Error Propagation Model for Analyzing Project Labor Cost Budget Risks in Industrial Construction

AbstractIndustrial construction employs various trades in large-scale prefabrication operations to produce modules and structural components at an offsite facility that will be shipped to the field for rapid installation. Developing an analytical methodology for characterizing the effect of variabil...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Veröffentlicht in:Journal of construction engineering and management 2021-04, Vol.147 (4)
Hauptverfasser: Hasan, Monjurul, Lu, Ming
Format: Artikel
Sprache:eng
Schlagworte:
Online-Zugang:Volltext
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue 4
container_start_page
container_title Journal of construction engineering and management
container_volume 147
creator Hasan, Monjurul
Lu, Ming
description AbstractIndustrial construction employs various trades in large-scale prefabrication operations to produce modules and structural components at an offsite facility that will be shipped to the field for rapid installation. Developing an analytical methodology for characterizing the effect of variability in productivity on labor cost budgeting is vital to this particular construction type. Integrating current practices of estimating, scheduling, and budgeting in industrial construction, this paper describes an error propagation model for calculating the standard deviation of the cumulative labor hours at particular time points of the project duration and establishing a confidence interval around the average value. Analogous to plotting an S-curve, the lower bound and upper bound of the interval for cumulative labor hours budgeted at control points along the project duration can be articulated to form the S-stripe, which visually portrays the risk of labor cost budget due to risks inherent in labor productivity. The application and verification of the proposed analytical methodology are illustrated with a steel fabrication project case. Monte Carlo simulation is applied to the same project data in the case study, resulting in a near-perfect correlation between the two sets of results. In the simulation experiment design, determining the minimum number of simulation runs that are deemed sufficient to obtain reliable sampling results entails trial and error, and the obtained result is case-specific. In contrast, the proposed analytical method circumvents this barrier by analytically deriving the project labor cost budget in the form of an S-stripe.
doi_str_mv 10.1061/(ASCE)CO.1943-7862.0002010
format Article
fullrecord <record><control><sourceid>proquest_cross</sourceid><recordid>TN_cdi_proquest_journals_2478924767</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>2478924767</sourcerecordid><originalsourceid>FETCH-LOGICAL-a390t-d5228320b5870833c55e490919286c717c551f9d6d1f79277398e9af8420522f3</originalsourceid><addsrcrecordid>eNp1kMlOwzAURS0EEqXwDxZsYJHybCce2JWoDFJREcPauIlTpZS42MmifD2OWmDFxrbue-dKPgidEhgR4OTyfPycTy7y2YiolCVCcjoCAAoE9tDgN9tHAxCMJYrx9BAdhbAEIClX2QC9Tbx3Hj96tzYL09auwQ-utCtcxXTcmNXmq24W_XxpixZPzTzmuQstvu7KhW3xUx3eA64bfN-UXWh9bVZx3sRXV_R1x-igMqtgT3b3EL3eTF7yu2Q6u73Px9PEMAVtUmaUSkZhnkkBkrEiy2yqQBFFJS8EETEglSp5SSqhqBBMSatMJVMKEa3YEJ1te9fefXY2tHrpOh8_EDRNhVTx4CJuXW23Cu9C8LbSa19_GL_RBHRvVOveqM5nurene3t6ZzTCfAubUNi_-h_yf_AbTC95DA</addsrcrecordid><sourcetype>Aggregation Database</sourcetype><iscdi>true</iscdi><recordtype>article</recordtype><pqid>2478924767</pqid></control><display><type>article</type><title>Error Propagation Model for Analyzing Project Labor Cost Budget Risks in Industrial Construction</title><source>American Society of Civil Engineers:NESLI2:Journals:2014</source><creator>Hasan, Monjurul ; Lu, Ming</creator><creatorcontrib>Hasan, Monjurul ; Lu, Ming</creatorcontrib><description>AbstractIndustrial construction employs various trades in large-scale prefabrication operations to produce modules and structural components at