Test Methods for Validating Inductive Transformer Performance during Cable Discharge: Main Principles, Parameters and Testing Procedures

High voltage connections will discharge through inductive voltage and combined transformers when they are switched off. In the past, there was a wide margin between the required capabilities and the actual capabilities of these components. Nowadays, however, this aspect is becoming more prominent du...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Veröffentlicht in:Energies (Basel) 2024-02, Vol.17 (4), p.799
Hauptverfasser: Grđan, Andrea, Žiger, Igor, Hanić, Zlatko, Tannemaat, Imre, Huth, Ralf, Novko, Ivan
Format: Artikel
Sprache:eng
Schlagworte:
Online-Zugang:Volltext
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
Beschreibung
Zusammenfassung:High voltage connections will discharge through inductive voltage and combined transformers when they are switched off. In the past, there was a wide margin between the required capabilities and the actual capabilities of these components. Nowadays, however, this aspect is becoming more prominent due to a higher penetration by cable systems into the grid. Currently, none of the relevant international standards contain any definitions or requirements for line discharge, nor test methods which would validate the ability of the transformer to discharge a line of certain capacitance at a certain voltage. This is why the aim of this paper is to provide a foundation for how to specify, assess and verify the capacitive discharge performance of instrument transformers. This paper will present the basic theory, influencing parameters, multiple test sequences and acceptance criteria for cable discharge. It is clear that capacitive discharges present both thermal and mechanical stress to the unit, which is why this paper will detail how to guarantee both aspects. The idea is that this paper serves as a literal blueprint which can then be transferred to the relevant clauses in upcoming international standards. All conclusions within this paper are achieved through calculations and testing on actual 123 kV inductive voltage transformers and combined units.
ISSN:1996-1073
1996-1073
DOI:10.3390/en17040799