Method for operating a combined cycle power plant

In the case of a method for operating a combined cycle power plant (10), which has a gas turbine installation (11) and a water-steam cycle (21) which is connected to the gas turbine installation (11) by means of a waste heat steam generator (24) and has at least one steam turbine (23). The gas turbi...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: BROESAMLE, STEFAN, RUCHTI, CHRISTOPH
Format: Patent
Sprache:eng ; fre ; ger
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
Beschreibung
Zusammenfassung:In the case of a method for operating a combined cycle power plant (10), which has a gas turbine installation (11) and a water-steam cycle (21) which is connected to the gas turbine installation (11) by means of a waste heat steam generator (24) and has at least one steam turbine (23). The gas turbine installation (11) includes a compressor (13), a combustion chamber (14) and a turbine (16). To cool the turbine (16), air compressed at the compressor (13) is removed, is cooled in at least one cooler (18, 19) flowed through by water thus generating steam and is introduced into the turbine (16). At least with the gas turbine installation (11) running, prior to or during the start-up of the water-steam cycle (21), waste heat which is contained in the steam generated in the at least one cooler (18, 19), is used to good effect for pre-heating the installation inside the combined cycle power plant (10).