Rapid construction method for secondary lining of small-section tunnel

A rapid construction method for a secondary lining of a small-section tunnel includes steps of: transporting and store secondary lining steel bars to a designated position in the tunnel with a steel bar transport vehicle and a wheel type dump truck; after the tunnel is cleaned, simultaneously constr...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: Liu, Kaiyang, Cao, Qin, Dai, Xiaosong, Su, Changyi, Yu, Nanshan, Sun, Qing, Jiang, Shangzhi, Cui, Jian, Cui, Lishan, Zhu, Haijun, Ye, Yisheng
Format: Patent
Sprache:eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator Liu, Kaiyang
Cao, Qin
Dai, Xiaosong
Su, Changyi
Yu, Nanshan
Sun, Qing
Jiang, Shangzhi
Cui, Jian
Cui, Lishan
Zhu, Haijun
Ye, Yisheng
description A rapid construction method for a secondary lining of a small-section tunnel includes steps of: transporting and store secondary lining steel bars to a designated position in the tunnel with a steel bar transport vehicle and a wheel type dump truck; after the tunnel is cleaned, simultaneously constructing the secondary lining from two ends to a middle of the tunnel; constructing a lower inverted arch with a customized inverted arch formwork and then constructing an upper arch wall with a plurality of portal arch wall formwork trolleys; wherein the portal arch wall formwork trolleys form a set, and are connected by hinges, so as to construct in a curve tunnel. The rapid construction method has a long single construction section, and procedure connection is compact, thereby realizing rapid and efficient construction of the secondary lining.
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_US11480054B2</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>US11480054B2</sourcerecordid><originalsourceid>FETCH-epo_espacenet_US11480054B23</originalsourceid><addsrcrecordid>eNrjZHALSizITFFIzs8rLikqTS7JzM9TyE0tychPUUjLL1IoTgXKpCQWVSrkZOZl5qUr5KcpFOcm5uToAmXAiktK8_JSc3gYWNMSc4pTeaE0N4Oim2uIs4duakF-fGpxQWJyal5qSXxosKGhiYWBgamJk5ExMWoAafc0IQ</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Rapid construction method for secondary lining of small-section tunnel</title><source>esp@cenet</source><creator>Liu, Kaiyang ; Cao, Qin ; Dai, Xiaosong ; Su, Changyi ; Yu, Nanshan ; Sun, Qing ; Jiang, Shangzhi ; Cui, Jian ; Cui, Lishan ; Zhu, Haijun ; Ye, Yisheng</creator><creatorcontrib>Liu, Kaiyang ; Cao, Qin ; Dai, Xiaosong ; Su, Changyi ; Yu, Nanshan ; Sun, Qing ; Jiang, Shangzhi ; Cui, Jian ; Cui, Lishan ; Zhu, Haijun ; Ye, Yisheng</creatorcontrib><description>A rapid construction method for a secondary lining of a small-section tunnel includes steps of: transporting and store secondary lining steel bars to a designated position in the tunnel with a steel bar transport vehicle and a wheel type dump truck; after the tunnel is cleaned, simultaneously constructing the secondary lining from two ends to a middle of the tunnel; constructing a lower inverted arch with a customized inverted arch formwork and then constructing an upper arch wall with a plurality of portal arch wall formwork trolleys; wherein the portal arch wall formwork trolleys form a set, and are connected by hinges, so as to construct in a curve tunnel. The rapid construction method has a long single construction section, and procedure connection is compact, thereby realizing rapid and efficient construction of the secondary lining.</description><language>eng</language><subject>EARTH DRILLING ; FIXED CONSTRUCTIONS ; GALLERIES ; LARGE UNDERGROUND CHAMBERS ; MINING ; SHAFTS ; TUNNELS</subject><creationdate>2022</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20221025&amp;DB=EPODOC&amp;CC=US&amp;NR=11480054B2$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,780,885,25563,76318</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20221025&amp;DB=EPODOC&amp;CC=US&amp;NR=11480054B2$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>Liu, Kaiyang</creatorcontrib><creatorcontrib>Cao, Qin</creatorcontrib><creatorcontrib>Dai, Xiaosong</creatorcontrib><creatorcontrib>Su, Changyi</creatorcontrib><creatorcontrib>Yu, Nanshan</creatorcontrib><creatorcontrib>Sun, Qing</creatorcontrib><creatorcontrib>Jiang, Shangzhi</creatorcontrib><creatorcontrib>Cui, Jian</creatorcontrib><creatorcontrib>Cui, Lishan</creatorcontrib><creatorcontrib>Zhu, Haijun</creatorcontrib><creatorcontrib>Ye, Yisheng</creatorcontrib><title>Rapid construction method for secondary lining of small-section tunnel</title><description>A rapid construction method for a secondary lining of a small-section tunnel includes steps of: transporting and store secondary lining steel bars to a designated position in the tunnel with a steel bar transport vehicle and a wheel type dump truck; after the tunnel is cleaned, simultaneously constructing the secondary lining from two ends to a middle of the tunnel; constructing a lower inverted arch with a customized inverted arch formwork and then constructing an upper arch wall with a plurality of portal arch wall formwork trolleys; wherein the portal arch wall formwork trolleys form a set, and are connected by hinges, so as to construct in a curve tunnel. The rapid construction method has a long single construction section, and procedure connection is compact, thereby realizing rapid and efficient construction of the secondary lining.