Quantification of Productivity Changes Due to Work Schedule Changes in Construction Projects: A Case Study

In a copper-molybdenum open pit mine in Chile, a collective labor dispute in April 2012 halted work on the site; the main problem was the negotiation of unified work schedules for contractors, subcontractors and their own staff. To avoid conflicts that could delay this project, the parties agreed to...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Veröffentlicht in:Revista de la construcción (Universidad Católica de Chile) 2014-04, Vol.13 (1), p.9-14
Hauptverfasser: Arriagada, Ricardo E, Alarcón C, Luis F
Format: Artikel
Sprache:eng
Schlagworte:
Online-Zugang:Volltext
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page 14
container_issue 1
container_start_page 9
container_title Revista de la construcción (Universidad Católica de Chile)
container_volume 13
creator Arriagada, Ricardo E
Alarcón C, Luis F
description In a copper-molybdenum open pit mine in Chile, a collective labor dispute in April 2012 halted work on the site; the main problem was the negotiation of unified work schedules for contractors, subcontractors and their own staff. To avoid conflicts that could delay this project, the parties agreed to submit to arbitration by an external agency, to determine and quantify the existence of lost productivity caused by the change of work schedules. The external agency considered three basic elements: a) the temporal dimension to allow the comparison of two work schedules, b) the acceptable range of productivity losses associated with these schedules; and c) an unbiased mechanism to allocate a productivity loss within the range associated with each schedule. This paper presents the analysis of productivity loss when work schedules are extended, the method utilized, and the results obtained. This probabilistic model randomly assigns discrete values of productivity loss for each day of the work schedules, and uses inefficiency ranges from industry research; this allows a non-biased, easy to implement, comparison of work schedules.
doi_str_mv 10.4067/S0718-915X2014000100001
format Article
fullrecord <record><control><sourceid>scielo_cross</sourceid><recordid>TN_cdi_scielo_journals_S0718_915X2014000100001</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><scielo_id>S0718_915X2014000100001</scielo_id><sourcerecordid>S0718_915X2014000100001</sourcerecordid><originalsourceid>FETCH-LOGICAL-c291t-ba323aa3dc84e62034fed9349fd668ab924c9610ec7cefeed741d46aa3b7f1b63</originalsourceid><addsrcrecordid>eNp1kF9LwzAUxYMoOHSfwXyBzqSJaePbqH9hoDJF30qa3LjU2UiSCvv2tk6GIL7ce-Hc3zlwEDqhZMaJKE6XpKBlJunZS04oJ4RQMo49NNkJ-7_uQzSNsR1fmOSlJBPUPvSqS846rZLzHfYW3wdvep3cp0sbXK1U9woRX_SAk8fPPrzhpV6B6dewE12HK9_FFEZsMBkcWtApnuM5rlQEvEy92RyjA6vWEaY_-wg9XV0-VjfZ4u76tpovMp1LmrJGsZwpxYwuOYicMG7BSMalNUKUqpE511JQArrQYAFMwanhYiCawtJGsCM02_pG7WDt69b3oRsC6--y6j9lDUCxBXTwMQaw9Udw7ypsakrqseZ_yS9N32-H</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>article</recordtype></control><display><type>article</type><title>Quantification of Productivity Changes Due to Work Schedule Changes in Construction Projects: A Case Study</title><source>EZB-FREE-00999 freely available EZB journals</source><creator>Arriagada, Ricardo E ; Alarcón C, Luis F</creator><creatorcontrib>Arriagada, Ricardo E ; Alarcón C, Luis F</creatorcontrib><description>In a copper-molybdenum open pit mine in Chile, a collective labor dispute in April 2012 halted work on the site; the main problem was the negotiation of unified work schedules for contractors, subcontractors and their own staff. To avoid conflicts that could delay this project, the parties agreed to submit to arbitration by an external agency, to determine and quantify the existence of lost productivity caused by the change of work schedules. The external agency considered three basic elements: a) the temporal dimension to allow the