System and method for integrated test on primary-secondary pole-mounted breaker

A system and a method for an integrated test on a primary-secondary pole-mounted breaker. The method includes: establishing an electrical connection between the system and the primary-secondary pole-mounted breaker; establishing a communication connection between the system and the primary-secondary...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: Zheng, Zhiyao, Lin, Jianqin, Wu, Gang, Li, Zhi, Hu, Jingbo, Xu, Aimin, Su, Yifang, Gao, Yibo, Yang, Hanpeng, Bian, Weiliang, Yu, Shaofeng
Format: Patent
Sprache:eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator Zheng, Zhiyao
Lin, Jianqin
Wu, Gang
Li, Zhi
Hu, Jingbo
Xu, Aimin
Su, Yifang
Gao, Yibo
Yang, Hanpeng
Bian, Weiliang
Yu, Shaofeng
description A system and a method for an integrated test on a primary-secondary pole-mounted breaker. The method includes: establishing an electrical connection between the system and the primary-secondary pole-mounted breaker; establishing a communication connection between the system and the primary-secondary pole-mounted breaker; applying, by the system, a voltage signal and a current signal to the primary-secondary pole-mounted breaker through the electrical connection, to generate a voltage and a current on the primary-secondary pole-mounted breaker; collecting, by the system, signals of the voltage and the current fed back from the primary-secondary pole-mounted breaker through the communication connection; performing, by the system, an integrated accuracy test and an integrated protection test; outputting a test result of the accuracy test and a test result of the integrated protection test to the industrial control machine, to generate the test report. A blind zone in quality control of primary-secondary pole-mounted breakers is eliminated. Efficiency is improved in testing primary-secondary pole-mounted breakers.
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_US11402457B2</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>US11402457B2</sourcerecordid><originalsourceid>FETCH-epo_espacenet_US11402457B23</originalsourceid><addsrcrecordid>eNqNyjEOwjAQBVE3FAi4w3IASyQE0YNAdBSBOlriH4iIvZa9FLk9IHEAqpniTc25HrPCEwdHHvoQR50k6oPinljhSJGVJFBMvec02oxWgvscRRlgvbzCl90S-Ik0N5OOh4zFrzOzPB4u-5NFlAY5cosAba51UVSrstpsd-X6H_MGgW83bA</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>System and method for integrated test on primary-secondary pole-mounted breaker</title><source>esp@cenet</source><creator>Zheng, Zhiyao ; Lin, Jianqin ; Wu, Gang ; Li, Zhi ; Hu, Jingbo ; Xu, Aimin ; Su, Yifang ; Gao, Yibo ; Yang, Hanpeng ; Bian, Weiliang ; Yu, Shaofeng</creator><creatorcontrib>Zheng, Zhiyao ; Lin, Jianqin ; Wu, Gang ; Li, Zhi ; Hu, Jingbo ; Xu, Aimin ; Su, Yifang ; Gao, Yibo ; Yang, Hanpeng ; Bian, Weiliang ; Yu, Shaofeng</creatorcontrib><description>A system and a method for an integrated test on a primary-secondary pole-mounted breaker. The method includes: establishing an electrical connection between the system and the primary-secondary pole-mounted breaker; establishing a communication connection between the system and the primary-secondary pole-mounted breaker; applying, by the system, a voltage signal and a current signal to the primary-secondary pole-mounted breaker through the electrical connection, to generate a voltage and a current on the primary-secondary pole-mounted breaker; collecting, by the system, signals of the voltage and the current fed back from the primary-secondary pole-mounted breaker through the communication connection; performing, by the system, an integrated accuracy test and an integrated protection test; outputting a test result of the accuracy test and a test result of the integrated protection test to the industrial control machine, to generate the test report. A blind zone in quality control of primary-secondary pole-mounted breakers is eliminated. Efficiency is improved in testing primary-secondary pole-mounted breakers.</description><language>eng</language><subject>MEASURING ; MEASURING ELECTRIC VARIABLES ; MEASURING MAGNETIC VARIABLES ; PHYSICS ; TESTING</subject><creationdate>2022</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20220802&amp;DB=EPODOC&amp;CC=US&amp;NR=11402457B2$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,776,881,25544,76292</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20220802&amp;DB=EPODOC&amp;CC=US&amp;NR=11402457B2$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>Zheng, Zhiyao</creatorcontrib><creatorcontrib>Lin, Jianqin</creatorcontrib><creatorcontrib>Wu, Gang</creatorcontrib><creatorcontrib>Li, Zhi</creatorcontrib><creatorcontrib>Hu, Jingbo</creatorcontrib><creatorcontrib>Xu, Aimin</creatorcontrib><creatorcontrib>Su, Yifang</creatorcontrib><creatorcontrib>Gao, Yibo</creatorcontrib><creatorcontrib>Yang, Hanpeng</creatorcontrib><creatorcontrib>Bian, Weiliang</creatorcontrib><creatorcontrib>Yu, Shaofeng</creatorcontrib><title>System and method for integrated test on primary-secondary pole-mounted breaker</title><description>A system and a method for an integrated test on a primary-secondary pole-mounted breaker. The method includes: establishing