Dynamic Fleet Configuration Model for Optimizing Earthmoving Operations Using Mixed Integer Linear Programming
AbstractPractitioners in construction management primarily focus on two key indicators of project success: total cost and completion time. Heavy equipment and machinery play pivotal role in determining these measures, representing significant cost elements in various heavy construction projects such...
Gespeichert in:
Veröffentlicht in: | Journal of construction engineering and management 2024-11, Vol.150 (11) |
---|---|
Hauptverfasser: | , , , , |
Format: | Artikel |
Sprache: | eng |
Schlagworte: | |
Online-Zugang: | Volltext |
Tags: |
Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
|
container_end_page | |
---|---|
container_issue | 11 |
container_start_page | |
container_title | Journal of construction engineering and management |
container_volume | 150 |
creator | Khallaf, Zaid Alshibani, Adel Alsawafy, Omar Mohammed, Awsan Bubshait, Abdulaziz |
description | AbstractPractitioners in construction management primarily focus on two key indicators of project success: total cost and completion time. Heavy equipment and machinery play pivotal role in determining these measures, representing significant cost elements in various heavy construction projects such as road construction. Consequently, there is a pressing need for an efficient approach to determining the optimal scheduling of these heavy resources to minimize costs and shorten completion times. This paper proposes an innovative approach to address this challenge by introducing a mixed integer linear programming (MILP) model. The aim is to identify the optimal configuration for heavy equipment in earthmoving operations. The dynamic nature of the configuration process is adopted, enabling daily updates to the schedule based on the contractor’s available resources. Moreover, environmental considerations are integrated into the decision-making process, ensuring a comprehensive approach to project optimization. To demonstrate the superiority of the developed model, three case projects from the literature have been solved. The proposed model led to a significant improvement in project cost, with an average enhancement of 25%, and in completion time, with an average improvement of 50% compared with the literature case studies.
Practical ApplicationsThis paper presents a novel MILP model designed to optimize earthmoving operations, focusing on dynamic fleet configurations and emission costs. Unlike existing models, this approach provides daily fleet setups for multiple cut and fill sites, considering the contractor’s available resources. It calculates optimal soil quantities to be moved, monitors soil levels at sites, and estimates daily trips between them. In the realm of project bidding and management, this model offers valuable insights and practical applications. It empowers project managers with a robust tool for optimizing fleet configurations during bid preparation, enabling contractors to determine the most cost-effective and time-efficient setups, enhancing their competitiveness. Moreover, the model facilitates the assessment of different parameters’ impacts, such as resource additions or equipment upgrades, on project cost and completion time. This dynamic approach enables contractors to make informed decisions during project execution, ensuring projects remain on track and within budget. Additionally, by considering emission costs, the model aligns with |
doi_str_mv | 10.1061/JCEMD4.COENG-14817 |
format | Article |
fullrecord | <record><control><sourceid>proquest_cross</sourceid><recordid>TN_cdi_proquest_journals_3095580741</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>3095580741</sourcerecordid><originalsourceid>FETCH-LOGICAL-a250t-f5ef180dd86e1ed5bcc746d1565d13b5e73222db6e22916555f8785f217cb5e83</originalsourceid><addsrcrecordid>eNp9kMFOwzAMhiMEEmPwApwice6WpE3aHlHXjaGNcmDnKmudkmltStIhxtPTrUjcONmyv9-WPoTuKZlQIuj0OUnXs2CSZOnLwqNBRMMLNKJx4HthJNglGpHQ973YF8E1unFuRwgNRMxHqJkdG1nrAs_3AB1OTKN0dbCy06bBa1PCHitjcdZ2utbfuqlwKm33XpvPU5-1MKAOb9xpsNZfUOJl00EFFq90A9LiV2sqK-u6B27RlZJ7B3e_dYw28_QtefJW2WKZPK48yTjpPMVB0YiUZSSAQsm3RREGoqRc8JL6Ww6hzxgrtwIYi6ngnKsojLhiNCz6beSP0cNwt7Xm4wCuy3fmYJv-Ze6TmPOIhAHtKTZQhTXOWVB5a3Ut7TGnJD95zQev-dlrfvbah6ZDSLoC_s7-k_gB6LJ71g</addsrcrecordid><sourcetype>Aggregation