an offsite facility that will be shipped to the field for rapid installation. Developing an analytical methodology for characterizing the effect of variability in productivity on labor cost budgeting is vital to this particular construction type. Integrating current practices of estimating, scheduling, and budgeting in industrial construction, this paper describes an error propagation model for calculating the standard deviation of the cumulative labor hours at particular time points of the project duration and establishing a confidence interval around the average value. Analogous to plotting an S-curve, the lower bound and upper bound of the interval for cumulative labor hours budgeted at control points along the project duration can be articulated to form the S-stripe, which visually portrays the risk of labor cost budget due to risks inherent in labor productivity. The application and verification of the proposed analytical methodology are illustrated with a steel fabrication project case. Monte Carlo simulation is applied to the same project data in the case study, resulting in a near-perfect correlation between the two sets of results. In the simulation experiment design, determining the minimum number of simulation runs that are deemed sufficient to obtain reliable sampling results entails trial and error, and the obtained result is case-specific. In contrast, the proposed analytical method circumvents this barrier by analytically deriving the project labor cost budget in the form of an S-stripe.</description><identifier>ISSN: 0733-9364</identifier><identifier>EISSN: 1943-7862</identifier><identifier>DOI: 10.1061/(ASCE)CO.1943-7862.0002010</identifier><language>eng</language><publisher>New York: American Society of Civil Engineers</publisher><subject>Budgeting ; Budgets ; Confidence intervals ; Correlation analysis ; Cost analysis ; Design of experiments ; Error analysis ; Labor ; Labor costs ; Labor economics ; Lower bounds ; Mathematical analysis ; Monte Carlo simulation ; Prefabrication ; Productivity ; Propagation ; S curves ; Simulation ; Technical Papers ; Upper bounds</subject><ispartof>Journal of construction engineering and management, 2021-04, Vol.147 (4)</ispartof><rights>2021 American Society of Civil Engineers</rights><lds50>peer_reviewed</lds50><woscitedreferencessubscribed>false</woscitedreferencessubscribed><citedby>FETCH-LOGICAL-a390t-d5228320b5870833c55e490919286c717c551f9d6d1f79277398e9af8420522f3</citedby><cites>FETCH-LOGICAL-a390t-d5228320b5870833c55e490919286c717c551f9d6d1f79277398e9af8420522f3</cites><orcidid>0000-0002-8191-8627 ; 0000-0003-2066-7948</orcidid></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktopdf>$$Uhttp://ascelibrary.org/doi/pdf/10.1061/(ASCE)CO.1943-7862.0002010$$EPDF$$P50$$Gasce$$H</linktopdf><linktohtml>$$Uhttp://ascelibrary.org/doi/abs/10.1061/(ASCE)CO.1943-7862.0002010$$EHTML$$P50$$Gasce$$H</linktohtml><link.rule.ids>314,776,780,27901,27902,75935,75943</link.rule.ids></links><search><creatorcontrib>Hasan, Monjurul</creatorcontrib><creatorcontrib>Lu, Ming</creatorcontrib><title>Error Propagation Model for Analyzing Project Labor Cost Budget Risks in Industrial Construction</title><title>Journal of construction engineering and management</title><description>AbstractIndustrial construction employs various trades in large-scale prefabrication operations to produce modules and structural components at an offsite facility that will be shipped to the field for rapid installation. Developing an analytical methodology for characterizing the effect of variability in productivity on labor cost budgeting is vital to this particular construction type. Integrating current practices of estimating, scheduling, and budgeting in industrial construction, this paper describes an error propagation model for calculating the standard deviation of the cumulative labor hours at particular time points of the project duration and establishing a confidence