Tunneling construction method for super-large-section reloading chamber
The invention discloses a tunneling construction method for a super-large-section reloading chamber. The method adopts a roadheader for tunneling construction, and specifically comprises the followingsteps that (1) a chamber external measure roadway is constructed from a shaft bottom passenger stati...
Gespeichert in:
Hauptverfasser: | , , , , , , , , , , , , |
---|---|
Format: | Patent |
Sprache: | chi ; eng |
Schlagworte: | |
Online-Zugang: | Volltext bestellen |
Tags: |
Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
|
Zusammenfassung: | The invention discloses a tunneling construction method for a super-large-section reloading chamber. The method adopts a roadheader for tunneling construction, and specifically comprises the followingsteps that (1) a chamber external measure roadway is constructed from a shaft bottom passenger station to reach the central position of the top arch of the reloading chamber; (2) first-layer tunneling pilot tunnel construction is performed from the central position of the top arch of the reloading chamber to form a semicircular arch top plate; (3) a thin spray material is sprayed on an anchor netarranged on the semicircular arch top plate for reinforcement; (4) a ventilation ramp communicated with the exit of the reloading chamber is formed by tunneling in the reloading chamber to achieve full-air-pressure ventilation; and (5) tunneling construction is performed downwards through a step layering method to finally reach a designed bottom plate height to complete reloading chamber construction. The method has the a |
---|