Automated scheduling and control of mechanical and electrical works with BIM
Current planning tools provide insufficient support for the scheduling and control of Mechanical and Electrical works in construction projects. Consequently, installation activities often deviate from project plans. However, BIM data on the spatial layout of Mechanical and Electrical systems can be...
Gespeichert in:
Veröffentlicht in: | Automation in construction 2021-04, Vol.124, p.103600, Article 103600 |
---|---|
Hauptverfasser: | , |
Format: | Artikel |
Sprache: | eng |
Schlagworte: | |
Online-Zugang: | Volltext |
Tags: |
Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
|
container_end_page | |
---|---|
container_issue | |
container_start_page | 103600 |
container_title | Automation in construction |
container_volume | 124 |
creator | Isaac, Shabtai Shimanovich, Maxim |
description | Current planning tools provide insufficient support for the scheduling and control of Mechanical and Electrical works in construction projects. Consequently, installation activities often deviate from project plans. However, BIM data on the spatial layout of Mechanical and Electrical systems can be used for more detailed and accurate planning of their installation, and to identify points where work progress should be tracked. This paper presents a novel method for the automated scheduling and control of Mechanical and Electrical Works. A topological analysis of the precise position of components is used to define relationships between the installation tasks, and to identify the optimal schedule. The definition of specific control points supports effective progress tracking to ensure that tasks adhere in practice to this schedule.
•A novel method is presented for automated scheduling and control of M&E Works.•BIM is used for a topological analysis of the components' precise positions.•Relationships between tasks are then defined based on the topological analysis.•The optimal schedule is identified taking into account constraints such as resources.•Control points in the schedule support effective progress tracking. |
doi_str_mv | 10.1016/j.autcon.2021.103600 |
format | Article |
fullrecord | <record><control><sourceid>proquest_cross</sourceid><recordid>TN_cdi_proquest_journals_2505721883</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><els_id>S0926580521000510</els_id><sourcerecordid>2505721883</sourcerecordid><originalsourceid>FETCH-LOGICAL-c334t-195f2f3f937bcb5986b4fc4747b0236109de54913c6814410e09ac955373ff7d3</originalsourceid><addsrcrecordid>eNp9kMtOwzAQRS0EEqXwBywisU4Zv-J4g1QqHpWK2MDaShybuqRxsR0q_p60Yc1qNDN37ugehK4xzDDg4nYzq_qkfTcjQPAwogXACZrgUpBclBKfoglIUuS8BH6OLmLcAICAQk7Qat4nv62SabKo16bpW9d9ZFXXZINfCr7NvM22Rq-rzumqPW5Ma3QKx3bvw2fM9i6ts_vlyyU6s1UbzdVfnaL3x4e3xXO-en1aLuarXFPKUo4lt8RSK6modc1lWdTMaiaYqIHQAoNsDGcSU12UmDEMBmSlJedUUGtFQ6foZvTdBf_Vm5jUxvehG14qwoELgsuSDio2qnTwMQZj1S64bRV-FAZ14KY2auSmDtzUyG04uxvPzJDg25mgonam06ZxYcitGu_-N_gFDLF2vg</addsrcrecordid><sourcetype>Aggregation Database</sourcetype><iscdi>true</iscdi><recordtype>article</recordtype><pqid>2505721883</pqid></control><display><type>article</type><title>Automated scheduling and control of mechanical and electrical works with BIM</title><source>Elsevier ScienceDirect Journals</source><creator>Isaac, Shabtai ; Shimanovich, Maxim</creator><creatorcontrib>Isaac, Shabtai ; Shimanovich, Maxim</creatorcontrib><description>Current planning tools provide insufficient support for the scheduling and control of Mechanical and Electrical works in construction projects. Consequently, installation activities often deviate from project plans. However, BIM data on the spatial layout of Mechanical and Electrical systems can be used for more detailed and accurate planning of their installation, and to identify points where work progress should be tracked. This paper presents a novel method for the automated scheduling and control of Mechanical and Electrical Works. A topological analysis of the precise position of components is used to define relationships between the installation tasks, and to identify the optimal schedule. The definition of specific control points supports effective progress tracking to ensure that tasks adhere in practice to this schedule.
