Intelligent crew and outage scheduling in electrical distribution system by hybrid generic algorithm

Working outages such as component maintenance/exchange and system extension are important routine works in distribution systems. The scheduling for crew dispatching and customer outages is inherently a discrete, nonlinear, and multiple objective problem. In this paper, a hybrid evolutionary algorith...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: Jaw-Shyang Wu, Tsung-En Lee, Chih-Hao Cao
Format: Tagungsbericht
Sprache:eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page 101
container_issue
container_start_page 96
container_title
container_volume
creator Jaw-Shyang Wu
Tsung-En Lee
Chih-Hao Cao
description Working outages such as component maintenance/exchange and system extension are important routine works in distribution systems. The scheduling for crew dispatching and customer outages is inherently a discrete, nonlinear, and multiple objective problem. In this paper, a hybrid evolutionary algorithm is exploited to solve the outage scheduling and crew dispatching for distribution system maintenance. Fitness function with practical considerations is proposed. Optimal solution of the date and timing to start the work and the candidate teams to send for the work are solved. The scheduling is capable of the planning for the cases of multiple teams with different get-into time and get-off time for multiple work areas. A practical distribution system is selected to demonstrate the effectiveness of the proposed approach.
doi_str_mv 10.1109/ICIEA.2009.5138177
format Conference Proceeding
fullrecord <record><control><sourceid>ieee_6IE</sourceid><recordid>TN_cdi_ieee_primary_5138177</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><ieee_id>5138177</ieee_id><sourcerecordid>5138177</sourcerecordid><originalsourceid>FETCH-LOGICAL-i175t-16c5777eef1e25adabf6d780fb24bd428e934b8422d34d5c99454a88dbdf82e3</originalsourceid><addsrcrecordid>eNpNkM1qwzAQhNWfQNM0L9Be9AJOpbVkSccQ-mMI9JJ7kKy1o-I4xVIofvuKNofuZRZm-GCGkEfOVpwz81xv6pf1ChgzK8lLzZW6IkujNBcgBGjG1DWZA5e6ADDq5p-njBG3v15VQMn1jNxnjDasUsDvyDLGT5ZPSDBg5sTXQ8K-Dx0OiTYjflM7eHo6J9shjc0B_bkPQ0fDQLHHJo2hsT31IebPnVM4DTROMeGRuokeJjcGTzMLc47avjuNIR2OD2TW2j7i8qILsnt92W3ei-3HW71Zb4vAlUwFrxqplEJsOYK03rq28kqz1oFwPtdGUwqnBYAvhZdNbiqF1do732rAckGe_rABEfdfYzjacdpf9it_ADuEX5w</addsrcrecordid><sourcetype>Publisher</sourcetype><iscdi>true</iscdi><recordtype>conference_proceeding</recordtype></control><display><type>conference_proceeding</type><title>Intelligent crew and outage scheduling in electrical distribution system by hybrid generic algorithm</title><source>IEEE Electronic Library (IEL) Conference Proceedings</source><creator>Jaw-Shyang Wu ; Tsung-En Lee ; Chih-Hao Cao</creator><creatorcontrib>Jaw-Shyang Wu ; Tsung-En Lee ; Chih-Hao Cao</creatorcontrib><description>Working outages such as component maintenance/exchange and system extension are important routine works in distribution systems. The scheduling for crew dispatching and customer outages is inherently a discrete, nonlinear, and multiple objective problem. In this paper, a hybrid evolutionary algorithm is exploited to solve the outage scheduling and crew dispatching for distribution system maintenance. Fitness function with practical considerations is proposed. Optimal solution of the date and timing to start the work and the candidate teams to send for the work are solved. The scheduling is capable of the planning for the cases of multiple teams with different get-into time and get-off time for multiple work areas. A practical distribution system is selected to demonstrate the effectiveness of the proposed approach.