Moving a Reinforced-Concrete Building: Case Study

The project management team directing the construction of a concrete building learned during the last stages of construction that the building encroached by 190 cm into the permit specified setback. This case study discusses how the Internet was used to aid the contractor in addressing the problem a...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Veröffentlicht in:Journal of construction engineering and management 2006-02, Vol.132 (2), p.115-124
Hauptverfasser: Telem, Dory, Shapira, Aviad, Goren, Ytzhak D, Schexnayder, Cliff J
Format: Artikel