Impact of Shift Work on Labor Productivity for Labor Intensive Contractor
Generally, a contractor has three options in accelerating a construction schedule: working longer hours, increasing the number of workers, or creating an additional shift of workers. There has been a significant amount of research conducted on scheduled overtime on construction labor productivity. H...
Gespeichert in:
Veröffentlicht in: | Journal of construction engineering and management 2008-03, Vol.134 (3), p.197-204 |
---|---|
Hauptverfasser: | , , , |
Format: | Artikel |
Sprache: | eng |
Schlagworte: | |
Online-Zugang: | Volltext |
Tags: |
Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
|
container_end_page | 204 |
---|---|
container_issue | 3 |
container_start_page | 197 |
container_title | Journal of construction engineering and management |
container_volume | 134 |
creator | Hanna, Awad S Chang, Chul-Ki Sullivan, Kenneth T Lackney, Jeffery A |
description | Generally, a contractor has three options in accelerating a construction schedule: working longer hours, increasing the number of workers, or creating an additional shift of workers. There has been a significant amount of research conducted on scheduled overtime on construction labor productivity. However, little information has been found in the literature addressing the labor inefficiency associated with working a second shift. This paper has qualitative and quantitative components. The qualitative part details why and how shift work affects labor productivity, and then addresses the appropriate use of shift work. The quantitative component determines the relationship between the length of shift work and labor efficiency. The results of the research show that shift work has the potential to be both beneficial and detrimental to the productivity of construction labor. Small amounts of well-organized shift work can serve as a very effective response to schedule compression. The productivity loss, obtained from the quantification model developed through this study, ranges from
−11
to 17% depending on the amount of shift work used. |
doi_str_mv | 10.1061/(ASCE)0733-9364(2008)134:3(197) |
format | Article |
fullrecord | <record><control><sourceid>proquest_cross</sourceid><recordid>TN_cdi_proquest_miscellaneous_33017733</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>33017733</sourcerecordid><originalsourceid>FETCH-LOGICAL-a382t-a16c4b99744c49bbe4e26112e8e1f2ea20bd588925572b04840c8148aeb61d623</originalsourceid><addsrcrecordid>eNp9kF1LwzAYhYMoOKf_ITfqdlHNV9tkF8IoUwsDhSlehjRLsbNrZtIO9u9N6dilVy8cHs7hfQC4x-gBowQ_TuarbDFFKaWRoAmbEIT4FFM2oxMs0ukZGGHBaJTyhJyD0Ym7BFfebxDCLBHxCOT5dqd0C20JV99V2cIv636gbeBSFdbBd2fXnW6rfdUeYBmCIc6b1jS-2huY2aZ1ocC6a3BRqtqbm-Mdg8_nxUf2Gi3fXvJsvowU5aSNFE40K4RIGdNMFIVhhiQYE8MNLolRBBXrmHNB4jglBWKcIc0x48oUCV4nhI7B3dC7c_a3M76V28prU9eqMbbzklKE0_BtAJ8GUDvrvTOl3Llqq9xBYiR7hVL2CmWvRvZqZK9QBoWSyqAwFNwel5TXqi6danTlTy0EYR7gnpsNXMCM3NjONUHAaeX_kT-NoYKN</addsrcrecordid><sourcetype>Aggregation Database</sourcetype><iscdi>true</iscdi><recordtype>article</recordtype><pqid>33017733</pqid></control><display><type>article</type><title>Impact of Shift Work on Labor Productivity for Labor Intensive Contractor</title><source>American Society of Civil Engineers:NESLI2:Journals:2014</source><source>EBSCOhost Business Source Complete</source><creator>Hanna, Awad S ; Chang, Chul-Ki ; Sullivan, Kenneth T ; Lackney, Jeffery A</creator><creatorcontrib>Hanna, Awad S ; Chang, Chul-Ki ; Sullivan, Kenneth T ; Lackney, Jeffery A</creatorcontrib><description>Generally, a contractor has three options in accelerating a construction schedule: working longer hours, increasing the number of workers, or creating an additional shift of workers. There has been a significant amount of research conducted on scheduled overtime on construction labor productivity. However, little information has been found in the literature addressing the labor inefficiency associated with working a second shift. This paper has qualitative and quantitative components. The qualitative part details why and how shift work affects labor productivity, and then addresses the appropriate use of shift work. The quantitative component determines the relationship between the length of shift work and labor efficiency. The results of the research show that shift work has the potential to be both beneficial and detrimental to the productivity of construction labor. Small amounts of well-organized shift work can serve as a very effective response to schedule compression. The productivity loss, obtained from the quantification model developed through this study, ranges from
