Design Procedure for Determining Optimal Length of Side-Weir in Flood Control Detention Basin Considering Bed Roughness Coefficient

AbstractSide-weir detention basins have been increasingly highlighted as an alternative countermeasure for decreasing peak flood discharge and have become increasingly adopted as part of an integrated watershed flood protection plan. However, there were few methodologies sufficient enough to quantit...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Veröffentlicht in:Journal of irrigation and drainage engineering 2016-12, Vol.142 (12)
Hauptverfasser: Kim, Seojun, Yoon, Byungman, Kim, Sanghuk, Kim, Dongsu
Format: Artikel
Sprache:eng
Schlagworte:
Online-Zugang:Volltext
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue 12
container_start_page
container_title Journal of irrigation and drainage engineering
container_volume 142
creator Kim, Seojun
Yoon, Byungman
Kim, Sanghuk
Kim, Dongsu
description AbstractSide-weir detention basins have been increasingly highlighted as an alternative countermeasure for decreasing peak flood discharge and have become increasingly adopted as part of an integrated watershed flood protection plan. However, there were few methodologies sufficient enough to quantitatively estimate the decrease of the peak flow by the side-weir detention basin in flood-control measures by fully considering relevant design and hydraulic parameters. Until now, any noticeable standardized design procedure to optimally design the size of a side-weir located at the inlet of a detention basin has not been available. In this study, a generalized design procedure was proposed for determining the horizontal length of a side-weir considering hydraulic parameters, especially for the bed roughness as a major hydraulic parameter, where other hydraulic parameters were assumed to be invariant and restricted by field conditions. The proposed design procedure is exemplified based on a simple numerical model detailed herein. In particular, the design procedure considers complex overflow regimes dominated by free and submerged overflow between the main channel and detention basin through the side-weir. Subsequently, a concept for a flood control performance graph is suggested for evaluating the decrease of peak flow for design and hydraulic parameters of the side-weir, such as the bed roughness and the length of side-weir, respectively. Also, a design characteristic line is also proposed to finally determine the optimal length of side-weir.
doi_str_mv 10.1061/(ASCE)IR.1943-4774.0001008
format Article
fullrecord <record><control><sourceid>proquest_cross</sourceid><recordid>TN_cdi_proquest_miscellaneous_1846395450</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>1846395450</sourcerecordid><originalsourceid>FETCH-LOGICAL-a379t-a03b6da6f1451dc16cc6fecc68b2d618d6fa477ba3f71a93268b7f98da6dd4383</originalsourceid><addsrcrecordid>eNp1kMtOAyEUhonRxHp5B-KqLqZCocyMO22tNmmiqRqXhA6HkWYKFWYWrn1xGWvcueGE81-S8yF0QcmIEkGvhjfP07vLxWpES84ynud8RAihhBQHaPC3O0QDkjOWpX9-jE5i3CQPzwkZoK8ZRFs7_BR8BboLgI0PeAYthK111tX4cdfarWrwElzdvmNv8LPVkL2BDdg6PG-813jqXRt88xN0rfUO36qY1LSPyR36olvQeOW7-t1BjEkBY2xlk_0MHRnVRDj_nafodX73Mn3Ilo_3i-nNMlMsL9tMEbYWWglD-YTqioqqEgbSU6zHWtBCC6PStWvFTE5VycZJyE1ZpIjWnBXsFA33vbvgPzqIrdzaWEHTKAe-i5IWXLBywickWa_31ir4GAMYuQuJQviUlMievJQ9eblYyZ6y7CnLX_IpLPZhldrlxnfBpbP-kv8HvwFyYIoS</addsrcrecordid><sourcetype>Aggregation Database</sourcetype><iscdi>true</iscdi><recordtype>article</recordtype><pqid>1846395450</pqid></control><display><type>article</type><title>Design Procedure for Determining Optimal Length of Side-Weir in Flood Control Detention Basin Considering Bed Roughness Coefficient</title><source>American Society of Civil Engineers:NESLI2:Journals:2014</source><creator>Kim, Seojun ; Yoon, Byungman ; Kim, Sanghuk ; Kim, Dongsu</creator><creatorcontrib>Kim, Seojun ; Yoon, Byungman ; Kim, Sanghuk ; Kim, Dongsu</creatorcontrib><description>AbstractSide-weir detention basins have been increasingly highlighted as an alternative countermeasure for decreasing peak flood discharge and have become increasingly adopted as part of an integrated watershed flood protection plan. However, there were few methodologies sufficient enough to quantitatively estimate the decrease of the peak flow by the side-weir detention basin in flood-control measures by fully considering relevant design and hydraulic parameters. Until now, any noticeable standardized design procedure to optimally design the size of a side-weir located at the inlet of a detention basin has not been available. In this study, a generalized design procedure was proposed for determining the horizontal length of a side-weir considering hydraulic parameters, especially for the bed roughness as a major hydraulic parameter, where other hydraulic parameters were assumed to be invariant and restricted by field conditions. The proposed design procedure is exemplified based on a simple numerical model detailed herein. In particular, the design procedure considers complex overflow regimes dominated by free and submerged overflow between the main channel and detention basin through the side-weir. Subsequently, a concept for a flood control performance graph is suggested for evaluating the decrease of peak flow for design and hydraulic parameters of the side-weir, such as the bed roughness and the length of side-weir, respectively. Also, a design characteristic line is also proposed to finally determine the optimal length of side-weir.