Strand pulling construction monitoring method for steel strand in corrugated pipe of prestressed structure

The invention provides a strand pulling construction monitoring method for a steel strand in a corrugated pipe of a prestressed structure. The method comprises the following steps: S1, arranging a wireless probe on the steel strand, and continuously detecting the contact part of the steel strand and...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: LIANG JIAWEI, TANG XIAOJUN, CHANG LIANG, LI YUANTAO, LIU SONGCHUN, CHENG WEI, DING ZHAOXI, SU YANYOU, ZHANG HAICHUN
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator LIANG JIAWEI
TANG XIAOJUN
CHANG LIANG
LI YUANTAO
LIU SONGCHUN
CHENG WEI
DING ZHAOXI
SU YANYOU
ZHANG HAICHUN
description The invention provides a strand pulling construction monitoring method for a steel strand in a corrugated pipe of a prestressed structure. The method comprises the following steps: S1, arranging a wireless probe on the steel strand, and continuously detecting the contact part of the steel strand and the corrugated pipe in the moving process by using the wireless probe; S2, placing the steel strand in a cable penetrating machine, and using the cable penetrating machine to stabilize the steel strand; S3, enabling that a central processing unit is in data connection with the cable penetrating machine, and the central processing unit is in data connection with the wireless probe; S4, driving the steel strand to penetrate through the corrugated pipe by using the cable penetrating machine, and reading detection data of the wireless probe in real time by using the central processing unit; and S5, according to the data detected by the wireless probe, adjusting the steel strand pulling speed of the cable penetrating m
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN113605249A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN113605249A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN113605249A3</originalsourceid><addsrcrecordid>eNqNjM0KwjAQhHPxIOo7rA8gWKuCRymKJy96LyHd1ki6Gzab9zf-PICXGZiZb6bmeVOx1EHMIXgawDEllezUM8HI5JXlnY-oD-6gZ4GkiKHoh_NUEJE8WMXy4iMC9xAFS48plex7lwXnZtLbkHDx85lZnk_35rLCyC2maB0Sattcq6rer3eb7eFY_7N5AVDJQmc</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Strand pulling construction monitoring method for steel strand in corrugated pipe of prestressed structure</title><source>esp@cenet</source><creator>LIANG JIAWEI ; TANG XIAOJUN ; CHANG LIANG ; LI YUANTAO ; LIU SONGCHUN ; CHENG WEI ; DING ZHAOXI ; SU YANYOU ; ZHANG HAICHUN</creator><creatorcontrib>LIANG JIAWEI ; TANG XIAOJUN ; CHANG LIANG ; LI YUANTAO ; LIU SONGCHUN ; CHENG WEI ; DING ZHAOXI ; SU YANYOU ; ZHANG HAICHUN</creatorcontrib><description>The invention provides a strand pulling construction monitoring method for a steel strand in a corrugated pipe of a prestressed structure. The method comprises the following steps: S1, arranging a wireless probe on the steel strand, and continuously detecting the contact part of the steel strand and the corrugated pipe in the moving process by using the wireless probe; S2, placing the steel strand in a cable penetrating machine, and using the cable penetrating machine to stabilize the steel strand; S3, enabling that a central processing unit is in data connection with the cable penetrating machine, and the central processing unit is in data connection with the wireless probe; S4, driving the steel strand to penetrate through the corrugated pipe by using the cable penetrating machine, and reading detection data of the wireless probe in real time by using the central processing unit; and S5, according to the data detected by the wireless probe, adjusting the steel strand pulling speed of the cable penetrating m</description><language>chi ; eng</language><subject>ASSEMBLY OF BRIDGES ; CONSTRUCTION OF BRIDGES ; CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES ; ELECTRIC COMMUNICATION TECHNIQUE ; ELECTRICITY ; FIXED CONSTRUCTIONS ; OR VIADUCTS ; PICTORIAL COMMUNICATION, e.g. TELEVISION</subject><creationdate>2021</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20211105&amp;DB=EPODOC&amp;CC=CN&amp;NR=113605249A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,776,881,25542,76289</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20211105&amp;DB=EPODOC&amp;CC=CN&amp;NR=113605249A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>LIANG JIAWEI</creatorcontrib><creatorcontrib>TANG XIAOJUN</creatorcontrib><creatorcontrib>CHANG LIANG</creatorcontrib><creatorcontrib>LI YUANTAO</creatorcontrib><creatorcontrib>LIU SONGCHUN</creatorcontrib><creatorcontrib>CHENG WEI</creatorcontrib><creatorcontrib>DING ZHAOXI</creatorcontrib><creatorcontrib>SU YANYOU</creatorcontrib><creatorcontrib>ZHANG HAICHUN</creatorcontrib><title>Strand pulling construction monitoring method for steel strand in corrugated pipe of prestressed structure</title><description>The invention provides a strand pulling construction monitoring method for a steel strand in a corrugated pipe of a prestressed structure. The method comprises the following steps: S1, arranging a wireless probe on the steel strand, and continuously detecting