Grouted gravel column-supported highway embankment over soft clay: case study

In this paper, a simplified column construction method — the so-called grouted gravel column — and its application to construction of embankments over soft ground are introduced. The construction method, quality assurance (QA), and quality control (QC) of the grouted gravel columns are described. A...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Veröffentlicht in:Canadian geotechnical journal 2015-11, Vol.52 (11), p.1725-1733
Hauptverfasser: Liu, Hanlong, Kong, Gangqiang, Chu, Jian, Ding, Xuanming
Format: Artikel
Sprache:eng
Schlagworte:
Online-Zugang:Volltext
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
Beschreibung
Zusammenfassung:In this paper, a simplified column construction method — the so-called grouted gravel column — and its application to construction of embankments over soft ground are introduced. The construction method, quality assurance (QA), and quality control (QC) of the grouted gravel columns are described. A case study on the application of this method to a highway embankment in China is also presented. The case study shows that about 50% of surface settlement and 60% of the differential settlement between the column head and soil occurred during the construction of the embankment. The column to soil stress ratio was 8.0 for columns with caps and 4.2 for columns without caps. Static load tests were also conducted to assess the bearing capacity of the columns.
ISSN:0008-3674
1208-6010