</description><subject>EARTH DRILLING</subject><subject>FIXED CONSTRUCTIONS</subject><subject>GALLERIES</subject><subject>LARGE UNDERGROUND CHAMBERS</subject><subject>MINING</subject><subject>SHAFTS</subject><subject>TUNNELS</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2022</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNrjZHALSizITFFIzs8rLikqTS7JzM9TyE0tychPUUjLL1IoTgXKpCQWVSrkZOZl5qUr5KcpFOcm5uToAmXAiktK8_JSc3gYWNMSc4pTeaE0N4Oim2uIs4duakF-fGpxQWJyal5qSXxosKGhiYWBgamJk5ExMWoAafc0IQ</recordid><startdate>20221025</startdate><enddate>20221025</enddate><creator>Liu, Kaiyang</creator><creator>Cao, Qin</creator><creator>Dai, Xiaosong</creator><creator>Su, Changyi</creator><creator>Yu, Nanshan</creator><creator>Sun, Qing</creator><creator>Jiang, Shangzhi</creator><creator>Cui, Jian</creator><creator>Cui, Lishan</creator><creator>Zhu, Haijun</creator><creator>Ye, Yisheng</creator><scope>EVB</scope></search><sort><creationdate>20221025</creationdate><title>Rapid construction method for secondary lining of small-section tunnel</title><author>Liu, Kaiyang ; Cao, Qin ; Dai, Xiaosong ; Su, Changyi ; Yu, Nanshan ; Sun, Qing ; Jiang, Shangzhi ; Cui, Jian ; Cui, Lishan ; Zhu, Haijun ; Ye, Yisheng</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_US11480054B23</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>eng</language><creationdate>2022</creationdate><topic>EARTH DRILLING</topic><topic>FIXED CONSTRUCTIONS</topic><topic>GALLERIES</topic><topic>LARGE UNDERGROUND CHAMBERS</topic><topic>MINING</topic><topic>SHAFTS</topic><topic>TUNNELS</topic><toplevel>online_resources</toplevel><creatorcontrib>Liu, Kaiyang</creatorcontrib><creatorcontrib>Cao, Qin</creatorcontrib><creatorcontrib>Dai, Xiaosong</creatorcontrib><creatorcontrib>Su, Changyi</creatorcontrib><creatorcontrib>Yu, Nanshan</creatorcontrib><creatorcontrib>Sun, Qing</creatorcontrib><creatorcontrib>Jiang, Shangzhi</creatorcontrib><creatorcontrib>Cui, Jian</creatorcontrib><creatorcontrib>Cui, Lishan</creatorcontrib><creatorcontrib>Zhu, Haijun</creatorcontrib><creatorcontrib>Ye, Yisheng</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>Liu, Kaiyang</au><au>Cao, Qin</au><au>Dai, Xiaosong</au><au>Su, Changyi</au><au>Yu, Nanshan</au><au>Sun, Qing</au><au>Jiang, Shangzhi</au><au>Cui, Jian</au><au>Cui, Lishan</au><au>Zhu, Haijun</au><au>Ye, Yisheng</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Rapid construction method for secondary lining of small-section tunnel</title><date>2022-10-25</date><risdate>2022</risdate><abstract>A rapid construction method for a secondary lining of a small-section tunnel includes steps of: transporting and store secondary lining steel bars to a designated position in the tunnel with a steel bar transport vehicle and a wheel type dump truck; after the tunnel is cleaned, simultaneously constructing the secondary lining from two ends to a middle of the tunnel; constructing a lower inverted arch with a customized inverted arch formwork and then constructing an upper arch wall with a plurality of portal arch wall formwork trolleys; wherein the portal arch wall formwork trolleys form a set, and are connected by hinges, so as to construct in a curve tunnel. The rapid construction method has a long single construction section, and procedure connection is compact, thereby realizing rapid and efficient construction of the secondary lining.</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language eng
recordid cdi_epo_espacenet_US11480054B2
source esp@cenet
subjects EARTH DRILLING
FIXED CONSTRUCTIONS
GALLERIES
LARGE UNDERGROUND CHAMBERS
MINING
SHAFTS
TUNNELS
title Rapid construction method for secondary lining of small-section tunnel
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-10T17%3A50%3A03IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=Liu,%20Kaiyang&rft.date=2022-10-25&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3EUS11480054B2%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true