Predicting the critical path changes using sensitivity analysis: a delay analysis approach

PurposeThis research presents a framework that allows project managers to predict the next critical paths (CP(s)) and to take extra care when planning and executing those activities that have the potential to cause changes in a project's current CP(s).Design/methodology/approachThe method prese...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Veröffentlicht in:International journal of managing projects in business 2020-08, Vol.13 (5), p.1097-1119
Hauptverfasser: Hammad, Mohammed, Abbasi, Alireza, Chakrabortty, Ripon K, Ryan, Michael J
Format: Artikel
Sprache:eng
Schlagworte:
Online-Zugang:Volltext
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
Beschreibung
Zusammenfassung:PurposeThis research presents a framework that allows project managers to predict the next critical paths (CP(s)) and to take extra care when planning and executing those activities that have the potential to cause changes in a project's current CP(s).Design/methodology/approachThe method presented here is based on an assessment of each activity's contribution to the overall schedule variance, which involves assigning a probability distribution function to each activity duration in the project. A sensitivity analysis is also carried out, which forms the basis of identifying which activity most affects the project completion date and therefore will have the greatest effect in changing the CP.FindingsThe authors’ analysis reveals that the most appropriate probability density function (PDF) for the targeted project is the normal distribution. However, the aim of this work is not to determine the most suitable distribution for each activity but rather to study the effect of the activity distribution type on the CP prediction. The results show that the selection of the appropriate probability distribution is very important, since it can impact the CP prediction and estimated project completion date.Originality/valueThis research work proposes a delay analysis scheme which can help the project manager to predict the next CP and to improve performance by identifying which activity is the bottleneck. On the other hand, the simplicity arises from the fact that this method does not require any expensive machines or software to generate results.
ISSN:1753-8378
1753-8386
DOI:10.1108/IJMPB-07-2019-0184