Cruise Report, KNORR 5, June-July 1970

KNOOR 5 carried out mooring work from 26 June to 10 July, 1970. Five moorings were set and seven recovered at Sites D (39 degrees 00 N., 70 degrees 00' W.), L (34 degrees 00' N., 70 degrees 00' W.), and the Gulf Stream. Additional work included hydro stations, BT's, CTD's an...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
1. Verfasser: Heinmiller,R
Format: Report
Sprache:eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
Beschreibung
Zusammenfassung:KNOOR 5 carried out mooring work from 26 June to 10 July, 1970. Five moorings were set and seven recovered at Sites D (39 degrees 00 N., 70 degrees 00' W.), L (34 degrees 00' N., 70 degrees 00' W.), and the Gulf Stream. Additional work included hydro stations, BT's, CTD's and acoustic work. (Author)