LINING METHOD OF BAGGED CONCRETE

PURPOSE: To accurately construct a lining body closely stuck to the ground in a simplified process in a lining method in which only the outer shell of a tunnel is excavated ahead of time and reduce the construction period and cost. CONSTITUTION: Underground is excavated by an excavating machine 30 a...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: CHOKAI SUMIO, NINOMIYA KOJI, HAMADA KAZUTO, ASAGAMI YUJI, OKU TOSHIAKI, SADATSUKA MASAYUKI, IDA TAKAHISA, KANEKO MASASHI
Format: Patent
Sprache:eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator CHOKAI SUMIO
NINOMIYA KOJI
HAMADA KAZUTO
ASAGAMI YUJI
OKU TOSHIAKI
SADATSUKA MASAYUKI
IDA TAKAHISA
KANEKO MASASHI
description PURPOSE: To accurately construct a lining body closely stuck to the ground in a simplified process in a lining method in which only the outer shell of a tunnel is excavated ahead of time and reduce the construction period and cost. CONSTITUTION: Underground is excavated by an excavating machine 30 and after a certain unit in length has been excavated, vacant bags having water permeability are arranged in the groove-shaped and circular ground void generated at the rear side of excavating machine 30 and concrete (or mortar) is placed in the bags with pressure to construct the bagged concrete 31 as a concrete lining body. The working tunnels 33 may be applied with the bagged lining bodies in the same way with the ring part 32. The bagged concrete right after placing may be more pressurized to closely stick to the ground and more dewatered. In this way, the ground is prevented from slacking, by the pressurizing process and the quality of the bagged concrete lining body is increased owing to the dewatering of unnecessary water. Because of the bagged concrete, it is prevented from flowing out and hence, soil and underground water are prevented from mixing therewith and the quality can be secured.
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_JPH08326489A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>JPH08326489A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_JPH08326489A3</originalsourceid><addsrcrecordid>eNrjZFDw8fTz9HNX8HUN8fB3UfB3U3BydHd3dVFw9vdzDnINceVhYE1LzClO5YXS3AyKbq4hzh66qQX58anFBYnJqXmpJfFeAR4GFsZGZiYWlo7GxKgBANoIId0</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>LINING METHOD OF BAGGED CONCRETE</title><source>esp@cenet</source><creator>CHOKAI SUMIO ; NINOMIYA KOJI ; HAMADA KAZUTO ; ASAGAMI YUJI ; OKU TOSHIAKI ; SADATSUKA MASAYUKI ; IDA TAKAHISA ; KANEKO MASASHI</creator><creatorcontrib>CHOKAI SUMIO ; NINOMIYA KOJI ; HAMADA KAZUTO ; ASAGAMI YUJI ; OKU TOSHIAKI ; SADATSUKA MASAYUKI ; IDA TAKAHISA ; KANEKO MASASHI</creatorcontrib><description>PURPOSE: To accurately construct a lining body closely stuck to the ground in a simplified process in a lining method in which only the outer shell of a tunnel is excavated ahead of time and reduce the construction period and cost. CONSTITUTION: Underground is excavated by an excavating machine 30 and after a certain unit in length has been excavated, vacant bags having water permeability are arranged in the groove-shaped and circular ground void generated at the rear side of excavating machine 30 and concrete (or mortar) is placed in the bags with pressure to construct the bagged concrete 31 as a concrete lining body. The working tunnels 33 may be applied with the bagged lining bodies in the same way with the ring part 32. The bagged concrete right after placing may be more pressurized to closely stick to the ground and more dewatered. In this way, the ground is prevented from slacking, by the pressurizing process and the quality of the bagged concrete lining body is increased owing to the dewatering of unnecessary water. Because of the bagged concrete, it is prevented from flowing out and hence, soil and underground water are prevented from mixing therewith and the quality can be secured.</description><edition>6</edition><language>eng</language><subject>EARTH DRILLING ; FIXED CONSTRUCTIONS ; GALLERIES ; LARGE UNDERGROUND CHAMBERS ; MINING ; SHAFTS ; TUNNELS</subject><creationdate>1996</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=19961210&amp;DB=EPODOC&amp;CC=JP&amp;NR=H08326489A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,778,883,25551,76304</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=19961210&amp;DB=EPODOC&amp;CC=JP&amp;NR=H08326489A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>CHOKAI SUMIO</creatorcontrib><creatorcontrib>NINOMIYA KOJI</creatorcontrib><creatorcontrib>HAMADA KAZUTO</creatorcontrib><creatorcontrib>ASAGAMI YUJI</creatorcontrib><creatorcontrib>OKU TOSHIAKI</creatorcontrib><creatorcontrib>SADATSUKA MASAYUKI</creatorcontrib><creatorcontrib>IDA TAKAHISA</creatorcontrib><creatorcontrib>KANEKO MASASHI</creatorcontrib><title>LINING METHOD OF BAGGED CONCRETE</title><description>PURPOSE: To accurately construct a lining body closely stuck to the ground in a simplified process in a lining method in which only the