Process for early connection of near subway deep foundation pit main body structure and early disassembly of mid-partition wall

The invention discloses a near subway deep foundation pit main body structure early connection and mid-partition wall early removal process. The process comprises the steps that underground structure construction is conducted layer by layer in a foundation pit from bottom to top; when construction o...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: DUAN TAO, LI CHAO, GUO LEI, QING CHANGJIANG, ZHANG FENG, YANG ZUNLIN, JIN GUODONG, ZHANG KUN, XU YONG
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
Beschreibung
Zusammenfassung:The invention discloses a near subway deep foundation pit main body structure early connection and mid-partition wall early removal process. The process comprises the steps that underground structure construction is conducted layer by layer in a foundation pit from bottom to top; when construction of a foundation slab of the foundation pit is completed and the design strength is achieved, the middle partition wall of the underground structure of the bottommost layer is dismantled, a plurality of columns are reserved in the middle partition wall at the dismantled part at certain intervals, the middle partition wall below a construction trestle area is not dismantled, holing is conducted only at the position of a structural beam, and a support replacement belt is constructed; the beam plates of the middle partition wall cut-off areas of every two adjacent foundation pits are connected in a penetrating mode, structural beam penetrating is conducted on the middle partition wall areas which are not dismantled unde