−11
to 17% depending on the amount of shift work used.</description><identifier>ISSN: 0733-9364</identifier><identifier>EISSN: 1943-7862</identifier><identifier>DOI: 10.1061/(ASCE)0733-9364(2008)134:3(197)</identifier><identifier>CODEN: JCEMD4</identifier><language>eng</language><publisher>Reston, VA: American Society of Civil Engineers</publisher><subject>Applied sciences ; Buildings. Public works ; Construction works ; Exact sciences and technology ; Site organization ; TECHNICAL PAPERS</subject><ispartof>Journal of construction engineering and management, 2008-03, Vol.134 (3), p.197-204</ispartof><rights>2008 INIST-CNRS</rights><lds50>peer_reviewed</lds50><woscitedreferencessubscribed>false</woscitedreferencessubscribed><citedby>FETCH-LOGICAL-a382t-a16c4b99744c49bbe4e26112e8e1f2ea20bd588925572b04840c8148aeb61d623</citedby><cites>FETCH-LOGICAL-a382t-a16c4b99744c49bbe4e26112e8e1f2ea20bd588925572b04840c8148aeb61d623</cites></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktopdf>$$Uhttp://ascelibrary.org/doi/pdf/10.1061/(ASCE)0733-9364(2008)134:3(197)$$EPDF$$P50$$Gasce$$H</linktopdf><linktohtml>$$Uhttp://ascelibrary.org/doi/abs/10.1061/(ASCE)0733-9364(2008)134:3(197)$$EHTML$$P50$$Gasce$$H</linktohtml><link.rule.ids>314,776,780,27901,27902,75935,75943</link.rule.ids><backlink>$$Uhttp://pascal-francis.inist.fr/vibad/index.php?action=getRecordDetail&idt=20181347$$DView record in Pascal Francis$$Hfree_for_read</backlink></links><search><creatorcontrib>Hanna, Awad S</creatorcontrib><creatorcontrib>Chang, Chul-Ki</creatorcontrib><creatorcontrib>Sullivan, Kenneth T</creatorcontrib><creatorcontrib>Lackney, Jeffery A</creatorcontrib><title>Impact of Shift Work on Labor Productivity for Labor Intensive Contractor</title><title>Journal of construction engineering and management</title><description>Generally, a contractor has three options in accelerating a construction schedule: working longer hours, increasing the number of workers, or creating an additional shift of workers. There has been a significant amount of research conducted on scheduled overtime on construction labor productivity. However, little information has been found in the literature addressing the labor inefficiency associated with working a second shift. This paper has qualitative and quantitative components. The qualitative part details why and how shift work affects labor productivity, and then addresses the appropriate use of shift work. The quantitative component determines the relationship between the length of shift work and labor efficiency. The results of the research show that shift work has the potential to be both beneficial and detrimental to the productivity of construction labor. Small amounts of well-organized shift work can serve as a very effective response to schedule compression. The productivity loss, obtained from the quantification model developed through this study, ranges from
−11
to 17% depending on the amount of shift work used.</description><subject>Applied sciences</subject><subject>Buildings. Public works</subject><subject>Construction works</subject><subject>Exact sciences and technology</subject><subject>Site organization</subject><subject>TECHNICAL PAPERS</subject><issn>0733-9364</issn><issn>1943-7862</issn><fulltext>true</fulltext><rsrctype>article</rsrctype><creationdate>2008</creationdate><recordtype>article</recordtype><recordid>eNp9kF1LwzAYhYMoOKf_ITfqdlHNV9tkF8IoUwsDhSlehjRLsbNrZtIO9u9N6dilVy8cHs7hfQC4x-gBowQ_TuarbDFFKaWRoAmbEIT4FFM2oxMs0ukZGGHBaJTyhJyD0Ym7BFfebxDCLBHxCOT5dqd0C20JV99V2cIv636gbeBSFdbBd2fXnW6rfdUeYBmCIc6b1jS-2huY2aZ1ocC6a3BRqtqbm-Mdg8_nxUf2Gi3fXvJsvowU5aSNFE40K4RIGdNMFIVhhiQYE8MNLolRBBXrmHNB4jglBWKcIc0x48oUCV4nhI7B3dC7c_a3M76V28prU9eqMbbzklKE0_BtAJ8GUDvrvTOl3Llqq9xBYiR7hVL2CmWvRvZqZK9QBoWSyqAwFNwel5TXqi6danTlTy0EYR7gnpsNXMCM3NjONUHAaeX_kT-NoYKN</recordid><startdate>20080301</startdate><enddate>20080301</enddate><creator>Hanna, Awad S</creator><creator>Chang, Chul-Ki</creator><creator>Sullivan, Kenneth T</creator><creator>Lackney, Jeffery A</creator><general>American Society of Civil Engineers</general><scope>IQODW</scope><scope>AAYXX</scope><scope>CITATION</scope><scope>8FD</scope><scope>FR3</scope><scope>KR7</scope></search><sort><creationdate>20080301</creationdate><title>Impact of Shift Work on