Database</sourcetype><iscdi>true</iscdi><recordtype>article</recordtype><pqid>3095580741</pqid></control><display><type>article</type><title>Dynamic Fleet Configuration Model for Optimizing Earthmoving Operations Using Mixed Integer Linear Programming</title><source>American Society of Civil Engineers:NESLI2:Journals:2014</source><creator>Khallaf, Zaid ; Alshibani, Adel ; Alsawafy, Omar ; Mohammed, Awsan ; Bubshait, Abdulaziz</creator><creatorcontrib>Khallaf, Zaid ; Alshibani, Adel ; Alsawafy, Omar ; Mohammed, Awsan ; Bubshait, Abdulaziz</creatorcontrib><description>AbstractPractitioners in construction management primarily focus on two key indicators of project success: total cost and completion time. Heavy equipment and machinery play pivotal role in determining these measures, representing significant cost elements in various heavy construction projects such as road construction. Consequently, there is a pressing need for an efficient approach to determining the optimal scheduling of these heavy resources to minimize costs and shorten completion times. This paper proposes an innovative approach to address this challenge by introducing a mixed integer linear programming (MILP) model. The aim is to identify the optimal configuration for heavy equipment in earthmoving operations. The dynamic nature of the configuration process is adopted, enabling daily updates to the schedule based on the contractor’s available resources. Moreover, environmental considerations are integrated into the decision-making process, ensuring a comprehensive approach to project optimization. To demonstrate the superiority of the developed model, three case projects from the literature have been solved. The proposed model led to a significant improvement in project cost, with an average enhancement of 25%, and in completion time, with an average improvement of 50% compared with the literature case studies.
Practical ApplicationsThis paper presents a novel MILP model designed to optimize earthmoving operations, focusing on dynamic fleet configurations and emission costs. Unlike existing models, this approach provides daily fleet setups for multiple cut and fill sites, considering the contractor’s available resources. It calculates optimal soil quantities to be moved, monitors soil levels at sites, and estimates daily trips between them. In the realm of project bidding and management, this model offers valuable insights and practical applications. It empowers project managers with a robust tool for optimizing fleet configurations during bid preparation, enabling contractors to determine the most cost-effective and time-efficient setups, enhancing their competitiveness. Moreover, the model facilitates the assessment of different parameters’ impacts, such as resource additions or equipment upgrades, on project cost and completion time. This dynamic approach enables contractors to make informed decisions during project execution, ensuring projects remain on track and within budget. Additionally, by considering emission costs, the model aligns with the growing emphasis on sustainability in construction projects. Optimizing fleet configurations to minimize emissions not only reduces environmental impact but also helps contractors comply with stringent regulations and meet client demands for eco-friendly practices.</description><identifier>ISSN: 0733-9364</identifier><identifier>EISSN: 1943-7862</identifier><identifier>DOI: 10.1061/JCEMD4.COENG-14817</identifier><language>eng</language><publisher>New York: American Society of Civil Engineers</publisher><subject>Completion time ; Configuration management ; Construction management ; Earthmoving ; Earthmoving equipment ; Equipment costs ; Heavy construction ; Integer programming ; Linear programming ; Mixed integer ; Optimization ; Project management ; Resource scheduling ; Road construction ; Technical Papers ; Time measurement</subject><ispartof>Journal of construction engineering and management, 2024-11, Vol.150 (11)</ispartof><rights>2024 American Society of Civil Engineers</rights><lds50>peer_reviewed</lds50><woscitedreferencessubscribed>false</woscitedreferencessubscribed><cites>FETCH-LOGICAL-a250t-f5ef180dd86e1ed5bcc746d1565d13b5e73222db6e22916555f8785f217cb5e83</cites><orcidid>0000-0002-4059-0485 ; 0000-0003-2519-4238 ; 