Existing road transverse construction and road recovery method

The invention provides an existing road transverse construction and road recovery method which comprises the steps that hardening of an expanded area is completed, and meanwhile construction of a to-be-constructed area on one side of a non-expanded area is completed; the temporary municipal roads on...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: ZENG YINSHENG, LIN HAI, LIU YASONG, PAN GENGYI, SHI JINYAN, QIAN FUJIAN, QUAN YOUWEI, ZHOU WEI, NIU FENG
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator ZENG YINSHENG
LIN HAI
LIU YASONG
PAN GENGYI
SHI JINYAN
QIAN FUJIAN
QUAN YOUWEI
ZHOU WEI
NIU FENG
description The invention provides an existing road transverse construction and road recovery method which comprises the steps that hardening of an expanded area is completed, and meanwhile construction of a to-be-constructed area on one side of a non-expanded area is completed; the temporary municipal roads on the side far away from the expansion area are merged to the original municipal roads on the side close to the expansion area, the temporary municipal roads on the side close to the expansion area are merged to the expansion area, and construction of the original municipal road to-be-constructed area on the side far away from the expansion area is completed; the original municipal road away from one side of the expansion area is recovered, and construction of the to-be-constructed area of the original municipal road close to one side of the expansion area is completed; the original municipal road close to one side of the expansion area is recovered, the expansion area is dismantled, and follow-up construction is co
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN115162082A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN115162082A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN115162082A3</originalsourceid><addsrcrecordid>eNrjZLBzrcgsLsnMS1coyk9MUSgpSswrLkstKk5VSM7PKy4pKk0uyczPU0jMS4EoKEpNzgfKVyrkppZk5KfwMLCmJeYUp_JCaW4GRTfXEGcP3dSC_PjU4oLE5NS81JJ4Zz9DQ1NDMyMDCyNHY2LUAACq9DEr</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Existing road transverse construction and road recovery method</title><source>esp@cenet</source><creator>ZENG YINSHENG ; LIN HAI ; LIU YASONG ; PAN GENGYI ; SHI JINYAN ; QIAN FUJIAN ; QUAN YOUWEI ; ZHOU WEI ; NIU FENG</creator><creatorcontrib>ZENG YINSHENG ; LIN HAI ; LIU YASONG ; PAN GENGYI ; SHI JINYAN ; QIAN FUJIAN ; QUAN YOUWEI ; ZHOU WEI ; NIU FENG</creatorcontrib><description>The invention provides an existing road transverse construction and road recovery method which comprises the steps that hardening of an expanded area is completed, and meanwhile construction of a to-be-constructed area on one side of a non-expanded area is completed; the temporary municipal roads on the side far away from the expansion area are merged to the original municipal roads on the side close to the expansion area, the temporary municipal roads on the side close to the expansion area are merged to the expansion area, and construction of the original municipal road to-be-constructed area on the side far away from the expansion area is completed; the original municipal road away from one side of the expansion area is recovered, and construction of the to-be-constructed area of the original municipal road close to one side of the expansion area is completed; the original municipal road close to one side of the expansion area is recovered, the expansion area is dismantled, and follow-up construction is co</description><language>chi ; eng</language><subject>CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES ; CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, ORTHE LIKE ; FIXED CONSTRUCTIONS ; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR</subject><creationdate>2022</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20221011&amp;DB=EPODOC&amp;CC=CN&amp;NR=115162082A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,780,885,25564,76547</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20221011&amp;DB=EPODOC&amp;CC=CN&amp;NR=115162082A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>ZENG YINSHENG</creatorcontrib><creatorcontrib>LIN HAI</creatorcontrib><creatorcontrib>LIU YASONG</creatorcontrib><creatorcontrib>PAN GENGYI</creatorcontrib><creatorcontrib>SHI JINYAN</creatorcontrib><creatorcontrib>QIAN FUJIAN</creatorcontrib><creatorcontrib>QUAN YOUWEI</creatorcontrib><creatorcontrib>ZHOU WEI</creatorcontrib><creatorcontrib>NIU FENG</creatorcontrib><title>Existing road transverse construction and road recovery method</title><description>The invention provides an existing road transverse construction and road recovery method which comprises the steps that hardening of an