interval around the average value. Analogous to plotting an S-curve, the lower bound and upper bound of the interval for cumulative labor hours budgeted at control points along the project duration can be articulated to form the S-stripe, which visually portrays the risk of labor cost budget due to risks inherent in labor productivity. The application and verification of the proposed analytical methodology are illustrated with a steel fabrication project case. Monte Carlo simulation is applied to the same project data in the case study, resulting in a near-perfect correlation between the two sets of results. In the simulation experiment design, determining the minimum number of simulation runs that are deemed sufficient to obtain reliable sampling results entails trial and error, and the obtained result is case-specific. In contrast, the proposed analytical method circumvents this barrier by analytically deriving the project labor cost budget in the form of an S-stripe.</description><subject>Budgeting</subject><subject>Budgets</subject><subject>Confidence intervals</subject><subject>Correlation analysis</subject><subject>Cost analysis</subject><subject>Design of experiments</subject><subject>Error analysis</subject><subject>Labor</subject><subject>Labor costs</subject><subject>Labor economics</subject><subject>Lower bounds</subject><subject>Mathematical analysis</subject><subject>Monte Carlo simulation</subject><subject>Prefabrication</subject><subject>Productivity</subject><subject>Propagation</subject><subject>S curves</subject><subject>Simulation</subject><subject>Technical Papers</subject><subject>Upper bounds</subject><issn>0733-9364</issn><issn>1943-7862</issn><fulltext>true</fulltext><rsrctype>article</rsrctype><creationdate>2021</creationdate><recordtype>article</recordtype><recordid>eNp1kMlOwzAURS0EEqXwDxZsYJHybCce2JWoDFJREcPauIlTpZS42MmifD2OWmDFxrbue-dKPgidEhgR4OTyfPycTy7y2YiolCVCcjoCAAoE9tDgN9tHAxCMJYrx9BAdhbAEIClX2QC9Tbx3Hj96tzYL09auwQ-utCtcxXTcmNXmq24W_XxpixZPzTzmuQstvu7KhW3xUx3eA64bfN-UXWh9bVZx3sRXV_R1x-igMqtgT3b3EL3eTF7yu2Q6u73Px9PEMAVtUmaUSkZhnkkBkrEiy2yqQBFFJS8EETEglSp5SSqhqBBMSatMJVMKEa3YEJ1te9fefXY2tHrpOh8_EDRNhVTx4CJuXW23Cu9C8LbSa19_GL_RBHRvVOveqM5nurene3t6ZzTCfAubUNi_-h_yf_AbTC95DA</recordid><startdate>20210401</startdate><enddate>20210401</enddate><creator>Hasan, Monjurul</creator><creator>Lu, Ming</creator><general>American Society of Civil Engineers</general><scope>AAYXX</scope><scope>CITATION</scope><scope>8FD</scope><scope>FR3</scope><scope>KR7</scope><orcidid>https://orcid.org/0000-0002-8191-8627</orcidid><orcidid>https://orcid.org/0000-0003-2066-7948</orcidid></search><sort><creationdate>20210401</creationdate><title>Error Propagation Model for Analyzing Project Labor Cost Budget Risks in Industrial Construction</title><author>Hasan, Monjurul ; Lu, Ming</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-LOGICAL-a390t-d5228320b5870833c55e490919286c717c551f9d6d1f79277398e9af8420522f3</frbrgroupid><rsrctype>articles</rsrctype><prefilter>articles</prefilter><language>eng</language><creationdate>2021</creationdate><topic>Budgeting</topic><topic>Budgets</topic><topic>Confidence intervals</topic><topic>Correlation analysis</topic><topic>Cost analysis</topic><topic>Design of experiments</topic><topic>Error analysis</topic><topic>Labor</topic><topic>Labor costs</topic><topic>Labor economics</topic><topic>Lower bounds</topic><topic>Mathematical analysis</topic><topic>Monte Carlo simulation</topic><topic>Prefabrication</topic><topic>Productivity</topic><topic>Propagation</topic><topic>S curves</topic><topic>Simulation</topic><topic>Technical Papers</topic><topic>Upper bounds</topic><toplevel>peer_reviewed</toplevel><toplevel>online_resources</toplevel><creatorcontrib>Hasan, Monjurul</creatorcontrib><creatorcontrib>Lu, Ming</creatorcontrib><collection>CrossRef</collection><collection>Technology Research Database</collection><collection>Engineering Research