0000-0002-0084-1032</orcidid></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktopdf>$$Uhttp://ascelibrary.org/doi/pdf/10.1061/JCEMD4.COENG-14817$$EPDF$$P50$$Gasce$$H</linktopdf><linktohtml>$$Uhttp://ascelibrary.org/doi/abs/10.1061/JCEMD4.COENG-14817$$EHTML$$P50$$Gasce$$H</linktohtml><link.rule.ids>314,780,784,27924,27925,76193,76201</link.rule.ids></links><search><creatorcontrib>Khallaf, Zaid</creatorcontrib><creatorcontrib>Alshibani, Adel</creatorcontrib><creatorcontrib>Alsawafy, Omar</creatorcontrib><creatorcontrib>Mohammed, Awsan</creatorcontrib><creatorcontrib>Bubshait, Abdulaziz</creatorcontrib><title>Dynamic Fleet Configuration Model for Optimizing Earthmoving Operations Using Mixed Integer Linear Programming</title><title>Journal of construction engineering and management</title><description>AbstractPractitioners in construction management primarily focus on two key indicators of project success: total cost and completion time. Heavy equipment and machinery play pivotal role in determining these measures, representing significant cost elements in various heavy construction projects such as road construction. Consequently, there is a pressing need for an efficient approach to determining the optimal scheduling of these heavy resources to minimize costs and shorten completion times. This paper proposes an innovative approach to address this challenge by introducing a mixed integer linear programming (MILP) model. The aim is to identify the optimal configuration for heavy equipment in earthmoving operations. The dynamic nature of the configuration process is adopted, enabling daily updates to the schedule based on the contractor’s available resources. Moreover, environmental considerations are integrated into the decision-making process, ensuring a comprehensive approach to project optimization. To demonstrate the superiority of the developed model, three case projects from the literature have been solved. The proposed model led to a significant improvement in project cost, with an average enhancement of 25%, and in completion time, with an average improvement of 50% compared with the literature case studies.
Practical ApplicationsThis paper presents a novel MILP model designed to optimize earthmoving operations, focusing on dynamic fleet configurations and emission costs. Unlike existing models, this approach provides daily fleet setups for multiple cut and fill sites, considering the contractor’s available resources. It calculates optimal soil quantities to be moved, monitors soil levels at sites, and estimates daily trips between them. In the realm of project bidding and management, this model offers valuable insights and practical applications. It empowers project managers with a robust tool for optimizing fleet configurations during bid preparation, enabling contractors to determine the most cost-effective and time-efficient setups, enhancing their competitiveness. Moreover, the model facilitates the assessment of different parameters’ impacts, such as resource additions or equipment upgrades, on project cost and completion time. This dynamic approach enables contractors to make informed decisions during project execution, ensuring projects remain on track and within budget. Additionally, by considering emission costs, the model aligns with the growing emphasis on sustainability in construction projects. Optimizing fleet configurations to minimize emissions not only reduces environmental impact but also helps contractors comply with stringent regulations and meet client demands for eco-friendly practices.</description><subject>Completion time</subject><subject>Configuration management</subject><subject>Construction management</subject><subject>Earthmoving</subject><subject>Earthmoving equipment</subject><subject>Equipment costs</subject><subject>Heavy construction</subject><subject>Integer programming</subject><subject>Linear programming</subject><subject>Mixed integer</subject><subject>Optimization</subject><subject>Project management</subject><subject>Resource scheduling</subject><subject>Road construction</subject><subject>Technical Papers</subject><subject>Time