Construction method for muddy water large shield to pass through metro depot with low influence

The invention relates to the technical field of shield construction, in particular to a construction method for a large-muddy-water shield to pass through a metro depot with low influence. The construction method comprises the following steps that S1, the integrity and the settlement degree of a str...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: LI AN, WANG TAO, ZOU ZEZE, LI HONGBO, PENG TIANLE, DU WEI, WANG MENG, LI YUNXIAN, JIANG SHENGHUA, XU ZE, LI RAN, ZHU HONGWU, DENG XIFEI, YANG JIE, QU ZEJUN
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator LI AN
WANG TAO
ZOU ZEZE
LI HONGBO
PENG TIANLE
DU WEI
WANG MENG
LI YUNXIAN
JIANG SHENGHUA
XU ZE
LI RAN
ZHU HONGWU
DENG XIFEI
YANG JIE
QU ZEJUN
description The invention relates to the technical field of shield construction, in particular to a construction method for a large-muddy-water shield to pass through a metro depot with low influence. The construction method comprises the following steps that S1, the integrity and the settlement degree of a structure foundation are explored, and risk assessment of shield tunneling machine underneath pass construction is conducted; s2, reinforcing and repairing the structure foundation according to the evaluation result; s3, dividing a test section for underneath pass construction of the shield tunneling machine, collecting and analyzing parameters of settlement and structural stress change of a structure of the test section in the construction process, and determining a construction scheme of underneath pass construction of the shield tunneling machine according to an analysis result; s4, formal shield tunneling machine underneath pass construction is conducted according to the construction scheme of shield tunneling mac
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN118187893A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN118187893A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN118187893A3</originalsourceid><addsrcrecordid>eNqNy7EKwjAURuEuDqK-w-8DOIQO1lFCxcnJvYTktgmkuSW5ofj2KvgATmf5zrYZNKciuVoJnDCTeHYYOWOuzr2wGqGMaPJEKD5QdBDGYkqB-Mx18t8nMxwtLFiDeEReEdIYKyVL-2Yzmljo8OuuOd76p76fPn6gshhLiWTQD6U61Z27S3tt_zFvuRs9ZA</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Construction method for muddy water large shield to pass through metro depot with low influence</title><source>esp@cenet</source><creator>LI AN ; WANG TAO ; ZOU ZEZE ; LI HONGBO ; PENG TIANLE ; DU WEI ; WANG MENG ; LI YUNXIAN ; JIANG SHENGHUA ; XU ZE ; LI RAN ; ZHU HONGWU ; DENG XIFEI ; YANG JIE ; QU ZEJUN</creator><creatorcontrib>LI AN ; WANG TAO ; ZOU ZEZE ; LI HONGBO ; PENG TIANLE ; DU WEI ; WANG MENG ; LI YUNXIAN ; JIANG SHENGHUA ; XU ZE ; LI RAN ; ZHU HONGWU ; DENG XIFEI ; YANG JIE ; QU ZEJUN</creatorcontrib><description>The invention relates to the technical field of shield construction, in particular to a construction method for a large-muddy-water shield to pass through a metro depot with low influence. The construction method comprises the following steps that S1, the integrity and the settlement degree of a structure foundation are explored, and risk assessment of shield tunneling machine underneath pass construction is conducted; s2, reinforcing and repairing the structure foundation according to the evaluation result; s3, dividing a test section for underneath pass construction of the shield tunneling machine, collecting and analyzing parameters of settlement and structural stress change of a structure of the test section in the construction process, and determining a construction scheme of underneath pass construction of the shield tunneling machine according to an analysis result; s4, formal shield tunneling machine underneath pass construction is conducted according to the construction scheme of shield tunneling mac</description><language>chi ; eng</language><subject>EARTH DRILLING ; FIXED CONSTRUCTIONS ; GALLERIES ; LARGE UNDERGROUND CHAMBERS ; MINING ; SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, ORDRAINING IN OR OF MINES OR TUNNELS ; SHAFTS ; TUNNELS</subject><creationdate>2024</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20240614&amp;DB=EPODOC&amp;CC=CN&amp;NR=118187893A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,780,885,25564,76547</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20240614&amp;DB=EPODOC&amp;CC=CN&amp;NR=118187893A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>LI AN</creatorcontrib><creatorcontrib>WANG TAO</creatorcontrib><creatorcontrib>ZOU ZEZE</creatorcontrib><creatorcontrib>LI HONGBO</creatorcontrib><creatorcontrib>PENG TIANLE</creatorcontrib><creatorcontrib>DU WEI</creatorcontrib><creatorcontrib>WANG MENG</creatorcontrib><creatorcontrib>LI YUNXIAN</creatorcontrib><creatorcontrib>JIANG SHENGHUA</creatorcontrib><creatorcontrib>XU ZE</creatorcontrib><creatorcontrib>LI RAN</creatorcontrib><creatorcontrib>ZHU HONGWU</creatorcontrib><creatorcontrib>DENG XIFEI</creatorcontrib><creatorcontrib>YANG JIE</creatorcontrib><creatorcontrib>QU ZEJUN</creatorcontrib><title>Construction method for muddy water large shield to pass through metro depot with low influence</title><description>The invention relates to the technical field of shield construction, in particular to a construction method for a large-muddy-water shield to pass through a metro depot with low influence. The construction method comprises the following steps that S1, the integrity and the settlement