</description><identifier>ISSN: 2156-2318</identifier><identifier>ISBN: 9781424427994</identifier><identifier>ISBN: 1424427991</identifier><identifier>EISSN: 2158-2297</identifier><identifier>EISBN: 9781424428007</identifier><identifier>EISBN: 1424428009</identifier><identifier>DOI: 10.1109/ICIEA.2009.5138177</identifier><identifier>LCCN: 2008906721</identifier><language>eng</language><publisher>IEEE</publisher><subject>Computer science ; Costs ; crew dispatching ; Dispatching ; Evolutionary computation ; Expert systems ; genetic algorithm ; Genetic algorithms ; heuristic rules ; intelligent man-machine interface ; outage scheduling ; Processor scheduling ; Scheduling algorithm ; Timing ; User interfaces</subject><ispartof>2009 4th IEEE Conference on Industrial Electronics and Applications, 2009, p.96-101</ispartof><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://ieeexplore.ieee.org/document/5138177$$EHTML$$P50$$Gieee$$H</linktohtml><link.rule.ids>309,310,780,784,789,790,2058,27925,54920</link.rule.ids><linktorsrc>$$Uhttps://ieeexplore.ieee.org/document/5138177$$EView_record_in_IEEE$$FView_record_in_$$GIEEE</linktorsrc></links><search><creatorcontrib>Jaw-Shyang Wu</creatorcontrib><creatorcontrib>Tsung-En Lee</creatorcontrib><creatorcontrib>Chih-Hao Cao</creatorcontrib><title>Intelligent crew and outage scheduling in electrical distribution system by hybrid generic algorithm</title><title>2009 4th IEEE Conference on Industrial Electronics and Applications</title><addtitle>ICIEA</addtitle><description>Working outages such as component maintenance/exchange and system extension are important routine works in distribution systems. The scheduling for crew dispatching and customer outages is inherently a discrete, nonlinear, and multiple objective problem. In this paper, a hybrid evolutionary algorithm is exploited to solve the outage scheduling and crew dispatching for distribution system maintenance. Fitness function with practical considerations is proposed. Optimal solution of the date and timing to start the work and the candidate teams to send for the work are solved. The scheduling is capable of the planning for the cases of multiple teams with different get-into time and get-off time for multiple work areas. A practical distribution system is selected to demonstrate the effectiveness of the proposed approach.</description><subject>Computer science</subject><subject>Costs</subject><subject>crew dispatching</subject><subject>Dispatching</subject><subject>Evolutionary computation</subject><subject>Expert systems</subject><subject>genetic algorithm</subject><subject>Genetic algorithms</subject><subject>heuristic rules</subject><subject>intelligent man-machine interface</subject><subject>outage scheduling</subject><subject>Processor scheduling</subject><subject>Scheduling algorithm</subject><subject>Timing</subject><subject>User interfaces</subject><issn>2156-2318</issn><issn>2158-2297</issn><isbn>9781424427994</isbn><isbn>1424427991</isbn><isbn>9781424428007</isbn><isbn>1424428009</isbn><fulltext>true</fulltext><rsrctype>conference_proceeding</rsrctype><creationdate>2009</creationdate><recordtype>conference_proceeding</recordtype><sourceid>6IE</sourceid><sourceid>RIE</sourceid><recordid>eNpNkM1qwzAQhNWfQNM0L9Be9AJOpbVkSccQ-mMI9JJ7kKy1o-I4xVIofvuKNofuZRZm-GCGkEfOVpwz81xv6pf1ChgzK8lLzZW6IkujNBcgBGjG1DWZA5e6ADDq5p-njBG3v15VQMn1jNxnjDasUsDvyDLGT5ZPSDBg5sTXQ8K-Dx0OiTYjflM7eHo6J9shjc0B_bkPQ0fDQLHHJo2hsT31IebPnVM4DTROMeGRuokeJjcGTzMLc47avjuNIR2OD2TW2j7i8qILsnt92W3ei-3HW71Zb4vAlUwFrxqplEJsOYK03rq28kqz1oFwPtdGUwqnBYAvhZdNbiqF1do732rAckGe_rABEfdfYzjacdpf9it_ADuEX5w</recordid><startdate>200905</startdate><enddate>200905</enddate><creator>Jaw-Shyang Wu</creator><creator>Tsung-En Lee</creator><creator>Chih-Hao Cao</creator><general>IEEE</general><scope>6IE</scope><scope>6IL</scope><scope>CBEJK</scope><scope>RIE</scope><scope>RIL</scope></search><sort><creationdate>200905</creationdate><title>Intelligent crew and outage scheduling in electrical distribution system by hybrid generic algorithm</title><author>Jaw-Shyang Wu ; Tsung-En Lee ; Chih-Hao Cao</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-LOGICAL-i175t-16c5777eef1e25adabf6d780fb24bd428e934b8422d34d5c99454a88dbdf82e3</frbrgroupid><rsrctype>conference_proceedings</rsrctype><prefilter>conference_proceedings</prefilter><language>eng</language><creationdate>2009</creationdate><topic>Computer