Identification of T – pier construction work activities on the elevated railway project to develop work breakdown structure

The development of elevated railway infrastructures in Indonesia is going rapidly. The uniqueness of the T-Pier construction in the elevated railway project is the construction method that causes many activities to execute. The explained activities in the construction method were not clear, neither...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: Saputra, Pungky Dharma, Suhandi, Luxpetrus Agustian, Purwanti, Nina, Fansuri, Muhammad Hamzah, Laksmi, Anasya Arsita
Format: Tagungsbericht
Sprache:eng
Schlagworte:
Online-Zugang:Volltext
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue 1
container_start_page
container_title
container_volume 2877
creator Saputra, Pungky Dharma
Suhandi, Luxpetrus Agustian
Purwanti, Nina
Fansuri, Muhammad Hamzah
Laksmi, Anasya Arsita
description The development of elevated railway infrastructures in Indonesia is going rapidly. The uniqueness of the T-Pier construction in the elevated railway project is the construction method that causes many activities to execute. The explained activities in the construction method were not clear, neither treated in much detail. In line with the problem, this research aim is to identify T-Piers construction work activities specifically. The project sample was MRT Jakarta CP 103 elevated section and T-Pier construction was the object of the case study. The first stage of this research was archive analysis, expert validation, and surveying of 100 bridge engineers. The collected data were analyzed by the descriptive analysis method. Then the work breakdown structure tree diagram was developed and shown the activities development. There were 31 activities identified starting from preparation until finishing and grouped into the main section group of activities i.e. pile cap, pier column, installation, and dismantling of temporary shoring, and pier head group activities. All the experts agreed that the activities identified were valid and almost all respondents 100% agree. The activities identified were at level 5 in the work breakdown structure development. The detailed activities can be standardized as a reference in future similar projects.
doi_str_mv 10.1063/5.0179948
format Conference Proceeding
fullrecord <record><control><sourceid>proquest_scita</sourceid><recordid>TN_cdi_scitation_primary_10_1063_5_0179948</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>2902132339</sourcerecordid><originalsourceid>FETCH-LOGICAL-p133t-b6d2f220ed42ef68c2b26c75fd457aa592d521123fed618d75f92cc04dd144b63</originalsourceid><addsrcrecordid>eNotkM9Kw0AQxhdRsFYPvsGCNyF1_2WTPUrxT6HgpYK3sNmd4LYxGzeblh4E38E39EmMTU8zzPfNN8MPoWtKZpRIfpfOCM2UEvkJmtA0pUkmqTxFE0KUSJjgb-foouvWhDCVZfkEfS0sNNFVzujofIN9hVf49_sHtw4CNr7pYujNQdr5sMF66LcuOujwMIrvgKGGrY5gcdCu3uk9boNfg4k4emxhC7Vvx9UygN5Yv2vwmNkHuERnla47uDrWKXp9fFjNn5Ply9Nifr9MWsp5TEppWcUYASsYVDI3rGTSZGllRZppnSpmU0Yp4xVYSXM7KIoZQ4S1VIhS8im6GXOH3z576GKx9n1ohpMFU4RRzjhXg-t2dHXGxQOOog3uQ4d9QUnxj7dIiyNe_gcqdG_-</addsrcrecordid><sourcetype>Aggregation Database</sourcetype><iscdi>true</iscdi><recordtype>conference_proceeding</recordtype><pqid>2902132339</pqid></control><display><type>conference_proceeding</type><title>Identification of T – pier construction work activities on the elevated railway project to develop work breakdown structure</title><source>AIP Journals Complete</source><creator>Saputra, Pungky Dharma ; Suhandi, Luxpetrus Agustian ; Purwanti, Nina ; Fansuri, Muhammad Hamzah ; Laksmi, Anasya Arsita</creator><contributor>Vaidyanathan, Sundarapandian ; Sambas, Aceng ; Sukono</contributor><creatorcontrib>Saputra, Pungky Dharma ; Suhandi, Luxpetrus Agustian ; Purwanti, Nina ; Fansuri, Muhammad Hamzah ; Laksmi, Anasya Arsita ; Vaidyanathan, Sundarapandian ; Sambas, Aceng ; Sukono</creatorcontrib><description>The development of elevated railway infrastructures in Indonesia is going rapidly. The uniqueness of the T-Pier construction in the elevated railway project is the construction method that causes many activities to execute. The explained activities in the construction method were not clear, neither treated in much detail. In line with the problem, this research aim is to identify T-Piers construction work activities specifically. The project sample was MRT Jakarta CP 103 elevated section and T-Pier construction was the object of the case study. The first stage of this research was archive analysis, expert validation, and surveying of 100 bridge engineers. The collected data were analyzed by the descriptive analysis method. Then the work breakdown structure tree diagram was developed and shown the activities development. There were 31 activities identified starting from preparation until finishing and grouped into the main section group of activities i.e. pile cap, pier column, installation, and dismantling of temporary shoring, and pier head group activities. All the experts agreed that the activities identified were valid and almost all respondents 100% agree. The activities identified were at level 5 in the work breakdown structure development. The detailed activities can be standardized as a reference in future similar projects.