measurement</subject><issn>0733-9364</issn><issn>1943-7862</issn><fulltext>true</fulltext><rsrctype>article</rsrctype><creationdate>2024</creationdate><recordtype>article</recordtype><recordid>eNp9kMFOwzAMhiMEEmPwApwice6WpE3aHlHXjaGNcmDnKmudkmltStIhxtPTrUjcONmyv9-WPoTuKZlQIuj0OUnXs2CSZOnLwqNBRMMLNKJx4HthJNglGpHQ973YF8E1unFuRwgNRMxHqJkdG1nrAs_3AB1OTKN0dbCy06bBa1PCHitjcdZ2utbfuqlwKm33XpvPU5-1MKAOb9xpsNZfUOJl00EFFq90A9LiV2sqK-u6B27RlZJ7B3e_dYw28_QtefJW2WKZPK48yTjpPMVB0YiUZSSAQsm3RREGoqRc8JL6Ww6hzxgrtwIYi6ngnKsojLhiNCz6beSP0cNwt7Xm4wCuy3fmYJv-Ze6TmPOIhAHtKTZQhTXOWVB5a3Ut7TGnJD95zQev-dlrfvbah6ZDSLoC_s7-k_gB6LJ71g</recordid><startdate>20241101</startdate><enddate>20241101</enddate><creator>Khallaf, Zaid</creator><creator>Alshibani, Adel</creator><creator>Alsawafy, Omar</creator><creator>Mohammed, Awsan</creator><creator>Bubshait, Abdulaziz</creator><general>American Society of Civil Engineers</general><scope>AAYXX</scope><scope>CITATION</scope><scope>8FD</scope><scope>FR3</scope><scope>KR7</scope><orcidid>https://orcid.org/0000-0002-4059-0485</orcidid><orcidid>https://orcid.org/0000-0003-2519-4238</orcidid><orcidid>https://orcid.org/0000-0002-0084-1032</orcidid></search><sort><creationdate>20241101</creationdate><title>Dynamic Fleet Configuration Model for Optimizing Earthmoving Operations Using Mixed Integer Linear Programming</title><author>Khallaf, Zaid ; Alshibani, Adel ; Alsawafy, Omar ; Mohammed, Awsan ; Bubshait, Abdulaziz</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-LOGICAL-a250t-f5ef180dd86e1ed5bcc746d1565d13b5e73222db6e22916555f8785f217cb5e83</frbrgroupid><rsrctype>articles</rsrctype><prefilter>articles</prefilter><language>eng</language><creationdate>2024</creationdate><topic>Completion time</topic><topic>Configuration management</topic><topic>Construction management</topic><topic>Earthmoving</topic><topic>Earthmoving equipment</topic><topic>Equipment costs</topic><topic>Heavy construction</topic><topic>Integer programming</topic><topic>Linear programming</topic><topic>Mixed integer</topic><topic>Optimization</topic><topic>Project management</topic><topic>Resource scheduling</topic><topic>Road construction</topic><topic>Technical Papers</topic><topic>Time measurement</topic><toplevel>peer_reviewed</toplevel><toplevel>online_resources</toplevel><creatorcontrib>Khallaf, Zaid</creatorcontrib><creatorcontrib>Alshibani, Adel</creatorcontrib><creatorcontrib>Alsawafy, Omar</creatorcontrib><creatorcontrib>Mohammed, Awsan</creatorcontrib><creatorcontrib>Bubshait, Abdulaziz</creatorcontrib><collection>CrossRef</collection><collection>Technology Research Database</collection><collection>Engineering Research Database</collection><collection>Civil Engineering Abstracts</collection><jtitle>Journal of construction engineering and management</jtitle></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext</fulltext></delivery><addata><au>Khallaf, Zaid</au><au>Alshibani, Adel</au><au>Alsawafy, Omar</au><au>Mohammed, Awsan</au><au>Bubshait, Abdulaziz</au><format>journal</format><genre>article</genre><ristype>JOUR</ristype><atitle>Dynamic Fleet Configuration Model for Optimizing Earthmoving Operations Using Mixed Integer Linear Programming</atitle><jtitle>Journal of construction engineering and management</jtitle><date>2024-11-01</date><risdate>2024</risdate><volume>150</volume><issue>11</issue><issn>0733-9364</issn><eissn>1943-7862</eissn><abstract>AbstractPractitioners in construction management primarily focus on two key indicators of project success: total cost and completion time. Heavy equipment and machinery play pivotal role in determining these measures, representing significant cost elements in various heavy construction projects such as road construction. Consequently, there is a pressing need for an efficient approach to determining the optimal scheduling of these heavy resources to minimize costs and shorten completion times. This paper proposes an innovative approach to address this challenge by introducing a mixed integer linear programming (MILP) model. The aim is to identify the optimal configuration for heavy equipment in earthmoving operations. The dynamic nature of the configuration process is adopted, enabling daily updates to the schedule based on the contractor’s available resources. Moreover, environmental considerations are integrated into the decision-making process, ensuring a comprehensive approach to project optimization. To demonstrate the superiority of the developed model, three case projects from the literature have been solved. The proposed model led to a significant improvement in project cost, with an average enhancement of 25%, and in completion time, with an average improvement of 50% compared with the literature case studies.
