Estimating Building Construction Costs by Production Processes
Building actors need accurate estimates in order to efficiently undertake the construction of buildings. The knowledge of real expected costs of construction works is a necessary condition for contractors to submit competitive tenders and for developers to be aware of the magnitude of their investme...
Gespeichert in:
Veröffentlicht in: | The open construction & building technology journal 2014, Vol.8 (1), p.171-181 |
---|---|
Hauptverfasser: | , , |
Format: | Artikel |
Sprache: | eng |
Online-Zugang: | Volltext |
Tags: |
Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
|
Zusammenfassung: | Building actors need accurate estimates in order to efficiently undertake the construction of buildings. The
knowledge of real expected costs of construction works is a necessary condition for contractors to submit competitive tenders
and for developers to be aware of the magnitude of their investment. In this paper, an innovative process-based model
is presented, the POP model. This model aims at providing building actors with a systematized methodology to calculate
building construction costs based on the planning, organization and scheduling of the expected works. Unlike the model
of construction work units, the most widespread estimate model in Spain, the POP model comprises all construction costs
in a direct way by identifying the production processes involved and the resources consumed, giving a new approach to
the principles of the activity-based costing methodology in tune with the process-based cost models that are emerging in
the international scene. Nowadays, the model is being applied in real construction works with satisfactory results of transparency,
detail and adaptability. Not only reliable estimates are obtained, but also the performance of works is devised, allowing
its optimization and control. |
---|---|