Cost overrun estimation in the construction of high-rise buildings using fuzzy inference model

Proper cost forecasting is a major parameter in the success of construction projects, and has a significant impact on various phases of a project, including its budget approval phase. Project managers usually look for solutions to reduce costs. It needs to identify the cost-rising factors, and to ex...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Veröffentlicht in:Revista de la construcción 2023-09, Vol.22 (2), p.382-406
Hauptverfasser: Paydar, Ali, Khademi Fahraji, Yaser, Tajaddini, Abbas, Sabzi, Zahra
Format: Artikel
Sprache:eng ; por
Schlagworte:
Online-Zugang:Volltext
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page 406
container_issue 2
container_start_page 382
container_title Revista de la construcción
container_volume 22
creator Paydar, Ali
Khademi Fahraji, Yaser
Tajaddini, Abbas
Sabzi, Zahra
description Proper cost forecasting is a major parameter in the success of construction projects, and has a significant impact on various phases of a project, including its budget approval phase. Project managers usually look for solutions to reduce costs. It needs to identify the cost-rising factors, and to exclude them from projects. This study principally aimed at forecasting cost increase of high-rise building construction, using a neuro fuzzy inference model. In fact, the model is able to quantify cost overrun, resulted from each influencing factor, based on fuzzy logic. Through a vast literature review, 43 cost-influencing factors were identified, which then were reduced to 13, using the principal component analysis method, and experts’ opinions. The construction cost was then predicted by the inference model created, based on each factor. The results showed that the factor of “lack of commitment of the Ministry of Housing” had the greatest impact, while the factor of “not considering measures to resolve potential disputes” had the least impact on the estimation of cost overrun in high-rise buildings.
doi_str_mv 10.7764/RDLC.22.2.382
format Article
fullrecord <record><control><sourceid>scielo_cross</sourceid><recordid>TN_cdi_scielo_journals_S0718_915X2023000200382</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><scielo_id>S0718_915X2023000200382</scielo_id><sourcerecordid>S0718_915X2023000200382</sourcerecordid><originalsourceid>FETCH-LOGICAL-c772-e496605a9a3b0851c959d6106b134376043e0ed7185c2f12c9678b1883ac9c603</originalsourceid><addsrcrecordid>eNpNkE9LxDAQxYMouOgevecLtCaTNk2OUv_CgqB78GRo03Q3SzeRpBV2P72p68G5vGGYN8PvIXRDSV5VvLh9u1_VOUAOORNwhhakoiKTtPw4_9dfomWMO5KKyUJIskCftY8j9t8mhMlhE0e7b0brHbYOj1uDtXdxDJP-nfkeb-1mmwUbDW4nO3TWbSKeYhLcT8fjIdl6E4zTBu99Z4ZrdNE3QzTLP71C68eHdf2crV6fXuq7VaarCjJTSM5J2ciGtUSUVMtSdpwS3lJWsIqTghliukRRaugpaMkr0VIhWKOl5oRdofx0NmprBq92fgou_VPvM7qa0YEAS9yQ0AUkQ3Yy6OBjDKZXXyGRh4OiRM15qjlPBaBAzfs_AT5mgg</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>article</recordtype></control><display><type>article</type><title>Cost overrun estimation in the construction of high-rise buildings using fuzzy inference model</title><source>Elektronische Zeitschriftenbibliothek - Frei zugängliche E-Journals</source><creator>Paydar, Ali ; Khademi Fahraji, Yaser ; Tajaddini, Abbas ; Sabzi, Zahra</creator><creatorcontrib>Paydar, Ali ; Khademi Fahraji, Yaser ; Tajaddini, Abbas ; Sabzi, Zahra ; Department of Civil Engineering, Karaj branch, Islamic Azad University, Karaj (Iran) ; Department of Civil Engineering, Malard branch, Islamic Azad University, Tehran (Iran) ; Department of Civil Engineering, Karaj branch, Islamic Azad University, Karaj, (Iran)</creatorcontrib><description>Proper cost forecasting is a major parameter in the success of construction projects, and has a significant impact on various phases of a project, including its budget approval phase. Project managers usually look for solutions to reduce costs. It needs to identify the cost-rising factors, and to exclude them from projects. This study principally aimed at forecasting cost increase of high-rise building construction, using a neuro fuzzy inference model. In fact, the model is able to quantify cost overrun, resulted from each influencing factor, based on fuzzy logic. Through a vast literature review, 43 cost-influencing factors were identified, which then were reduced to 13, using the principal component analysis method, and experts’ opinions. The construction cost was then predicted by the inference model created, based on each factor. The results showed that the factor of “lack of commitment of the Ministry of Housing” had the greatest impact, while the factor of “not considering measures to resolve potential disputes” had the least impact on the estimation of cost overrun in high-rise buildings.