Project progress control method and system based on double-code network plan, medium and equipment

The invention provides a project progress control method and system based on a double-code network plan, a medium and equipment, a network logic unit is adopted as a basic unit of network construction, the total time difference of work is determined by the network logic unit, and the free time diffe...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: PANG ZHENNING, CHEN YONGMING, WANG GANG, ZHU SHUSHU, WANG WANG, LI GUANGDONG, XIAO LIANG, ZHONG ZHENXIANG
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator PANG ZHENNING
CHEN YONGMING
WANG GANG
ZHU SHUSHU
WANG WANG
LI GUANGDONG
XIAO LIANG
ZHONG ZHENXIANG
description The invention provides a project progress control method and system based on a double-code network plan, a medium and equipment, a network logic unit is adopted as a basic unit of network construction, the total time difference of work is determined by the network logic unit, and the free time difference of work is jointly determined by the network logic unit and the function of virtual work. According to the checked project progress deviation, the total time difference, the free time difference and the network logic unit road section of each work are utilized to determine a responsible person which mistakes the construction period, and the responsible person is used for formulating a work-up deviation correction measure for a worker who mistakes work. According to the method, the total time difference and the free time difference of the work can be calculated without the earliest start time, the latest start time, the earliest end time and the latest end time of the work, the calculation is simple, and the s
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN118521073A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN118521073A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN118521073A3</originalsourceid><addsrcrecordid>eNqNjLEKwjAURbs4iPoPz92CtYiuUhQncXAvaXKr1SQv5qWIf28RP8DpLOeccdacI9-hE4XI1wgR0uxTZEsO6caGlDckb0lw1CiBIfZkuG8scs0G5JFeHB8UrPKLITJd774Rnn0XHHyaZqNWWcHsx0k2P-wv1TFH4BoSlMYwqatTUWzXq2K5KXflP84HY_k-Ew</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Project progress control method and system based on double-code network plan, medium and equipment</title><source>esp@cenet</source><creator>PANG ZHENNING ; CHEN YONGMING ; WANG GANG ; ZHU SHUSHU ; WANG WANG ; LI GUANGDONG ; XIAO LIANG ; ZHONG ZHENXIANG</creator><creatorcontrib>PANG ZHENNING ; CHEN YONGMING ; WANG GANG ; ZHU SHUSHU ; WANG WANG ; LI GUANGDONG ; XIAO LIANG ; ZHONG ZHENXIANG</creatorcontrib><description>The invention provides a project progress control method and system based on a double-code network plan, a medium and equipment, a network logic unit is adopted as a basic unit of network construction, the total time difference of work is determined by the network logic unit, and the free time difference of work is jointly determined by the network logic unit and the function of virtual work. According to the checked project progress deviation, the total time difference, the free time difference and the network logic unit road section of each work are utilized to determine a responsible person which mistakes the construction period, and the responsible person is used for formulating a work-up deviation correction measure for a worker who mistakes work. According to the method, the total time difference and the free time difference of the work can be calculated without the earliest start time, the latest start time, the earliest end time and the latest end time of the work, the calculation is simple, and the s</description><language>chi ; eng</language><subject>CALCULATING ; COMPUTING ; COUNTING ; DATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FORADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORYOR FORECASTING PURPOSES ; PHYSICS ; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE,COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTINGPURPOSES, NOT OTHERWISE PROVIDED FOR</subject><creationdate>2024</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20240820&amp;DB=EPODOC&amp;CC=CN&amp;NR=118521073A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,777,882,25545,76296</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20240820&amp;DB=EPODOC&amp;CC=CN&amp;NR=118521073A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>PANG ZHENNING</creatorcontrib><creatorcontrib>CHEN YONGMING</creatorcontrib><creatorcontrib>WANG GANG</creatorcontrib><creatorcontrib>ZHU SHUSHU</creatorcontrib><creatorcontrib>WANG WANG</creatorcontrib><creatorcontrib>LI GUANGDONG</creatorcontrib><creatorcontrib>XIAO LIANG</creatorcontrib><creatorcontrib>ZHONG ZHENXIANG</creatorcontrib><title>Project progress control method and system based on double-code network plan, medium and equipment</title><description>The invention provides a project progress control method and system based on a double-code network plan, a medium and equipment, a network logic unit is adopted as a basic unit of network construction, the total time difference of work is determined by the network logic unit, and the free time difference of work is jointly determined by