</description><identifier>ISSN: 0733-9437</identifier><identifier>EISSN: 1943-4774</identifier><identifier>DOI: 10.1061/(ASCE)IR.1943-4774.0001008</identifier><language>eng</language><publisher>American Society of Civil Engineers</publisher><subject>Technical Note ; Technical Notes</subject><ispartof>Journal of irrigation and drainage engineering, 2016-12, Vol.142 (12)</ispartof><rights>2016 American Society of Civil Engineers</rights><lds50>peer_reviewed</lds50><woscitedreferencessubscribed>false</woscitedreferencessubscribed><citedby>FETCH-LOGICAL-a379t-a03b6da6f1451dc16cc6fecc68b2d618d6fa477ba3f71a93268b7f98da6dd4383</citedby><cites>FETCH-LOGICAL-a379t-a03b6da6f1451dc16cc6fecc68b2d618d6fa477ba3f71a93268b7f98da6dd4383</cites></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktopdf>$$Uhttp://ascelibrary.org/doi/pdf/10.1061/(ASCE)IR.1943-4774.0001008$$EPDF$$P50$$Gasce$$H</linktopdf><linktohtml>$$Uhttp://ascelibrary.org/doi/abs/10.1061/(ASCE)IR.1943-4774.0001008$$EHTML$$P50$$Gasce$$H</linktohtml><link.rule.ids>314,776,780,27903,27904,75939,75947</link.rule.ids></links><search><creatorcontrib>Kim, Seojun</creatorcontrib><creatorcontrib>Yoon, Byungman</creatorcontrib><creatorcontrib>Kim, Sanghuk</creatorcontrib><creatorcontrib>Kim, Dongsu</creatorcontrib><title>Design Procedure for Determining Optimal Length of Side-Weir in Flood Control Detention Basin Considering Bed Roughness Coefficient</title><title>Journal of irrigation and drainage engineering</title><description>AbstractSide-weir detention basins have been increasingly highlighted as an alternative countermeasure for decreasing peak flood discharge and have become increasingly adopted as part of an integrated watershed flood protection plan. However, there were few methodologies sufficient enough to quantitatively estimate the decrease of the peak flow by the side-weir detention basin in flood-control measures by fully considering relevant design and hydraulic parameters. Until now, any noticeable standardized design procedure to optimally design the size of a side-weir located at the inlet of a detention basin has not been available. In this study, a generalized design procedure was proposed for determining the horizontal length of a side-weir considering hydraulic parameters, especially for the bed roughness as a major hydraulic parameter, where other hydraulic parameters were assumed to be invariant and restricted by field conditions. The proposed design procedure is exemplified based on a simple numerical model detailed herein. In particular, the design procedure considers complex overflow regimes dominated by free and submerged overflow between the main channel and detention basin through the side-weir. Subsequently, a concept for a flood control performance graph is suggested for evaluating the decrease of peak flow for design and hydraulic parameters of the side-weir, such as the bed roughness and the length of side-weir, respectively. Also, a design characteristic line is also proposed to finally determine the optimal length of side-weir.</description><subject>Technical Note</subject><subject>Technical Notes</subject><issn>0733-9437</issn><issn>1943-4774</issn><fulltext>true</fulltext><rsrctype>article</rsrctype><creationdate>2016</creationdate><recordtype>article</recordtype><recordid>eNp1kMtOAyEUhonRxHp5B-KqLqZCocyMO22tNmmiqRqXhA6HkWYKFWYWrn1xGWvcueGE81-S8yF0QcmIEkGvhjfP07vLxWpES84ynud8RAihhBQHaPC3O0QDkjOWpX9-jE5i3CQPzwkZoK8ZRFs7_BR8BboLgI0PeAYthK111tX4cdfarWrwElzdvmNv8LPVkL2BDdg6PG-813jqXRt88xN0rfUO36qY1LSPyR36olvQeOW7-t1BjEkBY2xlk_0MHRnVRDj_nafodX73Mn3Ilo_3i-nNMlMsL9tMEbYWWglD-YTqioqqEgbSU6zHWtBCC6PStWvFTE5VycZJyE1ZpIjWnBXsFA33vbvgPzqIrdzaWEHTKAe-i5IWXLBywickWa_31ir4GAMYuQuJQviUlMievJQ9eblYyZ6y7CnLX_IpLPZhldrlxnfBpbP-kv8HvwFyYIoS</recordid><startdate>20161201</startdate><enddate>20161201</enddate><creator>Kim, Seojun</creator><creator>Yoon, Byungman</creator><creator>Kim, Sanghuk</creator><creator>Kim, Dongsu</creator><general>American Society of Civil Engineers</general><scope>AAYXX</scope><scope>CITATION</scope><scope>7QH</scope><scope>7UA</scope><scope>C1K</scope><scope>F1W</scope><scope>H96</scope><scope>L.G</scope></search><sort><creationdate>20161201</creationdate><title>Design