</description><identifier>ISSN: 0718-915X</identifier><identifier>EISSN: 0718-915X</identifier><identifier>DOI: 10.7764/RDLC.22.2.382</identifier><language>eng ; por</language><publisher>Escuela de Construcción Civil, Pontificia Universidad Católica de Chile</publisher><subject>CONSTRUCTION &amp; BUILDING TECHNOLOGY ; ENGINEERING, CIVIL</subject><ispartof>Revista de la construcción, 2023-09, Vol.22 (2), p.382-406</ispartof><rights>This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.</rights><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><link.rule.ids>230,314,780,784,885,27924,27925</link.rule.ids></links><search><creatorcontrib>Paydar, Ali</creatorcontrib><creatorcontrib>Khademi Fahraji, Yaser</creatorcontrib><creatorcontrib>Tajaddini, Abbas</creatorcontrib><creatorcontrib>Sabzi, Zahra</creatorcontrib><creatorcontrib>Department of Civil Engineering, Karaj branch, Islamic Azad University, Karaj (Iran)</creatorcontrib><creatorcontrib>Department of Civil Engineering, Malard branch, Islamic Azad University, Tehran (Iran)</creatorcontrib><creatorcontrib>Department of Civil Engineering, Karaj branch, Islamic Azad University, Karaj, (Iran)</creatorcontrib><title>Cost overrun estimation in the construction of high-rise buildings using fuzzy inference model</title><title>Revista de la construcción</title><addtitle>Revista de la Construcción</addtitle><description>Proper cost forecasting is a major parameter in the success of construction projects, and has a significant impact on various phases of a project, including its budget approval phase. Project managers usually look for solutions to reduce costs. It needs to identify the cost-rising factors, and to exclude them from projects. This study principally aimed at forecasting cost increase of high-rise building construction, using a neuro fuzzy inference model. In fact, the model is able to quantify cost overrun, resulted from each influencing factor, based on fuzzy logic. Through a vast literature review, 43 cost-influencing factors were identified, which then were reduced to 13, using the principal component analysis method, and experts’ opinions. The construction cost was then predicted by the inference model created, based on each factor. The results showed that the factor of “lack of commitment of the Ministry of Housing” had the greatest impact, while the factor of “not considering measures to resolve potential disputes” had the least impact on the estimation of cost overrun in high-rise buildings.</description><subject>CONSTRUCTION &amp; BUILDING TECHNOLOGY</subject><subject>ENGINEERING, CIVIL</subject><issn>0718-915X</issn><issn>0718-915X</issn><fulltext>true</fulltext><rsrctype>article</rsrctype><creationdate>2023</creationdate><recordtype>article</recordtype><recordid>eNpNkE9LxDAQxYMouOgevecLtCaTNk2OUv_CgqB78GRo03Q3SzeRpBV2P72p68G5vGGYN8PvIXRDSV5VvLh9u1_VOUAOORNwhhakoiKTtPw4_9dfomWMO5KKyUJIskCftY8j9t8mhMlhE0e7b0brHbYOj1uDtXdxDJP-nfkeb-1mmwUbDW4nO3TWbSKeYhLcT8fjIdl6E4zTBu99Z4ZrdNE3QzTLP71C68eHdf2crV6fXuq7VaarCjJTSM5J2ciGtUSUVMtSdpwS3lJWsIqTghliukRRaugpaMkr0VIhWKOl5oRdofx0NmprBq92fgou_VPvM7qa0YEAS9yQ0AUkQ3Yy6OBjDKZXXyGRh4OiRM15qjlPBaBAzfs_AT5mgg</recordid><startdate>20230901</startdate><enddate>20230901</enddate><creator>Paydar, Ali</creator><creator>Khademi Fahraji, Yaser</creator><creator>Tajaddini, Abbas</creator><creator>Sabzi, Zahra</creator><general>Escuela de Construcción Civil, Pontificia Universidad Católica de Chile</general><scope>AAYXX</scope><scope>CITATION</scope><scope>GPN</scope></search><sort><creationdate>20230901</creationdate><title>Cost overrun estimation in the construction of high-rise buildings using fuzzy inference model</title><author>Paydar, Ali ; Khademi Fahraji, Yaser ; Tajaddini, Abbas ; Sabzi, Zahra</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-LOGICAL-c772-e496605a9a3b0851c959d6106b134376043e0ed7185c2f12c9678b1883ac9c603</frbrgroupid><rsrctype>articles</rsrctype><prefilter>articles</prefilter><language>eng ; por</language><creationdate>2023</creationdate><topic>CONSTRUCTION &amp; BUILDING TECHNOLOGY</topic><topic>ENGINEERING, CIVIL</topic><toplevel>online_resources</toplevel><creatorcontrib>Paydar, Ali</creatorcontrib><creatorcontrib>Khademi Fahraji, Yaser</creatorcontrib><creatorcontrib>Tajaddini, Abbas</creatorcontrib><creatorcontrib>Sabzi, Zahra</creatorcontrib><creatorcontrib>Department of Civil Engineering, Karaj branch, Islamic Azad University, Karaj (Iran)</creatorcontrib><creatorcontrib>Department of Civil Engineering, Malard branch, Islamic Azad University, Tehran (Iran)</creatorcontrib><creatorcontrib>Department of Civil Engineering, Karaj branch, Islamic Azad University, Karaj, (Iran)</creatorcontrib><collection>CrossRef</collection><collection>SciELO</collection><jtitle>Revista de la construcción</jtitle></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext</fulltext></delivery><addata><au>Paydar, Ali</au><au>Khademi Fahraji, Yaser</au><au>Tajaddini, Abbas</au><au>Sabzi, Zahra</au><aucorp>Department of Civil Engineering, Karaj branch, Islamic Azad University, Karaj (Iran)</aucorp><aucorp>Department of Civil Engineering, Malard branch, Islamic Azad University, Tehran (Iran)</aucorp><aucorp>Department of Civil Engineering, Karaj branch, Islamic Azad University, Karaj, (Iran)</aucorp><format>journal</format><genre>article</genre><ristype>JOUR</ristype><atitle>Cost overrun estimation in the construction of high-rise buildings using fuzzy inference model</atitle><jtitle>Revista de la construcción</jtitle><addtitle>Revista de la Construcción</addtitle><date>2023-09-01</date><risdate>2023</risdate><volume>22</volume><issue>2</issue><spage>382</spage><epage>406</epage><pages>382-406</pages><issn>0718-915X</issn><eissn>0718-915X</eissn><abstract>Proper cost forecasting is a major parameter in the success of construction projects, and has a significant impact on various phases of a project, including its budget approval phase. Project managers usually look for solutions to reduce costs. It needs to identify the cost-rising factors, and to exclude them from projects. This study principally aimed at forecasting cost increase of high-rise building construction, using a neuro fuzzy inference model. In fact, the model is able to quantify cost overrun, resulted from each influencing factor, based on fuzzy logic. Through a vast literature review, 43 cost-influencing factors were identified, which then were reduced to 13, using the principal component analysis method, and experts’ opinions. The construction cost was then predicted by the inference model created, based on each factor. The results showed that the factor of “lack of commitment of the Ministry of Housing” had the greatest impact, while the factor of “not considering measures to resolve potential disputes” had the least impact on the estimation of cost overrun in high-rise buildings.</abstract><pub>Escuela de Construcción Civil, Pontificia Universidad Católica de Chile</pub><doi>10.7764/RDLC.22.2.382</doi><tpages>25</tpages><oa>free_for_read</oa></addata></record>
fulltext fulltext
identifier ISSN: 0718-915X
ispartof Revista de la construcción, 2023-09, Vol.22 (2), p.382-406
issn 0718-915X
0718-915X
language eng ; por
recordid cdi_scielo_journals_S0718_915X2023000200382
source Elektronische Zeitschriftenbibliothek - Frei zugängliche E-Journals
subjects CONSTRUCTION & BUILDING TECHNOLOGY
ENGINEERING, CIVIL
title Cost overrun estimation in the construction of high-rise buildings using fuzzy inference model
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-05T15%3A20%3A07IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-scielo_cross&rft_val_fmt=info:ofi/fmt:kev:mtx:journal&rft.genre=article&rft.atitle=Cost%20overrun%20estimation%20in%20the%20construction%20of%20high-rise%20buildings%20using%20fuzzy%20inference%20model&rft.jtitle=Revista%20de%20la%20construcci%C3%B3n&rft.au=Paydar,%20Ali&rft.aucorp=Department%20of%20Civil%20Engineering,%20Karaj%20branch,%20Islamic%20Azad%20University,%20Karaj%20(Iran)&rft.date=2023-09-01&rft.volume=22&rft.issue=2&rft.spage=382&rft.epage=406&rft.pages=382-406&rft.issn=0718-915X&rft.eissn=0718-915X&rft_id=info:doi/10.7764/RDLC.22.2.382&rft_dat=%3Cscielo_cross%3ES0718_915X2023000200382%3C/scielo_cross%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rft_scielo_id=S0718_915X2023000200382&rfr_iscdi=true