Construction method for forming reclamation land area

The invention discloses a construction method for forming a reclamation land area. The construction method is used for construction in a shallow dike area, and the shallow dike area is divided into afirst hydraulic reclamation area, a second hydraulic reclamation area and a third hydraulic reclamati...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: GUO SUMING, JIANG GUIXIANG, BU FANBO, HU KEJIE, ZHANG LUFENG, LI DENGHAI, JIANG XIWEN, LIU TAO, JIANG YI, YE SHUNBO
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator GUO SUMING
JIANG GUIXIANG
BU FANBO
HU KEJIE
ZHANG LUFENG
LI DENGHAI
JIANG XIWEN
LIU TAO
JIANG YI
YE SHUNBO
description The invention discloses a construction method for forming a reclamation land area. The construction method is used for construction in a shallow dike area, and the shallow dike area is divided into afirst hydraulic reclamation area, a second hydraulic reclamation area and a third hydraulic reclamation area; a water storage lake is arranged between the first hydraulic reclamation area and the second hydraulic reclamation area; and the third hydraulic reclamation area is closely adjacent to the second hydraulic reclamation area. The construction method for the reclamation land area includes theconstruction stage of hydraulic reclamation of mud for the first hydraulic reclamation area and the water storage lake and the construction stage of hydraulic reclamation of sand for the second hydraulic reclamation area and the third hydraulic reclamation area; the construction stage of hydraulic reclamation of the mud comprises the step that two cutter suction dredgers are selected for cutter suction dredging and mud hy
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN109083099A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN109083099A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN109083099A3</originalsourceid><addsrcrecordid>eNrjZDB1zs8rLikqTS7JzM9TyE0tychPUUjLLwLh3My8dIWi1OScxNxEsHROYl6KQmJRaiIPA2taYk5xKi-U5mZQdHMNcfbQTS3Ij08tLkhMTs1LLYl39jM0sDSwMDawtHQ0JkYNAI66LXY</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Construction method for forming reclamation land area</title><source>esp@cenet</source><creator>GUO SUMING ; JIANG GUIXIANG ; BU FANBO ; HU KEJIE ; ZHANG LUFENG ; LI DENGHAI ; JIANG XIWEN ; LIU TAO ; JIANG YI ; YE SHUNBO</creator><creatorcontrib>GUO SUMING ; JIANG GUIXIANG ; BU FANBO ; HU KEJIE ; ZHANG LUFENG ; LI DENGHAI ; JIANG XIWEN ; LIU TAO ; JIANG YI ; YE SHUNBO</creatorcontrib><description>The invention discloses a construction method for forming a reclamation land area. The construction method is used for construction in a shallow dike area, and the shallow dike area is divided into afirst hydraulic reclamation area, a second hydraulic reclamation area and a third hydraulic reclamation area; a water storage lake is arranged between the first hydraulic reclamation area and the second hydraulic reclamation area; and the third hydraulic reclamation area is closely adjacent to the second hydraulic reclamation area. The construction method for the reclamation land area includes theconstruction stage of hydraulic reclamation of mud for the first hydraulic reclamation area and the water storage lake and the construction stage of hydraulic reclamation of sand for the second hydraulic reclamation area and the third hydraulic reclamation area; the construction stage of hydraulic reclamation of the mud comprises the step that two cutter suction dredgers are selected for cutter suction dredging and mud hy</description><language>chi ; eng</language><subject>FIXED CONSTRUCTIONS ; FOUNDATIONS ; HYDRAULIC ENGINEERING ; SOIL SHIFTING</subject><creationdate>2018</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20181225&amp;DB=EPODOC&amp;CC=CN&amp;NR=109083099A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,780,885,25564,76547</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20181225&amp;DB=EPODOC&amp;CC=CN&amp;NR=109083099A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>GUO SUMING</creatorcontrib><creatorcontrib>JIANG GUIXIANG</creatorcontrib><creatorcontrib>BU FANBO</creatorcontrib><creatorcontrib>HU KEJIE</creatorcontrib><creatorcontrib>ZHANG LUFENG</creatorcontrib><creatorcontrib>LI DENGHAI</creatorcontrib><creatorcontrib>JIANG XIWEN</creatorcontrib><creatorcontrib>LIU TAO</creatorcontrib><creatorcontrib>JIANG YI</creatorcontrib><creatorcontrib>YE SHUNBO</creatorcontrib><title>Construction method for forming reclamation land area</title><description>The invention discloses a construction method for forming a