the network logic unit and the function of virtual work. According to the checked project progress deviation, the total time difference, the free time difference and the network logic unit road section of each work are utilized to determine a responsible person which mistakes the construction period, and the responsible person is used for formulating a work-up deviation correction measure for a worker who mistakes work. According to the method, the total time difference and the free time difference of the work can be calculated without the earliest start time, the latest start time, the earliest end time and the latest end time of the work, the calculation is simple, and the s</description><subject>CALCULATING</subject><subject>COMPUTING</subject><subject>COUNTING</subject><subject>DATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FORADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORYOR FORECASTING PURPOSES</subject><subject>PHYSICS</subject><subject>SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE,COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTINGPURPOSES, NOT OTHERWISE PROVIDED FOR</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2024</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNjLEKwjAURbs4iPoPz92CtYiuUhQncXAvaXKr1SQv5qWIf28RP8DpLOeccdacI9-hE4XI1wgR0uxTZEsO6caGlDckb0lw1CiBIfZkuG8scs0G5JFeHB8UrPKLITJd774Rnn0XHHyaZqNWWcHsx0k2P-wv1TFH4BoSlMYwqatTUWzXq2K5KXflP84HY_k-Ew</recordid><startdate>20240820</startdate><enddate>20240820</enddate><creator>PANG ZHENNING</creator><creator>CHEN YONGMING</creator><creator>WANG GANG</creator><creator>ZHU SHUSHU</creator><creator>WANG WANG</creator><creator>LI GUANGDONG</creator><creator>XIAO LIANG</creator><creator>ZHONG ZHENXIANG</creator><scope>EVB</scope></search><sort><creationdate>20240820</creationdate><title>Project progress control method and system based on double-code network plan, medium and equipment</title><author>PANG ZHENNING ; CHEN YONGMING ; WANG GANG ; ZHU SHUSHU ; WANG WANG ; LI GUANGDONG ; XIAO LIANG ; ZHONG ZHENXIANG</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN118521073A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2024</creationdate><topic>CALCULATING</topic><topic>COMPUTING</topic><topic>COUNTING</topic><topic>DATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FORADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORYOR FORECASTING PURPOSES</topic><topic>PHYSICS</topic><topic>SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE,COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTINGPURPOSES, NOT OTHERWISE PROVIDED FOR</topic><toplevel>online_resources</toplevel><creatorcontrib>PANG ZHENNING</creatorcontrib><creatorcontrib>CHEN YONGMING</creatorcontrib><creatorcontrib>WANG GANG</creatorcontrib><creatorcontrib>ZHU SHUSHU</creatorcontrib><creatorcontrib>WANG WANG</creatorcontrib><creatorcontrib>LI GUANGDONG</creatorcontrib><creatorcontrib>XIAO LIANG</creatorcontrib><creatorcontrib>ZHONG ZHENXIANG</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>PANG ZHENNING</au><au>CHEN YONGMING</au><au>WANG GANG</au><au>ZHU SHUSHU</au><au>WANG WANG</au><au>LI GUANGDONG</au><au>XIAO LIANG</au><au>ZHONG ZHENXIANG</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Project progress control method and system based on double-code network plan, medium and equipment</title><date>2024-08-20</date><risdate>2024</risdate><abstract>The invention provides a project progress control method and system based on a double-code network plan, a medium and equipment, a network logic unit is adopted as a basic unit of network construction, the total time difference of work is determined by the network logic unit, and the free time difference of work is jointly determined by the network logic unit and the function of virtual work. According to the checked project progress deviation, the total time difference, the free time difference and the network logic unit road section of each work are utilized to determine a responsible person which mistakes the construction period, and the responsible person is used for formulating a work-up deviation correction measure for a worker who mistakes work. According to the method, the total time difference and the free time difference of the work can be calculated without the earliest start time, the latest start time, the earliest end time and the latest end time of the work, the calculation is simple, and the s</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN118521073A
source esp@cenet
subjects CALCULATING
COMPUTING
COUNTING
DATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FORADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORYOR FORECASTING PURPOSES
PHYSICS
SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE,COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTINGPURPOSES, NOT OTHERWISE PROVIDED FOR
title Project progress control method and system based on double-code network plan, medium and equipment
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-19T00%3A47%3A32IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=PANG%20ZHENNING&rft.date=2024-08-20&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN118521073A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true