Methodology to Link the Results of Radiological Characterizations of Decommissioning Nuclear Power Plants

Kori Unit 1, the first commercial nuclear power plant (NPP) in Korea, was permanently shut down in 2017 and was scheduled for decommissioning. Various programs must be planned early in the decommissioning process to safely decommission NPPs. Radiological characterization is a key program in decommis...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Veröffentlicht in:Journal of nuclear fuel cycle and waste technology (Online) 2024, Vol.22 (3), p.363-376
Hauptverfasser: Jaeok Park, Tae Young Kong, Seongjun Kim, Jinho Son, Changju Song, Jiung Kim, Seungho Jo, Hee Geun Kim
Format: Artikel
Sprache:kor
Online-Zugang:Volltext
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page 376
container_issue 3
container_start_page 363
container_title Journal of nuclear fuel cycle and waste technology (Online)
container_volume 22
creator Jaeok Park
Tae Young Kong
Seongjun Kim
Jinho Son
Changju Song
Jiung Kim
Seungho Jo
Hee Geun Kim
description Kori Unit 1, the first commercial nuclear power plant (NPP) in Korea, was permanently shut down in 2017 and was scheduled for decommissioning. Various programs must be planned early in the decommissioning process to safely decommission NPPs. Radiological characterization is a key program in decommissioning and should be a high priority. Radiological characterization involves determining the decommissioning technology to be applied to a nuclear facility by identifying the radiation sources and radioactive contaminants present within the facility and assessing the extent and nature of the radioactive contaminants to be removed from the facility. This study introduces the regulatory requirements, procedures, and implementation methods for radiological characterization and proposes a methodology to link the results of radiological characterizations for each stage. To link radiological characteristics, this study proposes to conduct radiological characterization in the decommissioning phase to verify the results of radiological characterization in the transitional phase of decommissioning NPPs. This enables significantly reducing the scope and content of radiological characterization that must be performed in the decommissioning phase and maintaining the connection with the previous phase.
format Article
fullrecord <record><control><sourceid>kisti</sourceid><recordid>TN_cdi_kisti_ndsl_JAKO202431343280705</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>JAKO202431343280705</sourcerecordid><originalsourceid>FETCH-kisti_ndsl_JAKO2024313432807053</originalsourceid><addsrcrecordid>eNqNzs2KwjAUBeAgDlgc3-FuXBbaJJJ0KeowOP4hs5dMm9qLMReaiOjTTxUfwM05m4_D6bGEc63TiVR5nyW5EjrNdSEHbBQC_mVCZ0oqVSQM1zY2VJGj4w0iwQr9CWJjYW_DxcUAVMPeVPgAWBoHs8a0poy2xbuJSP4p5rak8xm7bfLoj7C5lM6aFnZ0tV0642P4ZB-1ccGOXj1k46_F7-w7PWGIePBVcIfl9GfLMy5FLqTg3clsIt51_6X3SP0</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>article</recordtype></control><display><type>article</type><title>Methodology to Link the Results of Radiological Characterizations of Decommissioning Nuclear Power Plants</title><source>DOAJ Directory of Open Access Journals</source><creator>Jaeok Park ; Tae Young Kong ; Seongjun Kim ; Jinho Son ; Changju Song ; Jiung Kim ; Seungho Jo ; Hee Geun Kim</creator><creatorcontrib>Jaeok Park ; Tae Young Kong ; Seongjun Kim ; Jinho Son ; Changju Song ; Jiung Kim ; Seungho Jo ; Hee Geun Kim</creatorcontrib><description>Kori Unit 1, the first commercial nuclear power plant (NPP) in Korea, was permanently shut down in 2017 and was scheduled for decommissioning. Various programs must be planned early in the decommissioning process to safely decommission NPPs. Radiological characterization is a key program in decommissioning and should be a high priority. Radiological characterization involves determining the decommissioning technology to be applied to a nuclear facility by identifying the radiation sources and radioactive