Temporary pier elevation determination method for girder few-fulcrum erection method

The invention discloses a temporary pier elevation determination method for a girder few-fulcrum erection method, which comprises the following steps of: sequentially numbering each temporary pier as Nj along the girder erection direction, j = {1, 2, 3...}; according to the linear relation between t...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: ZHU JINZHU, HUANG GANLE, DONG JIAN, ZHENG JIANXIN, LI JIE, HUANG CAN, LIAO WANCHENG, ZHOU RENZHONG, HU QINXIA, XUE XIANKAI, LI YONGHUI, GAO HONGLEI, MU WENJUN, SUN NANCHANG, LYU XINRUI
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator ZHU JINZHU
HUANG GANLE
DONG JIAN
ZHENG JIANXIN
LI JIE
HUANG CAN
LIAO WANCHENG
ZHOU RENZHONG
HU QINXIA
XUE XIANKAI
LI YONGHUI
GAO HONGLEI
MU WENJUN
SUN NANCHANG
LYU XINRUI
description The invention discloses a temporary pier elevation determination method for a girder few-fulcrum erection method, which comprises the following steps of: sequentially numbering each temporary pier as Nj along the girder erection direction, j = {1, 2, 3...}; according to the linear relation between the deflection of the maximum cantilever state before the main beam is erected to the temporary pier Nj and the height of a pad needing to be arranged on the temporary pier Ni when the main beam is just erected on the temporary pier Nj, the total height delta hi of the pad of the temporary pier Ni when the main beam is just erected on the temporary pier Nj is calculated, and i = {1, 2, 3...} and ilt; j; and the delta hi and the beam bottom elevation f0 manufactured at the temporary piers Ni according to the line shape of the main beam are overlapped, and the elevation Hi of each temporary pier Ni when the temporary piers Nj are arranged on the main beam is obtained. According to the method, a reserved height empiric
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN116822289A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN116822289A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN116822289A3</originalsourceid><addsrcrecordid>eNqNyr0KwjAUhuEsDqLew_ECOjSC1LEUxckpewnJFw3kj9NU8e4VdHB0ennhWQqlEEtmzU8qHkwIuOvqcyKLCo4-fS6i3rIll5munu1bOjwaNwfDcyQwzA9bi4XTYcLm25XYno5qODcoecRUtEFCHYdL2-47KWV36Hf_mBcGrjmi</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Temporary pier elevation determination method for girder few-fulcrum erection method</title><source>esp@cenet</source><creator>ZHU JINZHU ; HUANG GANLE ; DONG JIAN ; ZHENG JIANXIN ; LI JIE ; HUANG CAN ; LIAO WANCHENG ; ZHOU RENZHONG ; HU QINXIA ; XUE XIANKAI ; LI YONGHUI ; GAO HONGLEI ; MU WENJUN ; SUN NANCHANG ; LYU XINRUI</creator><creatorcontrib>ZHU JINZHU ; HUANG GANLE ; DONG JIAN ; ZHENG JIANXIN ; LI JIE ; HUANG CAN ; LIAO WANCHENG ; ZHOU RENZHONG ; HU QINXIA ; XUE XIANKAI ; LI YONGHUI ; GAO HONGLEI ; MU WENJUN ; SUN NANCHANG ; LYU XINRUI</creatorcontrib><description>The invention discloses a temporary pier elevation determination method for a girder few-fulcrum erection method, which comprises the following steps of: sequentially numbering each temporary pier as Nj along the girder erection direction, j = {1, 2, 3...}; according to the linear relation between the deflection of the maximum cantilever state before the main beam is erected to the temporary pier Nj and the height of a pad needing to be arranged on the temporary pier Ni when the main beam is just erected on the temporary pier Nj, the total height delta hi of the pad of the temporary pier Ni when the main beam is just erected on the temporary pier Nj is calculated, and i = {1, 2, 3...