the contact part of the steel strand and the corrugated pipe in the moving process by using the wireless probe; S2, placing the steel strand in a cable penetrating machine, and using the cable penetrating machine to stabilize the steel strand; S3, enabling that a central processing unit is in data connection with the cable penetrating machine, and the central processing unit is in data connection with the wireless probe; S4, driving the steel strand to penetrate through the corrugated pipe by using the cable penetrating machine, and reading detection data of the wireless probe in real time by using the central processing unit; and S5, according to the data detected by the wireless probe, adjusting the steel strand pulling speed of the cable penetrating m</description><subject>ASSEMBLY OF BRIDGES</subject><subject>CONSTRUCTION OF BRIDGES</subject><subject>CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES</subject><subject>ELECTRIC COMMUNICATION TECHNIQUE</subject><subject>ELECTRICITY</subject><subject>FIXED CONSTRUCTIONS</subject><subject>OR VIADUCTS</subject><subject>PICTORIAL COMMUNICATION, e.g. TELEVISION</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2021</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNjM0KwjAQhHPxIOo7rA8gWKuCRymKJy96LyHd1ki6Gzab9zf-PICXGZiZb6bmeVOx1EHMIXgawDEllezUM8HI5JXlnY-oD-6gZ4GkiKHoh_NUEJE8WMXy4iMC9xAFS48plex7lwXnZtLbkHDx85lZnk_35rLCyC2maB0Sattcq6rer3eb7eFY_7N5AVDJQmc</recordid><startdate>20211105</startdate><enddate>20211105</enddate><creator>LIANG JIAWEI</creator><creator>TANG XIAOJUN</creator><creator>CHANG LIANG</creator><creator>LI YUANTAO</creator><creator>LIU SONGCHUN</creator><creator>CHENG WEI</creator><creator>DING ZHAOXI</creator><creator>SU YANYOU</creator><creator>ZHANG HAICHUN</creator><scope>EVB</scope></search><sort><creationdate>20211105</creationdate><title>Strand pulling construction monitoring method for steel strand in corrugated pipe of prestressed structure</title><author>LIANG JIAWEI ; TANG XIAOJUN ; CHANG LIANG ; LI YUANTAO ; LIU SONGCHUN ; CHENG WEI ; DING ZHAOXI ; SU YANYOU ; ZHANG HAICHUN</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN113605249A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2021</creationdate><topic>ASSEMBLY OF BRIDGES</topic><topic>CONSTRUCTION OF BRIDGES</topic><topic>CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES</topic><topic>ELECTRIC COMMUNICATION TECHNIQUE</topic><topic>ELECTRICITY</topic><topic>FIXED CONSTRUCTIONS</topic><topic>OR VIADUCTS</topic><topic>PICTORIAL COMMUNICATION, e.g. TELEVISION</topic><toplevel>online_resources</toplevel><creatorcontrib>LIANG JIAWEI</creatorcontrib><creatorcontrib>TANG XIAOJUN</creatorcontrib><creatorcontrib>CHANG LIANG</creatorcontrib><creatorcontrib>LI YUANTAO</creatorcontrib><creatorcontrib>LIU SONGCHUN</creatorcontrib><creatorcontrib>CHENG WEI</creatorcontrib><creatorcontrib>DING ZHAOXI</creatorcontrib><creatorcontrib>SU YANYOU</creatorcontrib><creatorcontrib>ZHANG HAICHUN</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>LIANG JIAWEI</au><au>TANG XIAOJUN</au><au>CHANG LIANG</au><au>LI YUANTAO</au><au>LIU SONGCHUN</au><au>CHENG WEI</au><au>DING ZHAOXI</au><au>SU YANYOU</au><au>ZHANG HAICHUN</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Strand pulling construction monitoring method for steel strand in corrugated pipe of prestressed structure</title><date>2021-11-05</date><risdate>2021</risdate><abstract>The invention provides a strand pulling construction monitoring method for a steel strand in a corrugated pipe of a prestressed structure. The method comprises the following steps: S1, arranging a wireless probe on the steel strand, and continuously detecting the contact part of the steel strand and the corrugated pipe in the moving process by using the wireless probe; S2, placing the steel strand in a cable penetrating machine, and using the cable penetrating machine to stabilize the steel strand; S3, enabling that a central processing unit is in data connection with the cable penetrating machine, and the central processing unit is in data connection with the wireless probe; S4, driving the steel strand to penetrate through the corrugated pipe by using the cable penetrating machine, and reading detection data of the wireless probe in real time by using the central processing unit; and S5, according to the data detected by the wireless probe, adjusting the steel strand pulling speed of the cable penetrating m</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN113605249A
source esp@cenet
subjects ASSEMBLY OF BRIDGES
CONSTRUCTION OF BRIDGES
CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
ELECTRIC COMMUNICATION TECHNIQUE
ELECTRICITY
FIXED CONSTRUCTIONS
OR VIADUCTS
PICTORIAL COMMUNICATION, e.g. TELEVISION
title Strand pulling construction monitoring method for steel strand in corrugated pipe of prestressed structure
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-02-12T18%3A27%3A01IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=LIANG%20JIAWEI&rft.date=2021-11-05&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN113605249A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true