POWER TRANSMISSION LINE WORK METHOD, POWER TRANSMISSION LINE EQUIPMENT AND POWER TRANSMISSION LINE WORK SUPPORT DEVICE, USING WEDGE-TYPE CLAMP
PROBLEM TO BE SOLVED: To provide a power transmission line work method, power transmission line equipment and power transmission line work support device, using wedge-type clamp, capable of preventing generation of power loss and noise even with a simple method and capable of sufficiently ensuring m...
Gespeichert in:
Hauptverfasser: | , |
---|---|
Format: | Patent |
Sprache: | eng ; jpn |
Schlagworte: | |
Online-Zugang: | Volltext bestellen |
Tags: |
Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
|
Zusammenfassung: | PROBLEM TO BE SOLVED: To provide a power transmission line work method, power transmission line equipment and power transmission line work support device, using wedge-type clamp, capable of preventing generation of power loss and noise even with a simple method and capable of sufficiently ensuring mechanical strength of electric lines.SOLUTION: Electric lines are clamped on both sides of a steel tower 12 using wedge-type clamps 24, 24 and a power transmission line 16 is anchored to the steel 12 under the power transmission line in a bent state between the wedge-type clamps 24, 24. By cutting short power transmission line 16 (tentative jumper line 74) between the wedge-type clamps 24, 24, a jumper line 76 with an excess line 78 removed is formed.SELECTED DRAWING: Figure 8
【課題】簡便な手法でありながら電力損失及びノイズの発生を防止可能であると共に、電線の機械的強度を十分に確保可能である、楔型クランプを用いた送電線工事方法、送電線設備、及び送電線工事支援装置を提供する。【解決手段】電線を鉄塔12の両側にて楔型クランプ24、24を用いて把持し、楔型クランプ24、24の間で撓ませた状態下にて送電線16を鉄塔12に引き留める。そして、楔型クランプ24、24の間にある送電線16(仮ジャンパ線74)を切り詰めることで、余剰線78が除去されたジャンパ線76を形成する。【選択図】図8 |
---|