Labor Productivity for Labor Intensive Contractor</title><author>Hanna, Awad S ; Chang, Chul-Ki ; Sullivan, Kenneth T ; Lackney, Jeffery A</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-LOGICAL-a382t-a16c4b99744c49bbe4e26112e8e1f2ea20bd588925572b04840c8148aeb61d623</frbrgroupid><rsrctype>articles</rsrctype><prefilter>articles</prefilter><language>eng</language><creationdate>2008</creationdate><topic>Applied sciences</topic><topic>Buildings. Public works</topic><topic>Construction works</topic><topic>Exact sciences and technology</topic><topic>Site organization</topic><topic>TECHNICAL PAPERS</topic><toplevel>peer_reviewed</toplevel><toplevel>online_resources</toplevel><creatorcontrib>Hanna, Awad S</creatorcontrib><creatorcontrib>Chang, Chul-Ki</creatorcontrib><creatorcontrib>Sullivan, Kenneth T</creatorcontrib><creatorcontrib>Lackney, Jeffery A</creatorcontrib><collection>Pascal-Francis</collection><collection>CrossRef</collection><collection>Technology Research Database</collection><collection>Engineering Research Database</collection><collection>Civil Engineering Abstracts</collection><jtitle>Journal of construction engineering and management</jtitle></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext</fulltext></delivery><addata><au>Hanna, Awad S</au><au>Chang, Chul-Ki</au><au>Sullivan, Kenneth T</au><au>Lackney, Jeffery A</au><format>journal</format><genre>article</genre><ristype>JOUR</ristype><atitle>Impact of Shift Work on Labor Productivity for Labor Intensive Contractor</atitle><jtitle>Journal of construction engineering and management</jtitle><date>2008-03-01</date><risdate>2008</risdate><volume>134</volume><issue>3</issue><spage>197</spage><epage>204</epage><pages>197-204</pages><issn>0733-9364</issn><eissn>1943-7862</eissn><coden>JCEMD4</coden><abstract>Generally, a contractor has three options in accelerating a construction schedule: working longer hours, increasing the number of workers, or creating an additional shift of workers. There has been a significant amount of research conducted on scheduled overtime on construction labor productivity. However, little information has been found in the literature addressing the labor inefficiency associated with working a second shift. This paper has qualitative and quantitative components. The qualitative part details why and how shift work affects labor productivity, and then addresses the appropriate use of shift work. The quantitative component determines the relationship between the length of shift work and labor efficiency. The results of the research show that shift work has the potential to be both beneficial and detrimental to the productivity of construction labor. Small amounts of well-organized shift work can serve as a very effective response to schedule compression. The productivity loss, obtained from the quantification model developed through this study, ranges from
−11
to 17% depending on the amount of shift work used.</abstract><cop>Reston, VA</cop><pub>American Society of Civil Engineers</pub><doi>10.1061/(ASCE)0733-9364(2008)134:3(197)</doi><tpages>8</tpages></addata></record> |
fulltext | fulltext |
identifier | ISSN: 0733-9364 |
ispartof | Journal of construction engineering and management, 2008-03, Vol.134 (3), p.197-204 |
issn | 0733-9364 1943-7862 |
language | eng |
recordid | cdi_proquest_miscellaneous_33017733 |
source | American Society of Civil Engineers:NESLI2:Journals:2014; EBSCOhost Business Source Complete |
subjects | Applied sciences Buildings. Public works Construction works Exact sciences and technology Site organization TECHNICAL PAPERS |
title | Impact of Shift Work on Labor Productivity for Labor Intensive Contractor |
url | https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-02-11T06%3A24%3A57IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-proquest_cross&rft_val_fmt=info:ofi/fmt:kev:mtx:journal&rft.genre=article&rft.atitle=Impact%20of%20Shift%20Work%20on%20Labor%20Productivity%20for%20Labor%20Intensive%20Contractor&rft.jtitle=Journal%20of%20construction%20engineering%20and%20management&rft.au=Hanna,%20Awad%20S&rft.date=2008-03-01&rft.volume=134&rft.issue=3&rft.spage=197&rft.epage=204&rft.pages=197-204&rft.issn=0733-9364&rft.eissn=1943-7862&rft.coden=JCEMD4&rft_id=info:doi/10.1061/(ASCE)0733-9364(2008)134:3(197)&rft_dat=%3Cproquest_cross%3E33017733%3C/proquest_cross%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_pqid=33017733&rft_id=info:pmid/&rfr_iscdi=true |