contaminants present within the facility and assessing the extent and nature of the radioactive contaminants to be removed from the facility. This study introduces the regulatory requirements, procedures, and implementation methods for radiological characterization and proposes a methodology to link the results of radiological characterizations for each stage. To link radiological characteristics, this study proposes to conduct radiological characterization in the decommissioning phase to verify the results of radiological characterization in the transitional phase of decommissioning NPPs. This enables significantly reducing the scope and content of radiological characterization that must be performed in the decommissioning phase and maintaining the connection with the previous phase.</description><identifier>ISSN: 1738-1894</identifier><identifier>EISSN: 2288-5471</identifier><language>kor</language><ispartof>Journal of nuclear fuel cycle and waste technology (Online), 2024, Vol.22 (3), p.363-376</ispartof><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><link.rule.ids>230,314,780,784,885,4024</link.rule.ids></links><search><creatorcontrib>Jaeok Park</creatorcontrib><creatorcontrib>Tae Young Kong</creatorcontrib><creatorcontrib>Seongjun Kim</creatorcontrib><creatorcontrib>Jinho Son</creatorcontrib><creatorcontrib>Changju Song</creatorcontrib><creatorcontrib>Jiung Kim</creatorcontrib><creatorcontrib>Seungho Jo</creatorcontrib><creatorcontrib>Hee Geun Kim</creatorcontrib><title>Methodology to Link the Results of Radiological Characterizations of Decommissioning Nuclear Power Plants</title><title>Journal of nuclear fuel cycle and waste technology (Online)</title><addtitle>방사성폐기물학회지</addtitle><description>Kori Unit 1, the first commercial nuclear power plant (NPP) in Korea, was permanently shut down in 2017 and was scheduled for decommissioning. Various programs must be planned early in the decommissioning process to safely decommission NPPs. Radiological characterization is a key program in decommissioning and should be a high priority. Radiological characterization involves determining the decommissioning technology to be applied to a nuclear facility by identifying the radiation sources and radioactive contaminants present within the facility and assessing the extent and nature of the radioactive contaminants to be removed from the facility. This study introduces the regulatory requirements, procedures, and implementation methods for radiological characterization and proposes a methodology to link the results of radiological characterizations for each stage. To link radiological characteristics, this study proposes to conduct radiological characterization in the decommissioning phase to verify the results of radiological characterization in the transitional phase of decommissioning NPPs. This enables significantly reducing the scope and content of radiological characterization that must be performed in the decommissioning phase and maintaining the connection with the previous phase.</description><issn>1738-1894</issn><issn>2288-5471</issn><fulltext>true</fulltext><rsrctype>article</rsrctype><creationdate>2024</creationdate><recordtype>article</recordtype><sourceid>JDI</sourceid><recordid>eNqNzs2KwjAUBeAgDlgc3-FuXBbaJJJ0KeowOP4hs5dMm9qLMReaiOjTTxUfwM05m4_D6bGEc63TiVR5nyW5EjrNdSEHbBQC_mVCZ0oqVSQM1zY2VJGj4w0iwQr9CWJjYW_DxcUAVMPeVPgAWBoHs8a0poy2xbuJSP4p5rak8xm7bfLoj7C5lM6aFnZ0tV0642P4ZB-1ccGOXj1k46_F7-w7PWGIePBVcIfl9GfLMy5FLqTg3clsIt51_6X3SP0</recordid><startdate>2024</startdate><enddate>2024</enddate><creator>Jaeok Park</creator><creator>Tae Young Kong</creator><creator>Seongjun Kim</creator><creator>Jinho Son</creator><creator>Changju Song</creator><creator>Jiung Kim</creator><creator>Seungho Jo</creator><creator>Hee Geun Kim</creator><scope>JDI</scope></search><sort><creationdate>2024</creationdate><title>Methodology to Link the Results of Radiological Characterizations of Decommissioning Nuclear Power