The invention provides an ultra-large open caisson sinking soil taking construction method which comprises the steps that an open caisson core area and a remaining area are divided, an open caisson is divided into a plurality of areas, a soil taking area and a soil taking blind area of a well hole a...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: WANG XIN, JIANG JIANGHUA, TANG ZHONGGUO, FANG LIN, LI JIE, ZHANG XUGUANG, YU XIANGJUN, HUANG FENG, WEI XIAONING, OUYANG RUIPING
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator WANG XIN
JIANG JIANGHUA
TANG ZHONGGUO
FANG LIN
LI JIE
ZHANG XUGUANG
YU XIANGJUN
HUANG FENG
WEI XIAONING
OUYANG RUIPING
description The invention provides an ultra-large open caisson sinking soil taking construction method which comprises the steps that an open caisson core area and a remaining area are divided, an open caisson is divided into a plurality of areas, a soil taking area and a soil taking blind area of a well hole are determined, the soil taking depth of the soil taking area of the well hole is determined, layered and zoned soil taking is conducted on the whole section of the open caisson, and a mud suction hole and a water jetting hole are reserved through an open caisson structure. High-pressure jet water flow is adopted to destroy a blind area soil body, and the soil sampling progress is adjusted based on open caisson foundation posture monitoring and structural stress monitoring data. Full-section zoned and layered soil sampling is performed according to the symmetry principle, stable sinking of the open caisson foundation is facilitated, the good sinking state of the open caisson is guaranteed by setting the soil samplin
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN118007687A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN118007687A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN118007687A3</originalsourceid><addsrcrecordid>eNqNykEKwjAQQNFsXIh6h_EAhRbBditBEQRX7suQTmowzoTM9P6CeABXnwd_7W5eWK0uwZIwvMmeMkGUCpr4lXgG5AlUUgbDryXCkq1ik7HOBFKIIWBSFd66VcSstPt14_aX88NfGyoykhYMxGSjv3fd0Lb9cehPh3-eD24yNYM</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Construction method for sinking and soil taking of ultra-large open caisson</title><source>esp@cenet</source><creator>WANG XIN ; JIANG JIANGHUA ; TANG ZHONGGUO ; FANG LIN ; LI JIE ; ZHANG XUGUANG ; YU XIANGJUN ; HUANG FENG ; WEI XIAONING ; OUYANG RUIPING</creator><creatorcontrib>WANG XIN ; JIANG JIANGHUA ; TANG ZHONGGUO ; FANG LIN ; LI JIE ; ZHANG XUGUANG ; YU XIANGJUN ; HUANG FENG ; WEI XIAONING ; OUYANG RUIPING</creatorcontrib><description>The invention provides an ultra-large open caisson sinking soil taking construction method which comprises the steps that an open caisson core area and a remaining area are divided, an open caisson is divided into a plurality of areas, a soil taking area and a soil taking blind area of a well hole are determined, the soil taking depth of the soil taking area of the well hole is determined, layered and zoned soil taking is conducted on the whole section of the open caisson, and a mud suction hole and a water jetting hole are reserved through an open caisson structure. High-pressure jet water flow is adopted to destroy a blind area soil body, and the soil sampling progress is adjusted based on open caisson foundation posture monitoring and structural stress monitoring data. Full-section zoned and layered soil sampling is performed according to the symmetry principle, stable sinking of the open caisson foundation is facilitated, the good sinking state of the open caisson is guaranteed by setting the soil samplin</description><language>chi ; eng</language><subject>EMBANKMENTS ; EXCAVATIONS ; FIXED CONSTRUCTIONS ; FOUNDATIONS ; HYDRAULIC ENGINEERING ; SOIL SHIFTING ; UNDERGROUND OR UNDERWATER STRUCTURES</subject><creationdate>2024</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20240510&amp;DB=EPODOC&amp;CC=CN&amp;NR=118007687A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,780,885,25563,76418</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20240510&amp;DB=EPODOC&amp;CC=CN&amp;NR=118007687A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>WANG XIN</creatorcontrib><creatorcontrib>JIANG JIANGHUA</creatorcontrib><creatorcontrib>TANG ZHONGGUO</creatorcontrib><creatorcontrib>FANG LIN</creatorcontrib><creatorcontrib>LI JIE</creatorcontrib><creatorcontrib>ZHANG XUGUANG</creatorcontrib><creatorcontrib>YU XIANGJUN</creatorcontrib><creatorcontrib>HUANG FENG</creatorcontrib><creatorcontrib>WEI XIAONING</creatorcontrib><creatorcontrib>OUYANG RUIPING</creatorcontrib><title>Construction method for sinking and soil taking of ultra-large open caisson</title><description>The invention provides an ultra-large open caisson sinking soil taking construction method which comprises the steps that an open caisson core area and a remaining area are divided, an open caisson