Steel bar implanting construction method of manual hole digging pile in quicksand layer
The invention provides a steel bar implanting construction method of a manual hole digging pile in a quicksand layer. The steel bar implanting construction method comprises the following steps of: in the event of digging to the upper part of the quicksand layer close to the quicksand layer, implanti...
Gespeichert in:
Hauptverfasser: | , , , , |
---|---|
Format: | Patent |
Sprache: | chi ; eng |
Schlagworte: | |
Online-Zugang: | Volltext bestellen |
Tags: |
Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
|
Zusammenfassung: | The invention provides a steel bar implanting construction method of a manual hole digging pile in a quicksand layer. The steel bar implanting construction method comprises the following steps of: in the event of digging to the upper part of the quicksand layer close to the quicksand layer, implanting a layer of anchor bars with a certain length into the quicksand layer around the inner wall of a pile hole so as to reinforce the quicksand layer along the bottom angle of a current digging line firstly, pouring a protective wall at the upper layer of the quicksand layer, and pouring the upper ends of the anchor bars in the protective wall in the event of pouring; then, downwardly digging the quicksand layer, implanting a second layer of anchor bars into the quicksand layer and pouring the protective wall after digging at a certain depth, and circularly constructing in such a manner till passing through the quicksand layer. According to the invention, normal and safe hole digging operations of pile foundations i |
---|