CONSTRUCTION METHOD OF DOME ROOF

PROBLEM TO BE SOLVED: To shorten a construction period by providing a rotary bent support group in a fan shape between the central part of a dome roof and a tension ring, rotating the support group by a single block quantity, and repeating a process of assembling the roof on it. SOLUTION: A center b...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
1. Verfasser: KITANI SOICHI
Format: Patent
Sprache:eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
Beschreibung
Zusammenfassung:PROBLEM TO BE SOLVED: To shorten a construction period by providing a rotary bent support group in a fan shape between the central part of a dome roof and a tension ring, rotating the support group by a single block quantity, and repeating a process of assembling the roof on it. SOLUTION: A center bent support group 1 is provided on the ground so that the central part 2 of a steel frame dome roof is assembled on it. Next, a tension ring 3 is provided along an outer peripheral position of the roof so that a rotary bent support group 4 is provided in a fan shape between the central part 2 and the ring 3. Next, after assembling the steel frame dome roof 6 of two blocks in total a single block by a single block on the support groups 4 of two bodies, the support group 4 is rotated by a single block quantity (about 60 degrees) in the circumferential direction of a dome. After assembling a roof 6 of another one block further on the support group 4, the support group 4 is rotated by a single block quantity. After completing the steel frame dome roof by repeating a similar process, the support groups 1, 4 are dismantled and removed. Thus, a construction period can be shortened.