reclamation land area. The construction method is used for construction in a shallow dike area, and the shallow dike area is divided into afirst hydraulic reclamation area, a second hydraulic reclamation area and a third hydraulic reclamation area; a water storage lake is arranged between the first hydraulic reclamation area and the second hydraulic reclamation area; and the third hydraulic reclamation area is closely adjacent to the second hydraulic reclamation area. The construction method for the reclamation land area includes theconstruction stage of hydraulic reclamation of mud for the first hydraulic reclamation area and the water storage lake and the construction stage of hydraulic reclamation of sand for the second hydraulic reclamation area and the third hydraulic reclamation area; the construction stage of hydraulic reclamation of the mud comprises the step that two cutter suction dredgers are selected for cutter suction dredging and mud hy</description><subject>FIXED CONSTRUCTIONS</subject><subject>FOUNDATIONS</subject><subject>HYDRAULIC ENGINEERING</subject><subject>SOIL SHIFTING</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2018</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNrjZDB1zs8rLikqTS7JzM9TyE0tychPUUjLLwLh3My8dIWi1OScxNxEsHROYl6KQmJRaiIPA2taYk5xKi-U5mZQdHMNcfbQTS3Ij08tLkhMTs1LLYl39jM0sDSwMDawtHQ0JkYNAI66LXY</recordid><startdate>20181225</startdate><enddate>20181225</enddate><creator>GUO SUMING</creator><creator>JIANG GUIXIANG</creator><creator>BU FANBO</creator><creator>HU KEJIE</creator><creator>ZHANG LUFENG</creator><creator>LI DENGHAI</creator><creator>JIANG XIWEN</creator><creator>LIU TAO</creator><creator>JIANG YI</creator><creator>YE SHUNBO</creator><scope>EVB</scope></search><sort><creationdate>20181225</creationdate><title>Construction method for forming reclamation land area</title><author>GUO SUMING ; JIANG GUIXIANG ; BU FANBO ; HU KEJIE ; ZHANG LUFENG ; LI DENGHAI ; JIANG XIWEN ; LIU TAO ; JIANG YI ; YE SHUNBO</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN109083099A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2018</creationdate><topic>FIXED CONSTRUCTIONS</topic><topic>FOUNDATIONS</topic><topic>HYDRAULIC ENGINEERING</topic><topic>SOIL SHIFTING</topic><toplevel>online_resources</toplevel><creatorcontrib>GUO SUMING</creatorcontrib><creatorcontrib>JIANG GUIXIANG</creatorcontrib><creatorcontrib>BU FANBO</creatorcontrib><creatorcontrib>HU KEJIE</creatorcontrib><creatorcontrib>ZHANG LUFENG</creatorcontrib><creatorcontrib>LI DENGHAI</creatorcontrib><creatorcontrib>JIANG XIWEN</creatorcontrib><creatorcontrib>LIU TAO</creatorcontrib><creatorcontrib>JIANG YI</creatorcontrib><creatorcontrib>YE SHUNBO</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>GUO SUMING</au><au>JIANG GUIXIANG</au><au>BU FANBO</au><au>HU KEJIE</au><au>ZHANG LUFENG</au><au>LI DENGHAI</au><au>JIANG XIWEN</au><au>LIU TAO</au><au>JIANG YI</au><au>YE SHUNBO</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Construction method for forming reclamation land area</title><date>2018-12-25</date><risdate>2018</risdate><abstract>The invention discloses a construction method for forming a reclamation land area. The construction method is used for construction in a shallow dike area, and the shallow dike area is divided into afirst hydraulic reclamation area, a second hydraulic reclamation area and a third hydraulic reclamation area; a water storage lake is arranged between the first hydraulic reclamation area and the second hydraulic reclamation area; and the third hydraulic reclamation area is closely adjacent to the second hydraulic reclamation area. The construction method for the reclamation land area includes theconstruction stage of hydraulic reclamation of mud for the first hydraulic reclamation area and the water storage lake and the construction stage of hydraulic reclamation of sand for the second hydraulic reclamation area and the third hydraulic reclamation area; the construction stage of hydraulic reclamation of the mud comprises the step that two cutter suction dredgers are selected for cutter suction dredging and mud hy</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN109083099A
source esp@cenet
subjects FIXED CONSTRUCTIONS
FOUNDATIONS
HYDRAULIC ENGINEERING
SOIL SHIFTING
title Construction method for forming reclamation land area
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-06T07%3A25%3A36IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=GUO%20SUMING&rft.date=2018-12-25&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN109083099A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true