</description><identifier>ISSN: 0094-243X</identifier><identifier>EISSN: 1551-7616</identifier><identifier>DOI: 10.1063/5.0179948</identifier><identifier>CODEN: APCPCS</identifier><language>eng</language><publisher>Melville: American Institute of Physics</publisher><subject>Breakdown ; Construction ; Construction methods ; Pile caps</subject><ispartof>AIP conference proceedings, 2023, Vol.2877 (1)</ispartof><rights>Author(s)</rights><rights>2023 Author(s). Published by AIP Publishing.</rights><lds50>peer_reviewed</lds50><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://pubs.aip.org/acp/article-lookup/doi/10.1063/5.0179948$$EHTML$$P50$$Gscitation$$H</linktohtml><link.rule.ids>309,310,314,776,780,785,786,790,4498,23911,23912,25120,27903,27904,76130</link.rule.ids></links><search><contributor>Vaidyanathan, Sundarapandian</contributor><contributor>Sambas, Aceng</contributor><contributor>Sukono</contributor><creatorcontrib>Saputra, Pungky Dharma</creatorcontrib><creatorcontrib>Suhandi, Luxpetrus Agustian</creatorcontrib><creatorcontrib>Purwanti, Nina</creatorcontrib><creatorcontrib>Fansuri, Muhammad Hamzah</creatorcontrib><creatorcontrib>Laksmi, Anasya Arsita</creatorcontrib><title>Identification of T – pier construction work activities on the elevated railway project to develop work breakdown structure</title><title>AIP conference proceedings</title><description>The development of elevated railway infrastructures in Indonesia is going rapidly. The uniqueness of the T-Pier construction in the elevated railway project is the construction method that causes many activities to execute. The explained activities in the construction method were not clear, neither treated in much detail. In line with the problem, this research aim is to identify T-Piers construction work activities specifically. The project sample was MRT Jakarta CP 103 elevated section and T-Pier construction was the object of the case study. The first stage of this research was archive analysis, expert validation, and surveying of 100 bridge engineers. The collected data were analyzed by the descriptive analysis method. Then the work breakdown structure tree diagram was developed and shown the activities development. There were 31 activities identified starting from preparation until finishing and grouped into the main section group of activities i.e. pile cap, pier column, installation, and dismantling of temporary shoring, and pier head group activities. All the experts agreed that the activities identified were valid and almost all respondents 100% agree. The activities identified were at level 5 in the work breakdown structure development. The detailed activities can be standardized as a reference in future similar projects.</description><subject>Breakdown</subject><subject>Construction</subject><subject>Construction methods</subject><subject>Pile caps</subject><issn>0094-243X</issn><issn>1551-7616</issn><fulltext>true</fulltext><rsrctype>conference_proceeding</rsrctype><creationdate>2023</creationdate><recordtype>conference_proceeding</recordtype><recordid>eNotkM9Kw0AQxhdRsFYPvsGCNyF1_2WTPUrxT6HgpYK3sNmd4LYxGzeblh4E38E39EmMTU8zzPfNN8MPoWtKZpRIfpfOCM2UEvkJmtA0pUkmqTxFE0KUSJjgb-foouvWhDCVZfkEfS0sNNFVzujofIN9hVf49_sHtw4CNr7pYujNQdr5sMF66LcuOujwMIrvgKGGrY5gcdCu3uk9boNfg4k4emxhC7Vvx9UygN5Yv2vwmNkHuERnla47uDrWKXp9fFjNn5Ply9Nifr9MWsp5TEppWcUYASsYVDI3rGTSZGllRZppnSpmU0Yp4xVYSXM7KIoZQ4S1VIhS8im6GXOH3z576GKx9n1ohpMFU4RRzjhXg-t2dHXGxQOOog3uQ4d9QUnxj7dIiyNe_gcqdG_-</recordid><startdate>20231215</startdate><enddate>20231215</enddate><creator>Saputra, Pungky Dharma</creator><creator>Suhandi, Luxpetrus Agustian</creator><creator>Purwanti, Nina</creator><creator>Fansuri, Muhammad Hamzah</creator><creator>Laksmi, Anasya Arsita</creator><general>American Institute of Physics</general><scope>8FD</scope><scope>H8D</scope><scope>L7M</scope></search><sort><creationdate>20231215</creationdate><title>Identification