degree of a structure foundation are explored, and risk assessment of shield tunneling machine underneath pass construction is conducted; s2, reinforcing and repairing the structure foundation according to the evaluation result; s3, dividing a test section for underneath pass construction of the shield tunneling machine, collecting and analyzing parameters of settlement and structural stress change of a structure of the test section in the construction process, and determining a construction scheme of underneath pass construction of the shield tunneling machine according to an analysis result; s4, formal shield tunneling machine underneath pass construction is conducted according to the construction scheme of shield tunneling mac</description><subject>EARTH DRILLING</subject><subject>FIXED CONSTRUCTIONS</subject><subject>GALLERIES</subject><subject>LARGE UNDERGROUND CHAMBERS</subject><subject>MINING</subject><subject>SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, ORDRAINING IN OR OF MINES OR TUNNELS</subject><subject>SHAFTS</subject><subject>TUNNELS</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2024</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNy7EKwjAURuEuDqK-w-8DOIQO1lFCxcnJvYTktgmkuSW5ofj2KvgATmf5zrYZNKciuVoJnDCTeHYYOWOuzr2wGqGMaPJEKD5QdBDGYkqB-Mx18t8nMxwtLFiDeEReEdIYKyVL-2Yzmljo8OuuOd76p76fPn6gshhLiWTQD6U61Z27S3tt_zFvuRs9ZA</recordid><startdate>20240614</startdate><enddate>20240614</enddate><creator>LI AN</creator><creator>WANG TAO</creator><creator>ZOU ZEZE</creator><creator>LI HONGBO</creator><creator>PENG TIANLE</creator><creator>DU WEI</creator><creator>WANG MENG</creator><creator>LI YUNXIAN</creator><creator>JIANG SHENGHUA</creator><creator>XU ZE</creator><creator>LI RAN</creator><creator>ZHU HONGWU</creator><creator>DENG XIFEI</creator><creator>YANG JIE</creator><creator>QU ZEJUN</creator><scope>EVB</scope></search><sort><creationdate>20240614</creationdate><title>Construction method for muddy water large shield to pass through metro depot with low influence</title><author>LI AN ; WANG TAO ; ZOU ZEZE ; LI HONGBO ; PENG TIANLE ; DU WEI ; WANG MENG ; LI YUNXIAN ; JIANG SHENGHUA ; XU ZE ; LI RAN ; ZHU HONGWU ; DENG XIFEI ; YANG JIE ; QU ZEJUN</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN118187893A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2024</creationdate><topic>EARTH DRILLING</topic><topic>FIXED CONSTRUCTIONS</topic><topic>GALLERIES</topic><topic>LARGE UNDERGROUND CHAMBERS</topic><topic>MINING</topic><topic>SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, ORDRAINING IN OR OF MINES OR TUNNELS</topic><topic>SHAFTS</topic><topic>TUNNELS</topic><toplevel>online_resources</toplevel><creatorcontrib>LI AN</creatorcontrib><creatorcontrib>WANG TAO</creatorcontrib><creatorcontrib>ZOU ZEZE</creatorcontrib><creatorcontrib>LI HONGBO</creatorcontrib><creatorcontrib>PENG TIANLE</creatorcontrib><creatorcontrib>DU WEI</creatorcontrib><creatorcontrib>WANG MENG</creatorcontrib><creatorcontrib>LI YUNXIAN</creatorcontrib><creatorcontrib>JIANG SHENGHUA</creatorcontrib><creatorcontrib>XU ZE</creatorcontrib><creatorcontrib>LI RAN</creatorcontrib><creatorcontrib>ZHU HONGWU</creatorcontrib><creatorcontrib>DENG XIFEI</creatorcontrib><creatorcontrib>YANG JIE</creatorcontrib><creatorcontrib>QU ZEJUN</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>LI AN</au><au>WANG TAO</au><au>ZOU ZEZE</au><au>LI HONGBO</au><au>PENG TIANLE</au><au>DU WEI</au><au>WANG MENG</au><au>LI YUNXIAN</au><au>JIANG SHENGHUA</au><au>XU ZE</au><au>LI RAN</au><au>ZHU HONGWU</au><au>DENG XIFEI</au><au>YANG JIE</au><au>QU ZEJUN</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Construction method for muddy water large shield to pass through metro depot with low influence</title><date>2024-06-14</date><risdate>2024</risdate><abstract>The invention relates to the technical field of shield construction, in particular to a construction method for a large-muddy-water shield to pass through a metro depot with low influence. The construction method comprises the following steps that S1, the integrity and the settlement degree of a structure foundation are explored, and risk assessment of shield tunneling machine underneath pass construction is conducted; s2, reinforcing and repairing the structure foundation according to the evaluation result; s3, dividing a test section for underneath pass construction of the shield tunneling machine, collecting and analyzing parameters of settlement and structural stress change of a structure of the test section in the construction process, and determining a construction scheme of underneath pass construction of the shield tunneling machine according to an analysis result; s4, formal shield tunneling machine underneath pass construction is conducted according to the construction scheme of shield tunneling mac</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN118187893A
source esp@cenet
subjects EARTH DRILLING
FIXED CONSTRUCTIONS
GALLERIES
LARGE UNDERGROUND CHAMBERS
MINING
SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, ORDRAINING IN OR OF MINES OR TUNNELS
SHAFTS
TUNNELS
title Construction method for muddy water large shield to pass through metro depot with low influence
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2024-12-27T13%3A10%3A23IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=LI%20AN&rft.date=2024-06-14&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN118187893A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true