Method for controlling HP-bypass pressure control valve of drum type fluidized boiler of thermal power plant shut down

The present invention relates to a method to control a high pressure turbine bypass pressure control valve in shutdown of a drum type fluidized bed boiler of a thermal power plant, capable of controlling a water level in a boiler drum. According to the present invention, the method comprises: a step...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: JEONG, YEON JUNG, HONG, EUI BEOM, JUNG, JONG HA
Format: Patent
Sprache:eng ; kor
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
Beschreibung
Zusammenfassung:The present invention relates to a method to control a high pressure turbine bypass pressure control valve in shutdown of a drum type fluidized bed boiler of a thermal power plant, capable of controlling a water level in a boiler drum. According to the present invention, the method comprises: a step 1) of using a preset time delay function to the flow rate of main steam moving from a steam drum through a superheater to detect the flow rate of main steam at a boiler shutdown time point when closing a high pressure turbine control valve just after shutdown of a drum type boiler of a thermal power plant; a step 2) of determining a valve stroke with respect to the flow rate of main steam by a function converter including a characteristic function (f(x)), which is calculated by a flow rate characteristic relation with respect to a unique valve stroke of a high pressure turbine bypass pressure valve installed in a bypass for allowing the main steam to bypass the high pressure turbine; a step 3) of opening the high pressure turbine bypass pressure valve as much as the valve stroke in accordance with the flow rate of main steam detected in the step 1) during a predetermined time (t) from the boiler shutdown time point by the valve stroke with respect to the flow rate of main steam determined in the step 2); and a step 4) of calculating a deviation between a main steam pressure set point and the pressure of main steam after the predetermined time (t) from the boiler shutdown time point. 본 발명에 따른 화력발전소의 드럼형 유동층 보일러 정지시 고압터빈 우회 압력밸브 제어방법은 1) 화력발전소 드럼형 보일러 정지 직후 고압터빈 제어밸브 폐쇄시 증기드럼으로부터 과열기를 거쳐 이동하는 주증기 유량에 기설정 시간의 지연함수를 사용하여 보일러 정지 시점의 주증기 유량을 검출하는 단계와, 2) 상기 주증기가 고압터빈을 우회하는 우회로에 설치되는 고압터빈 우회 압력밸브 고유의 밸브 스트로크 대비 유량 특성관계에 의해 산출된 특성함수(f(x))를 내장한 함수변환기에 의해 주증기 유량 대비 밸브 스트로크(stroke)를 결정하는 단계와, 3) 상기 2)단계에서 결정된 주증기 유량 대비 밸브 스트로크(stroke)에 의해 보일러 정지시점부터 일정 시간(t) 동안 상기 1)단계에서 검출된 주증기 유량에 따른 밸브 스트로크만큼 상기 고압터빈 우회 압력밸브를 개방하는 단계와, 4) 상기 보일러 정지 일정 시간(t) 후부터는 주증기 압력 설정값(set point)과 상기 주증기 압력의 편차를 계산하여 제어부를 통해 고압터빈 우회 압력밸브를 제어하는 단계를 포함하여 이루어지는 것을 특징으로 한다.