} and ilt; j; and the delta hi and the beam bottom elevation f0 manufactured at the temporary piers Ni according to the line shape of the main beam are overlapped, and the elevation Hi of each temporary pier Ni when the temporary piers Nj are arranged on the main beam is obtained. According to the method, a reserved height empiric</description><language>chi ; eng</language><subject>ASSEMBLY OF BRIDGES ; CALCULATING ; COMPUTING ; CONSTRUCTION OF BRIDGES ; CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES ; COUNTING ; ELECTRIC DIGITAL DATA PROCESSING ; FIXED CONSTRUCTIONS ; OR VIADUCTS ; PHYSICS</subject><creationdate>2023</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20230929&amp;DB=EPODOC&amp;CC=CN&amp;NR=116822289A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,780,885,25564,76547</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20230929&amp;DB=EPODOC&amp;CC=CN&amp;NR=116822289A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>ZHU JINZHU</creatorcontrib><creatorcontrib>HUANG GANLE</creatorcontrib><creatorcontrib>DONG JIAN</creatorcontrib><creatorcontrib>ZHENG JIANXIN</creatorcontrib><creatorcontrib>LI JIE</creatorcontrib><creatorcontrib>HUANG CAN</creatorcontrib><creatorcontrib>LIAO WANCHENG</creatorcontrib><creatorcontrib>ZHOU RENZHONG</creatorcontrib><creatorcontrib>HU QINXIA</creatorcontrib><creatorcontrib>XUE XIANKAI</creatorcontrib><creatorcontrib>LI YONGHUI</creatorcontrib><creatorcontrib>GAO HONGLEI</creatorcontrib><creatorcontrib>MU WENJUN</creatorcontrib><creatorcontrib>SUN NANCHANG</creatorcontrib><creatorcontrib>LYU XINRUI</creatorcontrib><title>Temporary pier elevation determination method for girder few-fulcrum erection method</title><description>The invention discloses a temporary pier elevation determination method for a girder few-fulcrum erection method, which comprises the following steps of: sequentially numbering each temporary pier as Nj along the girder erection direction, j = {1, 2, 3...}; according to the linear relation between the deflection of the maximum cantilever state before the main beam is erected to the temporary pier Nj and the height of a pad needing to be arranged on the temporary pier Ni when the main beam is just erected on the temporary pier Nj, the total height delta hi of the pad of the temporary pier Ni when the main beam is just erected on the temporary pier Nj is calculated, and i = {1, 2, 3...} and ilt; j; and the delta hi and the beam bottom elevation f0 manufactured at the temporary piers Ni according to the line shape of the main beam are overlapped, and the elevation Hi of each temporary pier Ni when the temporary piers Nj are arranged on the main beam is obtained. According to the method, a reserved height empiric</description><subject>ASSEMBLY OF BRIDGES</subject><subject>CALCULATING</subject><subject>COMPUTING</subject><subject>CONSTRUCTION OF BRIDGES</subject><subject>CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES</subject><subject>COUNTING</subject><subject>ELECTRIC DIGITAL DATA PROCESSING</subject><subject>FIXED CONSTRUCTIONS</subject><subject>OR VIADUCTS</subject><subject>PHYSICS</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2023</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNyr0KwjAUhuEsDqLew_ECOjSC1LEUxckpewnJFw3kj9NU8e4VdHB0ennhWQqlEEtmzU8qHkwIuOvqcyKLCo4-fS6i3rIll5munu1bOjwaNwfDcyQwzA9bi4XTYcLm25XYno5qODcoecRUtEFCHYdL2-47KWV36Hf_mBcGrjmi</recordid><startdate>20230929</startdate><enddate>20230929</enddate><creator>ZHU JINZHU</creator><creator>HUANG GANLE</creator><creator>DONG JIAN</creator><creator>ZHENG JIANXIN</creator><creator>LI JIE</creator><creator>HUANG CAN</creator><creator>LIAO WANCHENG</creator><creator>ZHOU RENZHONG</creator><creator>HU QINXIA</creator><creator>XUE XIANKAI</creator><creator>LI YONGHUI</creator><creator>GAO HONGLEI</creator><creator>MU WENJUN</creator><creator>SUN NANCHANG</creator><creator>LYU