Developing computer-based schedule delay analysis methods based on information flow analysis: a case study

Schedule analysts often resolve diverse schedule delay problems in construction projects based on their subjective experiences. Although various process-based and mathematical-model schedule delay analysis methods are available for effective schedule delay analysis, these methods require time-consum...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Veröffentlicht in:Journal of civil engineering and management 2013-12, Vol.19 (6), p.823-835
Hauptverfasser: Tsai, Ming-Kuan, Yang, Jyh-Bin, Yau, Nie-Jia
Format: Artikel
Sprache:eng
Schlagworte:
Online-Zugang:Volltext
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
Beschreibung
Zusammenfassung:Schedule analysts often resolve diverse schedule delay problems in construction projects based on their subjective experiences. Although various process-based and mathematical-model schedule delay analysis methods are available for effective schedule delay analysis, these methods require time-consuming manual operation. The use of computer-based schedule delay analysis methods seems to be a solution. However, schedule analysts still have difficulty developing computer-based schedule delay analysis methods. Therefore, this study applies information flow analysis to classify the necessary work to develop computer-based schedule delay analysis methods. In contrast to numerous studies that focus only on computerizing a process-based or a mathematical-model schedule delay analysis method, this study constructs a computer-based method that integrates two process-based schedule delay analysis methods simultaneously. In a tested case study, the delay liability for the project owner and contractor was classified successfully. Importantly, this study provides a useful reference for similar applications in project management.
ISSN:1392-3730
1822-3605
DOI:10.3846/13923730.2013.801901