of T – pier construction work activities on the elevated railway project to develop work breakdown structure</title><author>Saputra, Pungky Dharma ; Suhandi, Luxpetrus Agustian ; Purwanti, Nina ; Fansuri, Muhammad Hamzah ; Laksmi, Anasya Arsita</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-LOGICAL-p133t-b6d2f220ed42ef68c2b26c75fd457aa592d521123fed618d75f92cc04dd144b63</frbrgroupid><rsrctype>conference_proceedings</rsrctype><prefilter>conference_proceedings</prefilter><language>eng</language><creationdate>2023</creationdate><topic>Breakdown</topic><topic>Construction</topic><topic>Construction methods</topic><topic>Pile caps</topic><toplevel>peer_reviewed</toplevel><toplevel>online_resources</toplevel><creatorcontrib>Saputra, Pungky Dharma</creatorcontrib><creatorcontrib>Suhandi, Luxpetrus Agustian</creatorcontrib><creatorcontrib>Purwanti, Nina</creatorcontrib><creatorcontrib>Fansuri, Muhammad Hamzah</creatorcontrib><creatorcontrib>Laksmi, Anasya Arsita</creatorcontrib><collection>Technology Research Database</collection><collection>Aerospace Database</collection><collection>Advanced Technologies Database with Aerospace</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext</fulltext></delivery><addata><au>Saputra, Pungky Dharma</au><au>Suhandi, Luxpetrus Agustian</au><au>Purwanti, Nina</au><au>Fansuri, Muhammad Hamzah</au><au>Laksmi, Anasya Arsita</au><au>Vaidyanathan, Sundarapandian</au><au>Sambas, Aceng</au><au>Sukono</au><format>book</format><genre>proceeding</genre><ristype>CONF</ristype><atitle>Identification of T – pier construction work activities on the elevated railway project to develop work breakdown structure</atitle><btitle>AIP conference proceedings</btitle><date>2023-12-15</date><risdate>2023</risdate><volume>2877</volume><issue>1</issue><issn>0094-243X</issn><eissn>1551-7616</eissn><coden>APCPCS</coden><abstract>The development of elevated railway infrastructures in Indonesia is going rapidly. The uniqueness of the T-Pier construction in the elevated railway project is the construction method that causes many activities to execute. The explained activities in the construction method were not clear, neither treated in much detail. In line with the problem, this research aim is to identify T-Piers construction work activities specifically. The project sample was MRT Jakarta CP 103 elevated section and T-Pier construction was the object of the case study. The first stage of this research was archive analysis, expert validation, and surveying of 100 bridge engineers. The collected data were analyzed by the descriptive analysis method. Then the work breakdown structure tree diagram was developed and shown the activities development. There were 31 activities identified starting from preparation until finishing and grouped into the main section group of activities i.e. pile cap, pier column, installation, and dismantling of temporary shoring, and pier head group activities. All the experts agreed that the activities identified were valid and almost all respondents 100% agree. The activities identified were at level 5 in the work breakdown structure development. The detailed activities can be standardized as a reference in future similar projects.</abstract><cop>Melville</cop><pub>American Institute of Physics</pub><doi>10.1063/5.0179948</doi><tpages>7</tpages></addata></record>
fulltext fulltext
identifier ISSN: 0094-243X
ispartof AIP conference proceedings, 2023, Vol.2877 (1)
issn 0094-243X
1551-7616
language eng
recordid cdi_scitation_primary_10_1063_5_0179948
source AIP Journals Complete
subjects Breakdown
Construction
Construction methods
Pile caps
title Identification of T – pier construction work activities on the elevated railway project to develop work breakdown structure
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-28T00%3A37%3A27IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-proquest_scita&rft_val_fmt=info:ofi/fmt:kev:mtx:book&rft.genre=proceeding&rft.atitle=Identification%20of%20T%20%E2%80%93%20pier%20construction%20work%20activities%20on%20the%20elevated%20railway%20project%20to%20develop%20work%20breakdown%20structure&rft.btitle=AIP%20conference%20proceedings&rft.au=Saputra,%20Pungky%20Dharma&rft.date=2023-12-15&rft.volume=2877&rft.issue=1&rft.issn=0094-243X&rft.eissn=1551-7616&rft.coden=APCPCS&rft_id=info:doi/10.1063/5.0179948&rft_dat=%3Cproquest_scita%3E2902132339%3C/proquest_scita%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_pqid=2902132339&rft_id=info:pmid/&rfr_iscdi=true