•A novel method is presented for automated scheduling and control of M&E Works.•BIM is used for a topological analysis of the components' precise positions.•Relationships between tasks are then defined based on the topological analysis.•The optimal schedule is identified taking into account constraints such as resources.•Control points in the schedule support effective progress tracking.</description><identifier>ISSN: 0926-5805</identifier><identifier>EISSN: 1872-7891</identifier><identifier>DOI: 10.1016/j.autcon.2021.103600</identifier><language>eng</language><publisher>Amsterdam: Elsevier B.V</publisher><subject>Automatic control ; Automation ; BIM ; Mechanical and electrical works ; Optimization ; Schedules ; Scheduling ; Task scheduling</subject><ispartof>Automation in construction, 2021-04, Vol.124, p.103600, Article 103600</ispartof><rights>2021 Elsevier B.V.</rights><rights>Copyright Elsevier BV Apr 2021</rights><lds50>peer_reviewed</lds50><woscitedreferencessubscribed>false</woscitedreferencessubscribed><citedby>FETCH-LOGICAL-c334t-195f2f3f937bcb5986b4fc4747b0236109de54913c6814410e09ac955373ff7d3</citedby><cites>FETCH-LOGICAL-c334t-195f2f3f937bcb5986b4fc4747b0236109de54913c6814410e09ac955373ff7d3</cites></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://www.sciencedirect.com/science/article/pii/S0926580521000510$$EHTML$$P50$$Gelsevier$$H</linktohtml><link.rule.ids>314,776,780,3537,27901,27902,65306</link.rule.ids></links><search><creatorcontrib>Isaac, Shabtai</creatorcontrib><creatorcontrib>Shimanovich, Maxim</creatorcontrib><title>Automated scheduling and control of mechanical and electrical works with BIM</title><title>Automation in construction</title><description>Current planning tools provide insufficient support for the scheduling and control of Mechanical and Electrical works in construction projects. Consequently, installation activities often deviate from project plans. However, BIM data on the spatial layout of Mechanical and Electrical systems can be used for more detailed and accurate planning of their installation, and to identify points where work progress should be tracked. This paper presents a novel method for the automated scheduling and control of Mechanical and Electrical Works. A topological analysis of the precise position of components is used to define relationships between the installation tasks, and to identify the optimal schedule. The definition of specific control points supports effective progress tracking to ensure that tasks adhere in practice to this schedule.
•A novel method is presented for automated scheduling and control of M&E Works.•BIM is used for a topological analysis of the components' precise positions.•Relationships between tasks are then defined based on the topological analysis.•The optimal schedule is identified taking into account constraints such as resources.•Control points in the schedule support effective progress tracking.</description><subject>Automatic control</subject><subject>Automation</subject><subject>BIM</subject><subject>Mechanical and electrical works</subject><subject>Optimization</subject><subject>Schedules</subject><subject>Scheduling</subject><subject>Task scheduling</subject><issn>0926-5805</issn><issn>1872-7891</issn><fulltext>true</fulltext><rsrctype>article</rsrctype><creationdate>2021</creationdate><recordtype>article</recordtype><recordid>eNp9kMtOwzAQRS0EEqXwBywisU4Zv-J4g1QqHpWK2MDaShybuqRxsR0q_p60Yc1qNDN37ugehK4xzDDg4nYzq_qkfTcjQPAwogXACZrgUpBclBKfoglIUuS8BH6OLmLcAICAQk7Qat4nv62SabKo16bpW9d9ZFXXZINfCr7NvM22Rq-rzumqPW5Ma3QKx3bvw2fM9i6ts_vlyyU6s1UbzdVfnaL3x4e3xXO-en1aLuarXFPKUo4lt8RSK6modc1lWdTMaiaYqIHQAoNsDGcSU12UmDEMBmSlJedUUGtFQ6foZvTdBf_Vm5jUxvehG14qwoELgsuSDio2qnTwMQZj1S64bRV-FAZ14KY2auSmDtzUyG04uxvPzJDg25mgonam06ZxYcitGu_-N_gFDLF2vg</recordid><startdate>202104</startdate><enddate>202104</enddate><creator>Isaac, Shabtai</creator><creator>Shimanovich, Maxim</creator><general>Elsevier B.V</general><general>Elsevier BV</general><scope>AAYXX</scope><scope>CITATION</scope><scope>7SC</scope><scope>7SP</scope><scope>8FD</scope><scope>FR3</scope><scope>JQ2</scope><scope>KR7</scope><scope>L7M</scope><scope>L~C</scope><scope>L~D</scope></search><sort><creationdate>202104</creationdate><title>Automated scheduling and control of mechanical and electrical works with BIM</title><author>Isaac, Shabtai ; Shimanovich, Maxim</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-LOGICAL-c334t-195f2f3f937bcb5986b4fc4747b0236109de54913c6814410e09ac955373ff7d3</frbrgroupid><rsrctype>articles</rsrctype><prefilter>articles</prefilter><language>eng</language><creationdate>2021</creationdate><topic>Automatic control</topic><topic>Automation</topic><topic>BIM</topic><topic>Mechanical and electrical works</topic><topic>Optimization</topic><topic>Schedules</topic><topic>Scheduling</topic><topic>Task scheduling</topic><toplevel>peer_reviewed</toplevel><toplevel>online_resources</toplevel><creatorcontrib>Isaac, Shabtai</creatorcontrib><creatorcontrib>Shimanovich, Maxim</creatorcontrib><collection>CrossRef</collection><collection>Computer and Information Systems Abstracts</collection><collection>Electronics & Communications Abstracts</collection><collection>Technology Research Database</collection><collection>Engineering Research Database</collection><collection>ProQuest Computer Science Collection</collection><collection>Civil Engineering Abstracts</collection><collection>Advanced Technologies Database with Aerospace</collection><collection>Computer and Information Systems Abstracts Academic</collection><collection>Computer and Information Systems Abstracts Professional</collection><jtitle>Automation in construction</jtitle></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext</fulltext></delivery><addata><au>Isaac, Shabtai</au><au>Shimanovich, Maxim</au><format>journal</format><genre>article</genre><ristype>JOUR</ristype><atitle>Automated scheduling and control of mechanical and electrical works with BIM</atitle><jtitle>Automation in construction</jtitle><date>2021-04</date><risdate>2021</risdate><volume>124</volume><spage>103600</spage><pages>103600-</pages><artnum>103600</artnum><issn>0926-5805</issn><eissn>1872-7891</eissn><abstract>Current planning tools provide insufficient support for the scheduling and control of Mechanical and Electrical works in construction projects. Consequently, installation activities often deviate from project plans. However, BIM data on the spatial layout of Mechanical and Electrical systems can be used for more detailed and accurate planning of their installation, and to identify points where work progress should be tracked. This paper presents a novel method for the automated scheduling and control of Mechanical and Electrical Works. A topological analysis of the precise position of components is used to define relationships between the installation tasks, and to identify the optimal schedule. The definition of specific control points supports effective progress tracking to ensure that tasks adhere in practice to this schedule.
•A novel method is presented for automated scheduling and control of M&E Works.•BIM is used for a topological analysis of the components' precise positions.•Relationships between tasks are then defined based on the topological analysis.•The optimal schedule is identified taking into account constraints such as resources.•Control points in the schedule support effective progress tracking.</abstract><cop>Amsterdam</cop><pub>Elsevier B.V</pub><doi>10.1016/j.autcon.2021.103600</doi></addata></record> |
fulltext | fulltext |
identifier | ISSN: 0926-5805 |
ispartof | Automation in construction, 2021-04, Vol.124, p.103600, Article 103600 |
issn | 0926-5805 1872-7891 |
language | eng |
recordid | cdi_proquest_journals_2505721883 |
source | Elsevier ScienceDirect Journals |
subjects | Automatic control Automation BIM Mechanical and electrical works Optimization Schedules Scheduling Task scheduling |
title | Automated scheduling and control of mechanical and electrical works with BIM |
url | https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-02-03T10%3A47%3A12IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-proquest_cross&rft_val_fmt=info:ofi/fmt:kev:mtx:journal&rft.genre=article&rft.atitle=Automated%20scheduling%20and%20control%20of%20mechanical%20and%20electrical%20works%20with%20BIM&rft.jtitle=Automation%20in%20construction&rft.au=Isaac,%20Shabtai&rft.date=2021-04&rft.volume=124&rft.spage=103600&rft.pages=103600-&rft.artnum=103600&rft.issn=0926-5805&rft.eissn=1872-7891&rft_id=info:doi/10.1016/j.autcon.2021.103600&rft_dat=%3Cproquest_cross%3E2505721883%3C/proquest_cross%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_pqid=2505721883&rft_id=info:pmid/&rft_els_id=S0926580521000510&rfr_iscdi=true |