Practical ApplicationsThis paper presents a novel MILP model designed to optimize earthmoving operations, focusing on dynamic fleet configurations and emission costs. Unlike existing models, this approach provides daily fleet setups for multiple cut and fill sites, considering the contractor’s available resources. It calculates optimal soil quantities to be moved, monitors soil levels at sites, and estimates daily trips between them. In the realm of project bidding and management, this model offers valuable insights and practical applications. It empowers project managers with a robust tool for optimizing fleet configurations during bid preparation, enabling contractors to determine the most cost-effective and time-efficient setups, enhancing their competitiveness. Moreover, the model facilitates the assessment of different parameters’ impacts, such as resource additions or equipment upgrades, on project cost and completion time. This dynamic approach enables contractors to make informed decisions during project execution, ensuring projects remain on track and within budget. Additionally, by considering emission costs, the model aligns with the growing emphasis on sustainability in construction projects. Optimizing fleet configurations to minimize emissions not only reduces environmental impact but also helps contractors comply with stringent regulations and meet client demands for eco-friendly practices.</abstract><cop>New York</cop><pub>American Society of Civil Engineers</pub><doi>10.1061/JCEMD4.COENG-14817</doi><orcidid>https://orcid.org/0000-0002-4059-0485</orcidid><orcidid>https://orcid.org/0000-0003-2519-4238</orcidid><orcidid>https://orcid.org/0000-0002-0084-1032</orcidid></addata></record> |
fulltext | fulltext |
identifier | ISSN: 0733-9364 |
ispartof | Journal of construction engineering and management, 2024-11, Vol.150 (11) |
issn | 0733-9364 1943-7862 |
language | eng |
recordid | cdi_proquest_journals_3095580741 |
source | American Society of Civil Engineers:NESLI2:Journals:2014 |
subjects | Completion time Configuration management Construction management Earthmoving Earthmoving equipment Equipment costs Heavy construction Integer programming Linear programming Mixed integer Optimization Project management Resource scheduling Road construction Technical Papers Time measurement |
title | Dynamic Fleet Configuration Model for Optimizing Earthmoving Operations Using Mixed Integer Linear Programming |
url | https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-07T05%3A36%3A24IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-proquest_cross&rft_val_fmt=info:ofi/fmt:kev:mtx:journal&rft.genre=article&rft.atitle=Dynamic%20Fleet%20Configuration%20Model%20for%20Optimizing%20Earthmoving%20Operations%20Using%20Mixed%20Integer%20Linear%20Programming&rft.jtitle=Journal%20of%20construction%20engineering%20and%20management&rft.au=Khallaf,%20Zaid&rft.date=2024-11-01&rft.volume=150&rft.issue=11&rft.issn=0733-9364&rft.eissn=1943-7862&rft_id=info:doi/10.1061/JCEMD4.COENG-14817&rft_dat=%3Cproquest_cross%3E3095580741%3C/proquest_cross%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_pqid=3095580741&rft_id=info:pmid/&rfr_iscdi=true |