an electrical connection between the system and the primary-secondary pole-mounted breaker; establishing a communication connection between the system and the primary-secondary pole-mounted breaker; applying, by the system, a voltage signal and a current signal to the primary-secondary pole-mounted breaker through the electrical connection, to generate a voltage and a current on the primary-secondary pole-mounted breaker; collecting, by the system, signals of the voltage and the current fed back from the primary-secondary pole-mounted breaker through the communication connection; performing, by the system, an integrated accuracy test and an integrated protection test; outputting a test result of the accuracy test and a test result of the integrated protection test to the industrial control machine, to generate the test report. A blind zone in quality control of primary-secondary pole-mounted breakers is eliminated. Efficiency is improved in testing primary-secondary pole-mounted breakers.</description><subject>MEASURING</subject><subject>MEASURING ELECTRIC VARIABLES</subject><subject>MEASURING MAGNETIC VARIABLES</subject><subject>PHYSICS</subject><subject>TESTING</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2022</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNyjEOwjAQBVE3FAi4w3IASyQE0YNAdBSBOlriH4iIvZa9FLk9IHEAqpniTc25HrPCEwdHHvoQR50k6oPinljhSJGVJFBMvec02oxWgvscRRlgvbzCl90S-Ik0N5OOh4zFrzOzPB4u-5NFlAY5cosAba51UVSrstpsd-X6H_MGgW83bA</recordid><startdate>20220802</startdate><enddate>20220802</enddate><creator>Zheng, Zhiyao</creator><creator>Lin, Jianqin</creator><creator>Wu, Gang</creator><creator>Li, Zhi</creator><creator>Hu, Jingbo</creator><creator>Xu, Aimin</creator><creator>Su, Yifang</creator><creator>Gao, Yibo</creator><creator>Yang, Hanpeng</creator><creator>Bian, Weiliang</creator><creator>Yu, Shaofeng</creator><scope>EVB</scope></search><sort><creationdate>20220802</creationdate><title>System and method for integrated test on primary-secondary pole-mounted breaker</title><author>Zheng, Zhiyao ; Lin, Jianqin ; Wu, Gang ; Li, Zhi ; Hu, Jingbo ; Xu, Aimin ; Su, Yifang ; Gao, Yibo ; Yang, Hanpeng ; Bian, Weiliang ; Yu, Shaofeng</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_US11402457B23</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>eng</language><creationdate>2022</creationdate><topic>MEASURING</topic><topic>MEASURING ELECTRIC VARIABLES</topic><topic>MEASURING MAGNETIC VARIABLES</topic><topic>PHYSICS</topic><topic>TESTING</topic><toplevel>online_resources</toplevel><creatorcontrib>Zheng, Zhiyao</creatorcontrib><creatorcontrib>Lin, Jianqin</creatorcontrib><creatorcontrib>Wu, Gang</creatorcontrib><creatorcontrib>Li, Zhi</creatorcontrib><creatorcontrib>Hu, Jingbo</creatorcontrib><creatorcontrib>Xu, Aimin</creatorcontrib><creatorcontrib>Su, Yifang</creatorcontrib><creatorcontrib>Gao, Yibo</creatorcontrib><creatorcontrib>Yang, Hanpeng</creatorcontrib><creatorcontrib>Bian, Weiliang</creatorcontrib><creatorcontrib>Yu, Shaofeng</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>Zheng, Zhiyao</au><au>Lin, Jianqin</au><au>Wu, Gang</au><au>Li, Zhi</au><au>Hu, Jingbo</au><au>Xu, Aimin</au><au>Su, Yifang</au><au>Gao, Yibo</au><au>Yang, Hanpeng</au><au>Bian, Weiliang</au><au>Yu, Shaofeng</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>System and method for integrated test on primary-secondary pole-mounted breaker</title><date>2022-08-02</date><risdate>2022</risdate><abstract>A system and a method for an integrated test on a primary-secondary pole-mounted breaker. The method includes: establishing an electrical connection between the system and the primary-secondary pole-mounted breaker; establishing a communication connection between the system and the primary-secondary pole-mounted breaker; applying, by the system, a voltage signal and a current signal to the primary-secondary pole-mounted breaker through the electrical connection, to generate a voltage and a current on the primary-secondary pole-mounted breaker; collecting, by the system, signals of the voltage and the current fed back from the primary-secondary pole-mounted breaker through the communication connection; performing, by the system, an integrated accuracy test and an integrated protection test; outputting a test result of the accuracy test and a test result of the integrated protection test to the industrial control machine, to generate the test report. A blind zone in quality control of primary-secondary pole-mounted breakers is eliminated. Efficiency is improved in testing primary-secondary pole-mounted breakers.</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language eng
recordid cdi_epo_espacenet_US11402457B2
source esp@cenet
subjects MEASURING
MEASURING ELECTRIC VARIABLES
MEASURING MAGNETIC VARIABLES
PHYSICS
TESTING
title System and method for integrated test on primary-secondary pole-mounted breaker
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-28T09%3A56%3A08IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=Zheng,%20Zhiyao&rft.date=2022-08-02&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3EUS11402457B2%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true