XINRUI</creator><scope>EVB</scope></search><sort><creationdate>20230929</creationdate><title>Temporary pier elevation determination method for girder few-fulcrum erection method</title><author>ZHU JINZHU ; HUANG GANLE ; DONG JIAN ; ZHENG JIANXIN ; LI JIE ; HUANG CAN ; LIAO WANCHENG ; ZHOU RENZHONG ; HU QINXIA ; XUE XIANKAI ; LI YONGHUI ; GAO HONGLEI ; MU WENJUN ; SUN NANCHANG ; LYU XINRUI</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN116822289A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2023</creationdate><topic>ASSEMBLY OF BRIDGES</topic><topic>CALCULATING</topic><topic>COMPUTING</topic><topic>CONSTRUCTION OF BRIDGES</topic><topic>CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES</topic><topic>COUNTING</topic><topic>ELECTRIC DIGITAL DATA PROCESSING</topic><topic>FIXED CONSTRUCTIONS</topic><topic>OR VIADUCTS</topic><topic>PHYSICS</topic><toplevel>online_resources</toplevel><creatorcontrib>ZHU JINZHU</creatorcontrib><creatorcontrib>HUANG GANLE</creatorcontrib><creatorcontrib>DONG JIAN</creatorcontrib><creatorcontrib>ZHENG JIANXIN</creatorcontrib><creatorcontrib>LI JIE</creatorcontrib><creatorcontrib>HUANG CAN</creatorcontrib><creatorcontrib>LIAO WANCHENG</creatorcontrib><creatorcontrib>ZHOU RENZHONG</creatorcontrib><creatorcontrib>HU QINXIA</creatorcontrib><creatorcontrib>XUE XIANKAI</creatorcontrib><creatorcontrib>LI YONGHUI</creatorcontrib><creatorcontrib>GAO HONGLEI</creatorcontrib><creatorcontrib>MU WENJUN</creatorcontrib><creatorcontrib>SUN NANCHANG</creatorcontrib><creatorcontrib>LYU XINRUI</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>ZHU JINZHU</au><au>HUANG GANLE</au><au>DONG JIAN</au><au>ZHENG JIANXIN</au><au>LI JIE</au><au>HUANG CAN</au><au>LIAO WANCHENG</au><au>ZHOU RENZHONG</au><au>HU QINXIA</au><au>XUE XIANKAI</au><au>LI YONGHUI</au><au>GAO HONGLEI</au><au>MU WENJUN</au><au>SUN NANCHANG</au><au>LYU XINRUI</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Temporary pier elevation determination method for girder few-fulcrum erection method</title><date>2023-09-29</date><risdate>2023</risdate><abstract>The invention discloses a temporary pier elevation determination method for a girder few-fulcrum erection method, which comprises the following steps of: sequentially numbering each temporary pier as Nj along the girder erection direction, j = {1, 2, 3...}; according to the linear relation between the deflection of the maximum cantilever state before the main beam is erected to the temporary pier Nj and the height of a pad needing to be arranged on the temporary pier Ni when the main beam is just erected on the temporary pier Nj, the total height delta hi of the pad of the temporary pier Ni when the main beam is just erected on the temporary pier Nj is calculated, and i = {1, 2, 3...} and ilt; j; and the delta hi and the beam bottom elevation f0 manufactured at the temporary piers Ni according to the line shape of the main beam are overlapped, and the elevation Hi of each temporary pier Ni when the temporary piers Nj are arranged on the main beam is obtained. According to the method, a reserved height empiric</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN116822289A
source esp@cenet
subjects ASSEMBLY OF BRIDGES
CALCULATING
COMPUTING
CONSTRUCTION OF BRIDGES
CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
COUNTING
ELECTRIC DIGITAL DATA PROCESSING
FIXED CONSTRUCTIONS
OR VIADUCTS
PHYSICS
title Temporary pier elevation determination method for girder few-fulcrum erection method
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2024-12-24T04%3A21%3A47IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=ZHU%20JINZHU&rft.date=2023-09-29&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN116822289A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true