine flow-shop scheduling problem with time delays in order to minimize the makespan, i.e., the maximum completion time. We present a comprehensive theoretical analysis of the different lower bounds of the state of the art and we elucidate dominance relationships between them....

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Veröffentlicht in:Annals of operations research 2021-03, Vol.298 (1-2), p.375-406
Hauptverfasser: Mkadem, Mohamed Amine, Moukrim, Aziz, Serairi, Mehdi
Format: Artikel
Sprache:eng
Schlagworte:
Online-Zugang:Volltext
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
Beschreibung
Zusammenfassung:We address the two-machine flow-shop scheduling problem with time delays in order to minimize the makespan, i.e., the maximum completion time. We present a comprehensive theoretical analysis of the different lower bounds of the state of the art and we elucidate dominance relationships between them. We then introduce an exact method based on a branch-and-bound scheme. This method includes a local search-based heuristic and three dominance rules. Finally, a computer simulation of the branch-and-bound method is given on a set of 480 instances. We point out the good performance of our branch-and-bound method that outperforms the state of the art exact method. Precisely, we manage to solve all the state of the art instances except one in a very short time.
ISSN:0254-5330
1572-9338
DOI:10.1007/s10479-018-3082-x