Plants</title><author>Jaeok Park ; Tae Young Kong ; Seongjun Kim ; Jinho Son ; Changju Song ; Jiung Kim ; Seungho Jo ; Hee Geun Kim</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-kisti_ndsl_JAKO2024313432807053</frbrgroupid><rsrctype>articles</rsrctype><prefilter>articles</prefilter><language>kor</language><creationdate>2024</creationdate><toplevel>online_resources</toplevel><creatorcontrib>Jaeok Park</creatorcontrib><creatorcontrib>Tae Young Kong</creatorcontrib><creatorcontrib>Seongjun Kim</creatorcontrib><creatorcontrib>Jinho Son</creatorcontrib><creatorcontrib>Changju Song</creatorcontrib><creatorcontrib>Jiung Kim</creatorcontrib><creatorcontrib>Seungho Jo</creatorcontrib><creatorcontrib>Hee Geun Kim</creatorcontrib><collection>KoreaScience</collection><jtitle>Journal of nuclear fuel cycle and waste technology (Online)</jtitle></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext</fulltext></delivery><addata><au>Jaeok Park</au><au>Tae Young Kong</au><au>Seongjun Kim</au><au>Jinho Son</au><au>Changju Song</au><au>Jiung Kim</au><au>Seungho Jo</au><au>Hee Geun Kim</au><format>journal</format><genre>article</genre><ristype>JOUR</ristype><atitle>Methodology to Link the Results of Radiological Characterizations of Decommissioning Nuclear Power Plants</atitle><jtitle>Journal of nuclear fuel cycle and waste technology (Online)</jtitle><addtitle>방사성폐기물학회지</addtitle><date>2024</date><risdate>2024</risdate><volume>22</volume><issue>3</issue><spage>363</spage><epage>376</epage><pages>363-376</pages><issn>1738-1894</issn><eissn>2288-5471</eissn><abstract>Kori Unit 1, the first commercial nuclear power plant (NPP) in Korea, was permanently shut down in 2017 and was scheduled for decommissioning. Various programs must be planned early in the decommissioning process to safely decommission NPPs. Radiological characterization is a key program in decommissioning and should be a high priority. Radiological characterization involves determining the decommissioning technology to be applied to a nuclear facility by identifying the radiation sources and radioactive contaminants present within the facility and assessing the extent and nature of the radioactive contaminants to be removed from the facility. This study introduces the regulatory requirements, procedures, and implementation methods for radiological characterization and proposes a methodology to link the results of radiological characterizations for each stage. To link radiological characteristics, this study proposes to conduct radiological characterization in the decommissioning phase to verify the results of radiological characterization in the transitional phase of decommissioning NPPs. This enables significantly reducing the scope and content of radiological characterization that must be performed in the decommissioning phase and maintaining the connection with the previous phase.</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext
identifier ISSN: 1738-1894
ispartof Journal of nuclear fuel cycle and waste technology (Online), 2024, Vol.22 (3), p.363-376
issn 1738-1894
2288-5471
language kor
recordid cdi_kisti_ndsl_JAKO202431343280705
source DOAJ Directory of Open Access Journals
title Methodology to Link the Results of Radiological Characterizations of Decommissioning Nuclear Power Plants
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-06T23%3A51%3A57IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-kisti&rft_val_fmt=info:ofi/fmt:kev:mtx:journal&rft.genre=article&rft.atitle=Methodology%20to%20Link%20the%20Results%20of%20Radiological%20Characterizations%20of%20Decommissioning%20Nuclear%20Power%20Plants&rft.jtitle=Journal%20of%20nuclear%20fuel%20cycle%20and%20waste%20technology%20(Online)&rft.au=Jaeok%20Park&rft.date=2024&rft.volume=22&rft.issue=3&rft.spage=363&rft.epage=376&rft.pages=363-376&rft.issn=1738-1894&rft.eissn=2288-5471&rft_id=info:doi/&rft_dat=%3Ckisti%3EJAKO202431343280705%3C/kisti%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true