comparison of two work schedules, b) the acceptable range of productivity losses associated with these schedules; and c) an unbiased mechanism to allocate a productivity loss within the range associated with each schedule. This paper presents the analysis of productivity loss when work schedules are extended, the method utilized, and the results obtained. This probabilistic model randomly assigns discrete values of productivity loss for each day of the work schedules, and uses inefficiency ranges from industry research; this allows a non-biased, easy to implement, comparison of work schedules.</description><identifier>ISSN: 0718-915X</identifier><identifier>EISSN: 0718-915X</identifier><identifier>DOI: 10.4067/S0718-915X2014000100001</identifier><language>eng</language><publisher>Escuela de Construcción Civil, Pontificia Universidad Católica de Chile</publisher><subject>CONSTRUCTION &amp; BUILDING TECHNOLOGY ; ENGINEERING, CIVIL</subject><ispartof>Revista de la construcción (Universidad Católica de Chile), 2014-04, Vol.13 (1), p.9-14</ispartof><rights>This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.</rights><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><link.rule.ids>230,314,776,780,881,27901,27902</link.rule.ids></links><search><creatorcontrib>Arriagada, Ricardo E</creatorcontrib><creatorcontrib>Alarcón C, Luis F</creatorcontrib><title>Quantification of Productivity Changes Due to Work Schedule Changes in Construction Projects: A Case Study</title><title>Revista de la construcción (Universidad Católica de Chile)</title><addtitle>Revista de la Construcción</addtitle><description>In a copper-molybdenum open pit mine in Chile, a collective labor dispute in April 2012 halted work on the site; the main problem was the negotiation of unified work schedules for contractors, subcontractors and their own staff. To avoid conflicts that could delay this project, the parties agreed to submit to arbitration by an external agency, to determine and quantify the existence of lost productivity caused by the change of work schedules. The external agency considered three basic elements: a) the temporal dimension to allow the comparison of two work schedules, b) the acceptable range of productivity losses associated with these schedules; and c) an unbiased mechanism to allocate a productivity loss within the range associated with each schedule. This paper presents the analysis of productivity loss when work schedules are extended, the method utilized, and the results obtained. This probabilistic model randomly assigns discrete values of productivity loss for each day of the work schedules, and uses inefficiency ranges from industry research; this allows a non-biased, easy to implement, comparison of work schedules.</description><subject>CONSTRUCTION &amp; BUILDING TECHNOLOGY</subject><subject>ENGINEERING, CIVIL</subject><issn>0718-915X</issn><issn>0718-915X</issn><fulltext>true</fulltext><rsrctype>article</rsrctype><creationdate>2014</creationdate><recordtype>article</recordtype><recordid>eNp1kF9LwzAUxYMoOHSfwXyBzqSJaePbqH9hoDJF30qa3LjU2UiSCvv2tk6GIL7ce-Hc3zlwEDqhZMaJKE6XpKBlJunZS04oJ4RQMo49NNkJ-7_uQzSNsR1fmOSlJBPUPvSqS846rZLzHfYW3wdvep3cp0sbXK1U9woRX_SAk8fPPrzhpV6B6dewE12HK9_FFEZsMBkcWtApnuM5rlQEvEy92RyjA6vWEaY_-wg9XV0-VjfZ4u76tpovMp1LmrJGsZwpxYwuOYicMG7BSMalNUKUqpE511JQArrQYAFMwanhYiCawtJGsCM02_pG7WDt69b3oRsC6--y6j9lDUCxBXTwMQaw9Udw7ypsakrqseZ_yS9N32-H</recordid><startdate>20140401</startdate><enddate>20140401</enddate><creator>Arriagada, Ricardo E</creator><creator>Alarcón C, Luis F</creator><general>Escuela de Construcción Civil, Pontificia Universidad Católica de Chile</general><scope>AAYXX</scope><scope>CITATION</scope><scope>GPN</scope></search><sort><creationdate>20140401</creationdate><title>Quantification of Productivity Changes Due to Work Schedule Changes in Construction Projects: A Case Study</title><author>Arriagada, Ricardo