Database</collection><collection>Civil Engineering Abstracts</collection><jtitle>Journal of construction engineering and management</jtitle></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext</fulltext></delivery><addata><au>Hasan, Monjurul</au><au>Lu, Ming</au><format>journal</format><genre>article</genre><ristype>JOUR</ristype><atitle>Error Propagation Model for Analyzing Project Labor Cost Budget Risks in Industrial Construction</atitle><jtitle>Journal of construction engineering and management</jtitle><date>2021-04-01</date><risdate>2021</risdate><volume>147</volume><issue>4</issue><issn>0733-9364</issn><eissn>1943-7862</eissn><abstract>AbstractIndustrial construction employs various trades in large-scale prefabrication operations to produce modules and structural components at an offsite facility that will be shipped to the field for rapid installation. Developing an analytical methodology for characterizing the effect of variability in productivity on labor cost budgeting is vital to this particular construction type. Integrating current practices of estimating, scheduling, and budgeting in industrial construction, this paper describes an error propagation model for calculating the standard deviation of the cumulative labor hours at particular time points of the project duration and establishing a confidence interval around the average value. Analogous to plotting an S-curve, the lower bound and upper bound of the interval for cumulative labor hours budgeted at control points along the project duration can be articulated to form the S-stripe, which visually portrays the risk of labor cost budget due to risks inherent in labor productivity. The application and verification of the proposed analytical methodology are illustrated with a steel fabrication project case. Monte Carlo simulation is applied to the same project data in the case study, resulting in a near-perfect correlation between the two sets of results. In the simulation experiment design, determining the minimum number of simulation runs that are deemed sufficient to obtain reliable sampling results entails trial and error, and the obtained result is case-specific. In contrast, the proposed analytical method circumvents this barrier by analytically deriving the project labor cost budget in the form of an S-stripe.</abstract><cop>New York</cop><pub>American Society of Civil Engineers</pub><doi>10.1061/(ASCE)CO.1943-7862.0002010</doi><orcidid>https://orcid.org/0000-0002-8191-8627</orcidid><orcidid>https://orcid.org/0000-0003-2066-7948</orcidid></addata></record>
fulltext fulltext
identifier ISSN: 0733-9364
ispartof Journal of construction engineering and management, 2021-04, Vol.147 (4)
issn 0733-9364
1943-7862
language eng
recordid cdi_proquest_journals_2478924767
source American Society of Civil Engineers:NESLI2:Journals:2014
subjects Budgeting
Budgets
Confidence intervals
Correlation analysis
Cost analysis
Design of experiments
Error analysis
Labor
Labor costs
Labor economics
Lower bounds
Mathematical analysis
Monte Carlo simulation
Prefabrication
Productivity
Propagation
S curves
Simulation
Technical Papers
Upper bounds
title Error Propagation Model for Analyzing Project Labor Cost Budget Risks in Industrial Construction
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-02-08T20%3A43%3A40IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-proquest_cross&rft_val_fmt=info:ofi/fmt:kev:mtx:journal&rft.genre=article&rft.atitle=Error%20Propagation%20Model%20for%20Analyzing%20Project%20Labor%20Cost%20Budget%20Risks%20in%20Industrial%20Construction&rft.jtitle=Journal%20of%20construction%20engineering%20and%20management&rft.au=Hasan,%20Monjurul&rft.date=2021-04-01&rft.volume=147&rft.issue=4&rft.issn=0733-9364&rft.eissn=1943-7862&rft_id=info:doi/10.1061/(ASCE)CO.1943-7862.0002010&rft_dat=%3Cproquest_cross%3E2478924767%3C/proquest_cross%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_pqid=2478924767&rft_id=info:pmid/&rfr_iscdi=true