expanded area is completed, and meanwhile construction of a to-be-constructed area on one side of a non-expanded area is completed; the temporary municipal roads on the side far away from the expansion area are merged to the original municipal roads on the side close to the expansion area, the temporary municipal roads on the side close to the expansion area are merged to the expansion area, and construction of the original municipal road to-be-constructed area on the side far away from the expansion area is completed; the original municipal road away from one side of the expansion area is recovered, and construction of the to-be-constructed area of the original municipal road close to one side of the expansion area is completed; the original municipal road close to one side of the expansion area is recovered, the expansion area is dismantled, and follow-up construction is co</description><subject>CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES</subject><subject>CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, ORTHE LIKE</subject><subject>FIXED CONSTRUCTIONS</subject><subject>MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2022</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNrjZLBzrcgsLsnMS1coyk9MUSgpSswrLkstKk5VSM7PKy4pKk0uyczPU0jMS4EoKEpNzgfKVyrkppZk5KfwMLCmJeYUp_JCaW4GRTfXEGcP3dSC_PjU4oLE5NS81JJ4Zz9DQ1NDMyMDCyNHY2LUAACq9DEr</recordid><startdate>20221011</startdate><enddate>20221011</enddate><creator>ZENG YINSHENG</creator><creator>LIN HAI</creator><creator>LIU YASONG</creator><creator>PAN GENGYI</creator><creator>SHI JINYAN</creator><creator>QIAN FUJIAN</creator><creator>QUAN YOUWEI</creator><creator>ZHOU WEI</creator><creator>NIU FENG</creator><scope>EVB</scope></search><sort><creationdate>20221011</creationdate><title>Existing road transverse construction and road recovery method</title><author>ZENG YINSHENG ; LIN HAI ; LIU YASONG ; PAN GENGYI ; SHI JINYAN ; QIAN FUJIAN ; QUAN YOUWEI ; ZHOU WEI ; NIU FENG</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN115162082A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2022</creationdate><topic>CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES</topic><topic>CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, ORTHE LIKE</topic><topic>FIXED CONSTRUCTIONS</topic><topic>MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR</topic><toplevel>online_resources</toplevel><creatorcontrib>ZENG YINSHENG</creatorcontrib><creatorcontrib>LIN HAI</creatorcontrib><creatorcontrib>LIU YASONG</creatorcontrib><creatorcontrib>PAN GENGYI</creatorcontrib><creatorcontrib>SHI JINYAN</creatorcontrib><creatorcontrib>QIAN FUJIAN</creatorcontrib><creatorcontrib>QUAN YOUWEI</creatorcontrib><creatorcontrib>ZHOU WEI</creatorcontrib><creatorcontrib>NIU FENG</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>ZENG YINSHENG</au><au>LIN HAI</au><au>LIU YASONG</au><au>PAN GENGYI</au><au>SHI JINYAN</au><au>QIAN FUJIAN</au><au>QUAN YOUWEI</au><au>ZHOU WEI</au><au>NIU FENG</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Existing road transverse construction and road recovery method</title><date>2022-10-11</date><risdate>2022</risdate><abstract>The invention provides an existing road transverse construction and road recovery method which comprises the steps that hardening of an expanded area is completed, and meanwhile construction of a to-be-constructed area on one side of a non-expanded area is completed; the temporary municipal roads on the side far away from the expansion area are merged to the original municipal roads on the side close to the expansion area, the temporary municipal roads on the side close to the expansion area are merged to the expansion area, and construction of the original municipal road to-be-constructed area on the side far away from the expansion area is completed; the original municipal road away from one side of the expansion area is recovered, and construction of the to-be-constructed area of the original municipal road close to one side of the expansion area is completed; the original municipal road close to one side of the expansion area is recovered, the expansion area is dismantled, and follow-up construction is co</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN115162082A
source esp@cenet
subjects CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, ORTHE LIKE
FIXED CONSTRUCTIONS
MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
title Existing road transverse construction and road recovery method
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2024-12-23T20%3A35%3A47IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=ZENG%20YINSHENG&rft.date=2022-10-11&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN115162082A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true