Activity delay patterns in project networks

Delays in activities completion drive human projects to schedule and cost overruns. It is believed activity delays are the consequence of multiple idiosyncrasies without specific patterns or rules. Here we show that is not the case. Using data for 180 construction project schedules, we demonstrate t...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Veröffentlicht in:arXiv.org 2024-02
Hauptverfasser: Vazquez, Alexei, Marasinou, Chrysostomos, Kalogridis, Georgios, Ellinas, Christos
Format: Artikel
Sprache:eng
Schlagworte:
Online-Zugang:Volltext
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
Beschreibung
Zusammenfassung:Delays in activities completion drive human projects to schedule and cost overruns. It is believed activity delays are the consequence of multiple idiosyncrasies without specific patterns or rules. Here we show that is not the case. Using data for 180 construction project schedules, we demonstrate that activity delays satisfy a universal model that we call the law of activity delays. After we correct for delay risk factors, what remains follows a log-normal distribution.
ISSN:2331-8422
DOI:10.48550/arxiv.2304.10304