is divided into a plurality of areas, a soil taking area and a soil taking blind area of a well hole are determined, the soil taking depth of the soil taking area of the well hole is determined, layered and zoned soil taking is conducted on the whole section of the open caisson, and a mud suction hole and a water jetting hole are reserved through an open caisson structure. High-pressure jet water flow is adopted to destroy a blind area soil body, and the soil sampling progress is adjusted based on open caisson foundation posture monitoring and structural stress monitoring data. Full-section zoned and layered soil sampling is performed according to the symmetry principle, stable sinking of the open caisson foundation is facilitated, the good sinking state of the open caisson is guaranteed by setting the soil samplin</description><subject>EMBANKMENTS</subject><subject>EXCAVATIONS</subject><subject>FIXED CONSTRUCTIONS</subject><subject>FOUNDATIONS</subject><subject>HYDRAULIC ENGINEERING</subject><subject>SOIL SHIFTING</subject><subject>UNDERGROUND OR UNDERWATER STRUCTURES</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2024</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNykEKwjAQQNFsXIh6h_EAhRbBditBEQRX7suQTmowzoTM9P6CeABXnwd_7W5eWK0uwZIwvMmeMkGUCpr4lXgG5AlUUgbDryXCkq1ik7HOBFKIIWBSFd66VcSstPt14_aX88NfGyoykhYMxGSjv3fd0Lb9cehPh3-eD24yNYM</recordid><startdate>20240510</startdate><enddate>20240510</enddate><creator>WANG XIN</creator><creator>JIANG JIANGHUA</creator><creator>TANG ZHONGGUO</creator><creator>FANG LIN</creator><creator>LI JIE</creator><creator>ZHANG XUGUANG</creator><creator>YU XIANGJUN</creator><creator>HUANG FENG</creator><creator>WEI XIAONING</creator><creator>OUYANG RUIPING</creator><scope>EVB</scope></search><sort><creationdate>20240510</creationdate><title>Construction method for sinking and soil taking of ultra-large open caisson</title><author>WANG XIN ; JIANG JIANGHUA ; TANG ZHONGGUO ; FANG LIN ; LI JIE ; ZHANG XUGUANG ; YU XIANGJUN ; HUANG FENG ; WEI XIAONING ; OUYANG RUIPING</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN118007687A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2024</creationdate><topic>EMBANKMENTS</topic><topic>EXCAVATIONS</topic><topic>FIXED CONSTRUCTIONS</topic><topic>FOUNDATIONS</topic><topic>HYDRAULIC ENGINEERING</topic><topic>SOIL SHIFTING</topic><topic>UNDERGROUND OR UNDERWATER STRUCTURES</topic><toplevel>online_resources</toplevel><creatorcontrib>WANG XIN</creatorcontrib><creatorcontrib>JIANG JIANGHUA</creatorcontrib><creatorcontrib>TANG ZHONGGUO</creatorcontrib><creatorcontrib>FANG LIN</creatorcontrib><creatorcontrib>LI JIE</creatorcontrib><creatorcontrib>ZHANG XUGUANG</creatorcontrib><creatorcontrib>YU XIANGJUN</creatorcontrib><creatorcontrib>HUANG FENG</creatorcontrib><creatorcontrib>WEI XIAONING</creatorcontrib><creatorcontrib>OUYANG RUIPING</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>WANG XIN</au><au>JIANG JIANGHUA</au><au>TANG ZHONGGUO</au><au>FANG LIN</au><au>LI JIE</au><au>ZHANG XUGUANG</au><au>YU XIANGJUN</au><au>HUANG FENG</au><au>WEI XIAONING</au><au>OUYANG RUIPING</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Construction method for sinking and soil taking of ultra-large open caisson</title><date>2024-05-10</date><risdate>2024</risdate><abstract>The invention provides an ultra-large open caisson sinking soil taking construction method which comprises the steps that an open caisson core area and a remaining area are divided, an open caisson is divided into a plurality of areas, a soil taking area and a soil taking blind area of a well hole are determined, the soil taking depth of the soil taking area of the well hole is determined, layered and zoned soil taking is conducted on the whole section of the open caisson, and a mud suction hole and a water jetting hole are reserved through an open caisson structure. High-pressure jet water flow is adopted to destroy a blind area soil body, and the soil sampling progress is adjusted based on open caisson foundation posture monitoring and structural stress monitoring data. Full-section zoned and layered soil sampling is performed according to the symmetry principle, stable sinking of the open caisson foundation is facilitated, the good sinking state of the open caisson is guaranteed by setting the soil samplin</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN118007687A
source esp@cenet
subjects EMBANKMENTS
EXCAVATIONS
FIXED CONSTRUCTIONS
FOUNDATIONS
HYDRAULIC ENGINEERING
SOIL SHIFTING
UNDERGROUND OR UNDERWATER STRUCTURES
title Construction method for sinking and soil taking of ultra-large open caisson
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-08T08%3A09%3A07IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=WANG%20XIN&rft.date=2024-05-10&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN118007687A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true