Identifying risks and mitigation strategies in private sector participation (PSP) in power generation projects in Ghana
Purpose The purpose of this paper is to identify the risks associated with private sector participation (PSP) in power generation (PG) projects, how they were allocated and the strategies used to mitigate their likely adverse effects. Design/methodology/approach The paper adopts case study research...
Gespeichert in:
Veröffentlicht in: | Journal of facilities management 2017-05, Vol.15 (2), p.153-169 |
---|---|
Hauptverfasser: | , |
Format: | Artikel |
Sprache: | eng |
Schlagworte: | |
Online-Zugang: | Volltext |
Tags: |
Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
|
Zusammenfassung: | Purpose
The purpose of this paper is to identify the risks associated with private sector participation (PSP) in power generation (PG) projects, how they were allocated and the strategies used to mitigate their likely adverse effects.
Design/methodology/approach
The paper adopts case study research method and cross-case analyses to unearth the key risks and the contractual instruments used to manage them.
Findings
The paper identified 30 risk factors associated with four major private sector PG projects in Ghana. The allocation and mitigation strategies of these risks are also reported.
Originality/value
This is the first study to create a risk register of PSP PG projects. Private investors and government have been provided with a comprehensive list of risks associated with PG infrastructure. Would-be investors have also been armed with some potential risk management strategies for proper project structuring. |
---|---|
ISSN: | 1472-5967 1741-0983 |
DOI: | 10.1108/JFM-07-2016-0030 |