E ; Alarcón C, Luis F</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-LOGICAL-c291t-ba323aa3dc84e62034fed9349fd668ab924c9610ec7cefeed741d46aa3b7f1b63</frbrgroupid><rsrctype>articles</rsrctype><prefilter>articles</prefilter><language>eng</language><creationdate>2014</creationdate><topic>CONSTRUCTION &amp; BUILDING TECHNOLOGY</topic><topic>ENGINEERING, CIVIL</topic><toplevel>online_resources</toplevel><creatorcontrib>Arriagada, Ricardo E</creatorcontrib><creatorcontrib>Alarcón C, Luis F</creatorcontrib><collection>CrossRef</collection><collection>SciELO</collection><jtitle>Revista de la construcción (Universidad Católica de Chile)</jtitle></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext</fulltext></delivery><addata><au>Arriagada, Ricardo E</au><au>Alarcón C, Luis F</au><format>journal</format><genre>article</genre><ristype>JOUR</ristype><atitle>Quantification of Productivity Changes Due to Work Schedule Changes in Construction Projects: A Case Study</atitle><jtitle>Revista de la construcción (Universidad Católica de Chile)</jtitle><addtitle>Revista de la Construcción</addtitle><date>2014-04-01</date><risdate>2014</risdate><volume>13</volume><issue>1</issue><spage>9</spage><epage>14</epage><pages>9-14</pages><issn>0718-915X</issn><eissn>0718-915X</eissn><abstract>In a copper-molybdenum open pit mine in Chile, a collective labor dispute in April 2012 halted work on the site; the main problem was the negotiation of unified work schedules for contractors, subcontractors and their own staff. To avoid conflicts that could delay this project, the parties agreed to submit to arbitration by an external agency, to determine and quantify the existence of lost productivity caused by the change of work schedules. The external agency considered three basic elements: a) the temporal dimension to allow the comparison of two work schedules, b) the acceptable range of productivity losses associated with these schedules; and c) an unbiased mechanism to allocate a productivity loss within the range associated with each schedule. This paper presents the analysis of productivity loss when work schedules are extended, the method utilized, and the results obtained. This probabilistic model randomly assigns discrete values of productivity loss for each day of the work schedules, and uses inefficiency ranges from industry research; this allows a non-biased, easy to implement, comparison of work schedules.</abstract><pub>Escuela de Construcción Civil, Pontificia Universidad Católica de Chile</pub><doi>10.4067/S0718-915X2014000100001</doi><tpages>6</tpages><oa>free_for_read</oa></addata></record>
fulltext fulltext
identifier ISSN: 0718-915X
ispartof Revista de la construcción (Universidad Católica de Chile), 2014-04, Vol.13 (1), p.9-14
issn 0718-915X
0718-915X
language eng
recordid cdi_scielo_journals_S0718_915X2014000100001
source EZB-FREE-00999 freely available EZB journals
subjects CONSTRUCTION & BUILDING TECHNOLOGY
ENGINEERING, CIVIL
title Quantification of Productivity Changes Due to Work Schedule Changes in Construction Projects: A Case Study
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-02-04T06%3A47%3A14IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-scielo_cross&rft_val_fmt=info:ofi/fmt:kev:mtx:journal&rft.genre=article&rft.atitle=Quantification%20of%20Productivity%20Changes%20Due%20to%20Work%20Schedule%20Changes%20in%20Construction%20Projects:%20A%20Case%20Study&rft.jtitle=Revista%20de%20la%20construcci%C3%B3n%20(Universidad%20Cato%CC%81lica%20de%20Chile)&rft.au=Arriagada,%20Ricardo%20E&rft.date=2014-04-01&rft.volume=13&rft.issue=1&rft.spage=9&rft.epage=14&rft.pages=9-14&rft.issn=0718-915X&rft.eissn=0718-915X&rft_id=info:doi/10.4067/S0718-915X2014000100001&rft_dat=%3Cscielo_cross%3ES0718_915X2014000100001%3C/scielo_cross%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rft_scielo_id=S0718_915X2014000100001&rfr_iscdi=true