outer shell of a tunnel is excavated ahead of time and reduce the construction period and cost. CONSTITUTION: Underground is excavated by an excavating machine 30 and after a certain unit in length has been excavated, vacant bags having water permeability are arranged in the groove-shaped and circular ground void generated at the rear side of excavating machine 30 and concrete (or mortar) is placed in the bags with pressure to construct the bagged concrete 31 as a concrete lining body. The working tunnels 33 may be applied with the bagged lining bodies in the same way with the ring part 32. The bagged concrete right after placing may be more pressurized to closely stick to the ground and more dewatered. In this way, the ground is prevented from slacking, by the pressurizing process and the quality of the bagged concrete lining body is increased owing to the dewatering of unnecessary water. Because of the bagged concrete, it is prevented from flowing out and hence, soil and underground water are prevented from mixing therewith and the quality can be secured.</description><subject>EARTH DRILLING</subject><subject>FIXED CONSTRUCTIONS</subject><subject>GALLERIES</subject><subject>LARGE UNDERGROUND CHAMBERS</subject><subject>MINING</subject><subject>SHAFTS</subject><subject>TUNNELS</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>1996</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNrjZFDw8fTz9HNX8HUN8fB3UfB3U3BydHd3dVFw9vdzDnINceVhYE1LzClO5YXS3AyKbq4hzh66qQX58anFBYnJqXmpJfFeAR4GFsZGZiYWlo7GxKgBANoIId0</recordid><startdate>19961210</startdate><enddate>19961210</enddate><creator>CHOKAI SUMIO</creator><creator>NINOMIYA KOJI</creator><creator>HAMADA KAZUTO</creator><creator>ASAGAMI YUJI</creator><creator>OKU TOSHIAKI</creator><creator>SADATSUKA MASAYUKI</creator><creator>IDA TAKAHISA</creator><creator>KANEKO MASASHI</creator><scope>EVB</scope></search><sort><creationdate>19961210</creationdate><title>LINING METHOD OF BAGGED CONCRETE</title><author>CHOKAI SUMIO ; NINOMIYA KOJI ; HAMADA KAZUTO ; ASAGAMI YUJI ; OKU TOSHIAKI ; SADATSUKA MASAYUKI ; IDA TAKAHISA ; KANEKO MASASHI</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_JPH08326489A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>eng</language><creationdate>1996</creationdate><topic>EARTH DRILLING</topic><topic>FIXED CONSTRUCTIONS</topic><topic>GALLERIES</topic><topic>LARGE UNDERGROUND CHAMBERS</topic><topic>MINING</topic><topic>SHAFTS</topic><topic>TUNNELS</topic><toplevel>online_resources</toplevel><creatorcontrib>CHOKAI SUMIO</creatorcontrib><creatorcontrib>NINOMIYA KOJI</creatorcontrib><creatorcontrib>HAMADA KAZUTO</creatorcontrib><creatorcontrib>ASAGAMI YUJI</creatorcontrib><creatorcontrib>OKU TOSHIAKI</creatorcontrib><creatorcontrib>SADATSUKA MASAYUKI</creatorcontrib><creatorcontrib>IDA TAKAHISA</creatorcontrib><creatorcontrib>KANEKO MASASHI</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>CHOKAI SUMIO</au><au>NINOMIYA KOJI</au><au>HAMADA KAZUTO</au><au>ASAGAMI YUJI</au><au>OKU TOSHIAKI</au><au>SADATSUKA MASAYUKI</au><au>IDA TAKAHISA</au><au>KANEKO MASASHI</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>LINING METHOD OF BAGGED CONCRETE</title><date>1996-12-10</date><risdate>1996</risdate><abstract>PURPOSE: To accurately construct a lining body closely stuck to the ground in a simplified process in a lining method in which only the outer shell of a tunnel is excavated ahead of time and reduce the construction period and cost. CONSTITUTION: Underground is excavated by an excavating machine 30 and after a certain unit in length has been excavated, vacant bags having water permeability are arranged in the groove-shaped and circular ground void generated at the rear side of excavating machine 30 and concrete (or mortar) is placed in the bags with pressure to construct the bagged concrete 31 as a concrete lining body. The working tunnels 33 may be applied with the bagged lining bodies in the same way with the ring part 32. The bagged concrete right after placing may be more pressurized to closely stick to the ground and more dewatered. In this way, the ground is prevented from slacking, by the pressurizing process and the quality of the bagged concrete lining body is increased owing to the dewatering of unnecessary water. Because of the bagged concrete, it is prevented from flowing out and hence, soil and underground water are prevented from mixing therewith and the quality can be secured.</abstract><edition>6</edition><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language eng
recordid cdi_epo_espacenet_JPH08326489A
source esp@cenet
subjects EARTH DRILLING
FIXED CONSTRUCTIONS
GALLERIES
LARGE UNDERGROUND CHAMBERS
MINING
SHAFTS
TUNNELS
title LINING METHOD OF BAGGED CONCRETE
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-15T11%3A46%3A51IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=CHOKAI%20SUMIO&rft.date=1996-12-10&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3EJPH08326489A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true