Procedure for Determining Optimal Length of Side-Weir in Flood Control Detention Basin Considering Bed Roughness Coefficient</title><author>Kim, Seojun ; Yoon, Byungman ; Kim, Sanghuk ; Kim, Dongsu</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-LOGICAL-a379t-a03b6da6f1451dc16cc6fecc68b2d618d6fa477ba3f71a93268b7f98da6dd4383</frbrgroupid><rsrctype>articles</rsrctype><prefilter>articles</prefilter><language>eng</language><creationdate>2016</creationdate><topic>Technical Note</topic><topic>Technical Notes</topic><toplevel>peer_reviewed</toplevel><toplevel>online_resources</toplevel><creatorcontrib>Kim, Seojun</creatorcontrib><creatorcontrib>Yoon, Byungman</creatorcontrib><creatorcontrib>Kim, Sanghuk</creatorcontrib><creatorcontrib>Kim, Dongsu</creatorcontrib><collection>CrossRef</collection><collection>Aqualine</collection><collection>Water Resources Abstracts</collection><collection>Environmental Sciences and Pollution Management</collection><collection>ASFA: Aquatic Sciences and Fisheries Abstracts</collection><collection>Aquatic Science &amp; Fisheries Abstracts (ASFA) 2: Ocean Technology, Policy &amp; Non-Living Resources</collection><collection>Aquatic Science &amp; Fisheries Abstracts (ASFA) Professional</collection><jtitle>Journal of irrigation and drainage engineering</jtitle></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext</fulltext></delivery><addata><au>Kim, Seojun</au><au>Yoon, Byungman</au><au>Kim, Sanghuk</au><au>Kim, Dongsu</au><format>journal</format><genre>article</genre><ristype>JOUR</ristype><atitle>Design Procedure for Determining Optimal Length of Side-Weir in Flood Control Detention Basin Considering Bed Roughness Coefficient</atitle><jtitle>Journal of irrigation and drainage engineering</jtitle><date>2016-12-01</date><risdate>2016</risdate><volume>142</volume><issue>12</issue><issn>0733-9437</issn><eissn>1943-4774</eissn><abstract>AbstractSide-weir detention basins have been increasingly highlighted as an alternative countermeasure for decreasing peak flood discharge and have become increasingly adopted as part of an integrated watershed flood protection plan. However, there were few methodologies sufficient enough to quantitatively estimate the decrease of the peak flow by the side-weir detention basin in flood-control measures by fully considering relevant design and hydraulic parameters. Until now, any noticeable standardized design procedure to optimally design the size of a side-weir located at the inlet of a detention basin has not been available. In this study, a generalized design procedure was proposed for determining the horizontal length of a side-weir considering hydraulic parameters, especially for the bed roughness as a major hydraulic parameter, where other hydraulic parameters were assumed to be invariant and restricted by field conditions. The proposed design procedure is exemplified based on a simple numerical model detailed herein. In particular, the design procedure considers complex overflow regimes dominated by free and submerged overflow between the main channel and detention basin through the side-weir. Subsequently, a concept for a flood control performance graph is suggested for evaluating the decrease of peak flow for design and hydraulic parameters of the side-weir, such as the bed roughness and the length of side-weir, respectively. Also, a design characteristic line is also proposed to finally determine the optimal length of side-weir.</abstract><pub>American Society of Civil Engineers</pub><doi>10.1061/(ASCE)IR.1943-4774.0001008</doi></addata></record>
fulltext fulltext
identifier ISSN: 0733-9437
ispartof Journal of irrigation and drainage engineering, 2016-12, Vol.142 (12)
issn 0733-9437
1943-4774
language eng
recordid cdi_proquest_miscellaneous_1846395450
source American Society of Civil Engineers:NESLI2:Journals:2014
subjects Technical Note
Technical Notes
title Design Procedure for Determining Optimal Length of Side-Weir in Flood Control Detention Basin Considering Bed Roughness Coefficient
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-25T02%3A44%3A59IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-proquest_cross&rft_val_fmt=info:ofi/fmt:kev:mtx:journal&rft.genre=article&rft.atitle=Design%20Procedure%20for%20Determining%20Optimal%20Length%20of%20Side-Weir%20in%20Flood%20Control%20Detention%20Basin%20Considering%20Bed%20Roughness%20Coefficient&rft.jtitle=Journal%20of%20irrigation%20and%20drainage%20engineering&rft.au=Kim,%20Seojun&rft.date=2016-12-01&rft.volume=142&rft.issue=12&rft.issn=0733-9437&rft.eissn=1943-4774&rft_id=info:doi/10.1061/(ASCE)IR.1943-4774.0001008&rft_dat=%3Cproquest_cross%3E1846395450%3C/proquest_cross%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_pqid=1846395450&rft_id=info:pmid/&rfr_iscdi=true