science</topic><topic>Costs</topic><topic>crew dispatching</topic><topic>Dispatching</topic><topic>Evolutionary computation</topic><topic>Expert systems</topic><topic>genetic algorithm</topic><topic>Genetic algorithms</topic><topic>heuristic rules</topic><topic>intelligent man-machine interface</topic><topic>outage scheduling</topic><topic>Processor scheduling</topic><topic>Scheduling algorithm</topic><topic>Timing</topic><topic>User interfaces</topic><toplevel>online_resources</toplevel><creatorcontrib>Jaw-Shyang Wu</creatorcontrib><creatorcontrib>Tsung-En Lee</creatorcontrib><creatorcontrib>Chih-Hao Cao</creatorcontrib><collection>IEEE Electronic Library (IEL) Conference Proceedings</collection><collection>IEEE Proceedings Order Plan All Online (POP All Online) 1998-present by volume</collection><collection>IEEE Xplore All Conference Proceedings</collection><collection>IEEE Electronic Library (IEL)</collection><collection>IEEE Proceedings Order Plans (POP All) 1998-Present</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>Jaw-Shyang Wu</au><au>Tsung-En Lee</au><au>Chih-Hao Cao</au><format>book</format><genre>proceeding</genre><ristype>CONF</ristype><atitle>Intelligent crew and outage scheduling in electrical distribution system by hybrid generic algorithm</atitle><btitle>2009 4th IEEE Conference on Industrial Electronics and Applications</btitle><stitle>ICIEA</stitle><date>2009-05</date><risdate>2009</risdate><spage>96</spage><epage>101</epage><pages>96-101</pages><issn>2156-2318</issn><eissn>2158-2297</eissn><isbn>9781424427994</isbn><isbn>1424427991</isbn><eisbn>9781424428007</eisbn><eisbn>1424428009</eisbn><abstract>Working outages such as component maintenance/exchange and system extension are important routine works in distribution systems. The scheduling for crew dispatching and customer outages is inherently a discrete, nonlinear, and multiple objective problem. In this paper, a hybrid evolutionary algorithm is exploited to solve the outage scheduling and crew dispatching for distribution system maintenance. Fitness function with practical considerations is proposed. Optimal solution of the date and timing to start the work and the candidate teams to send for the work are solved. The scheduling is capable of the planning for the cases of multiple teams with different get-into time and get-off time for multiple work areas. A practical distribution system is selected to demonstrate the effectiveness of the proposed approach.</abstract><pub>IEEE</pub><doi>10.1109/ICIEA.2009.5138177</doi><tpages>6</tpages></addata></record>
fulltext fulltext_linktorsrc
identifier ISSN: 2156-2318
ispartof 2009 4th IEEE Conference on Industrial Electronics and Applications, 2009, p.96-101
issn 2156-2318
2158-2297
language eng
recordid cdi_ieee_primary_5138177
source IEEE Electronic Library (IEL) Conference Proceedings
subjects Computer science
Costs
crew dispatching
Dispatching
Evolutionary computation
Expert systems
genetic algorithm
Genetic algorithms
heuristic rules
intelligent man-machine interface
outage scheduling
Processor scheduling
Scheduling algorithm
Timing
User interfaces
title Intelligent crew and outage scheduling in electrical distribution system by hybrid generic algorithm
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-04T20%3A50%3A02IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-ieee_6IE&rft_val_fmt=info:ofi/fmt:kev:mtx:book&rft.genre=proceeding&rft.atitle=Intelligent%20crew%20and%20outage%20scheduling%20in%20electrical%20distribution%20system%20by%20hybrid%20generic%20algorithm&rft.btitle=2009%204th%20IEEE%20Conference%20on%20Industrial%20Electronics%20and%20Applications&rft.au=Jaw-Shyang%20Wu&rft.date=2009-05&rft.spage=96&rft.epage=101&rft.pages=96-101&rft.issn=2156-2318&rft.eissn=2158-2297&rft.isbn=9781424427994&rft.isbn_list=1424427991&rft_id=info:doi/10.1109/ICIEA.2009.5138177&rft_dat=%3Cieee_6IE%3E5138177%3C/ieee_6IE%3E%3Curl%3E%3C/url%3E&rft.eisbn=9781424428007&rft.eisbn_list=1424428009&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rft_ieee_id=5138177&rfr_iscdi=true