Comprehensive treatment method for solving bridgehead bumping hazard of low roadbed in soft soil area

The invention belongs to the technical field of geotechnical engineering, and discloses a comprehensive treatment method for solving bridgehead bumping hazards of a low roadbed in a soft soil area. Firstly, a treatment area is determined, a pavement structure layer in the area is cleaned, and pile h...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: DENG MINGHUI, LIU HAITAO, LUO KEQI, LYU ZHENTAO, ZHENG YUEPENG, XU CAIYUN, CHANG YANBIN, LIN JIAN, SHI YINLEI, LI PUYU, WANG FUQI, XIAO ZUNQUN, WANG HUI
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator DENG MINGHUI
LIU HAITAO
LUO KEQI
LYU ZHENTAO
ZHENG YUEPENG
XU CAIYUN
CHANG YANBIN
LIN JIAN
SHI YINLEI
LI PUYU
WANG FUQI
XIAO ZUNQUN
WANG HUI
description The invention belongs to the technical field of geotechnical engineering, and discloses a comprehensive treatment method for solving bridgehead bumping hazards of a low roadbed in a soft soil area. Firstly, a treatment area is determined, a pavement structure layer in the area is cleaned, and pile hole positions are arranged; drilling and soil taking are carried out, and the roadbed soil and the foundation soil are made into flow-state solidified soil; foundation section flow state solidified soil is poured into the pile hole, after the core pile is inserted, the roadbed section flow state solidified soil is poured into the pile hole till the pile hole is filled, and a solidified soil pouring composite pile is formed; and finally, the honeycomb-shaped pavement reinforced panel and the asphalt mixture are laid until the pavement is flush with the bridge floor. The foundation, the roadbed and the pavement structure layer are considered as a whole, the foundation is strengthened through the solidified soil cast-
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN116556124A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN116556124A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN116556124A3</originalsourceid><addsrcrecordid>eNqNjEEKwjAURLtxIeodvgdwUbXdS1FcuXJffs2kDST5IYkVPL0RPICbeTC8mWWFTlyImOCTmUE5grODz-SQJ1GkJVISOxs_0hCNGovKioanC99q4jdHRaLJyouisBqgyPiy0bmEscTlcl0tNNuEzY-rans537vrDkF6pMAPeOS-u9V12zRtvT-eDv84H1txP0Y</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Comprehensive treatment method for solving bridgehead bumping hazard of low roadbed in soft soil area</title><source>esp@cenet</source><creator>DENG MINGHUI ; LIU HAITAO ; LUO KEQI ; LYU ZHENTAO ; ZHENG YUEPENG ; XU CAIYUN ; CHANG YANBIN ; LIN JIAN ; SHI YINLEI ; LI PUYU ; WANG FUQI ; XIAO ZUNQUN ; WANG HUI</creator><creatorcontrib>DENG MINGHUI ; LIU HAITAO ; LUO KEQI ; LYU ZHENTAO ; ZHENG YUEPENG ; XU CAIYUN ; CHANG YANBIN ; LIN JIAN ; SHI YINLEI ; LI PUYU ; WANG FUQI ; XIAO ZUNQUN ; WANG HUI</creatorcontrib><description>The invention belongs to the technical field of geotechnical engineering, and discloses a comprehensive treatment method for solving bridgehead bumping hazards of a low roadbed in a soft soil area. Firstly, a treatment area is determined, a pavement structure layer in the area is cleaned, and pile hole positions are arranged; drilling and soil taking are carried out, and the roadbed soil and the foundation soil are made into flow-state solidified soil; foundation section flow state solidified soil is poured into the pile hole, after the core pile is inserted, the roadbed section flow state solidified soil is poured into the pile hole till the pile hole is filled, and a solidified soil pouring composite pile is formed; and finally, the honeycomb-shaped pavement reinforced panel and the asphalt mixture are laid until the pavement is flush with the bridge floor. The foundation, the roadbed and the pavement structure layer are considered as a whole, the foundation is strengthened through the solidified soil cast-</description><language>chi ; eng</language><subject>ARTIFICIAL STONE ; ASSEMBLY OF BRIDGES ; CEMENTS ; CERAMICS ; CHEMISTRY ; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDINGMATERIALS ; CONCRETE ; CONSTRUCTION OF BRIDGES ; CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES ; CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, ORTHE LIKE ; EMBANKMENTS ; EXCAVATIONS ; FIXED CONSTRUCTIONS ; FOUNDATIONS ; HYDRAULIC ENGINEERING ; LIME, MAGNESIA ; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR ; METALLURGY ; OR VIADUCTS ; REFRACTORIES ; SLAG ; SOIL SHIFTING ; TREATMENT OF NATURAL STONE ; UNDERGROUND OR UNDERWATER STRUCTURES</subject><creationdate>2023</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20230808&amp;DB=EPODOC&amp;CC=CN&amp;NR=116556124A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,780,885,25564,76547</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20230808&amp;DB=EPODOC&amp;CC=CN&amp;NR=116556124A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>DENG MINGHUI</creatorcontrib><creatorcontrib>LIU HAITAO</creatorcontrib><creatorcontrib>LUO KEQI</creatorcontrib><creatorcontrib>LYU ZHENTAO</creatorcontrib><creatorcontrib>ZHENG YUEPENG</creatorcontrib><creatorcontrib>XU CAIYUN</creatorcontrib><creatorcontrib>CHANG YANBIN</creatorcontrib><creatorcontrib>LIN JIAN</creatorcontrib><creatorcontrib>SHI YINLEI</creatorcontrib><creatorcontrib>LI PUYU</creatorcontrib><creatorcontrib>WANG FUQI</creatorcontrib><creatorcontrib>XIAO ZUNQUN</creatorcontrib><creatorcontrib>WANG HUI</creatorcontrib><title>Comprehensive treatment method for solving bridgehead bumping hazard of low roadbed in soft soil area</title><description>The invention belongs to the technical field of geotechnical engineering, and discloses a comprehensive treatment method for solving bridgehead bumping hazards of a low roadbed in a soft soil area. Firstly, a treatment area is determined, a pavement structure layer in the area is cleaned, and pile hole positions are arranged; drilling and soil taking are carried out, and the roadbed soil and the foundation soil are made into flow-state solidified soil; foundation section flow state solidified soil is poured into the pile hole, after the core pile is inserted, the roadbed section flow state solidified soil is poured into the pile hole till the pile hole is filled, and a solidified soil pouring composite pile is formed; and finally, the honeycomb-shaped pavement reinforced panel and the asphalt mixture are laid until the pavement is flush with the bridge floor. The foundation, the roadbed and the pavement structure layer are considered as a whole, the foundation is strengthened through the solidified soil cast-</description><subject>ARTIFICIAL STONE</subject><subject>ASSEMBLY OF BRIDGES</subject><subject>CEMENTS</subject><subject>CERAMICS</subject><subject>CHEMISTRY</subject><subject>COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDINGMATERIALS</subject><subject>CONCRETE</subject><subject>CONSTRUCTION OF BRIDGES</subject><subject>CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES</subject><subject>CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, ORTHE LIKE</subject><subject>EMBANKMENTS</subject><subject>EXCAVATIONS</subject><subject>FIXED CONSTRUCTIONS</subject><subject>FOUNDATIONS</subject><subject>HYDRAULIC ENGINEERING</subject><subject>LIME, MAGNESIA</subject><subject>MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR</subject><subject>METALLURGY</subject><subject>OR VIADUCTS</subject><subject>REFRACTORIES</subject><subject>SLAG</subject><subject>SOIL SHIFTING</subject><subject>TREATMENT OF NATURAL STONE</subject><subject>UNDERGROUND OR UNDERWATER STRUCTURES</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2023</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNjEEKwjAURLtxIeodvgdwUbXdS1FcuXJffs2kDST5IYkVPL0RPICbeTC8mWWFTlyImOCTmUE5grODz-SQJ1GkJVISOxs_0hCNGovKioanC99q4jdHRaLJyouisBqgyPiy0bmEscTlcl0tNNuEzY-rans537vrDkF6pMAPeOS-u9V12zRtvT-eDv84H1txP0Y</recordid><startdate>20230808</startdate><enddate>20230808</enddate><creator>DENG MINGHUI</creator><creator>LIU HAITAO</creator><creator>LUO KEQI</creator><creator>LYU ZHENTAO</creator><creator>ZHENG YUEPENG</creator><creator>XU CAIYUN</creator><creator>CHANG YANBIN</creator><creator>LIN JIAN</creator><creator>SHI YINLEI</creator><creator>LI PUYU</creator><creator>WANG FUQI</creator><creator>XIAO ZUNQUN</creator><creator>WANG HUI</creator><scope>EVB</scope></search><sort><creationdate>20230808</creationdate><title>Comprehensive treatment method for solving bridgehead bumping hazard of low roadbed in soft soil area</title><author>DENG MINGHUI ; LIU HAITAO ; LUO KEQI ; LYU ZHENTAO ; ZHENG YUEPENG ; XU CAIYUN ; CHANG YANBIN ; LIN JIAN ; SHI YINLEI ; LI PUYU ; WANG FUQI ; XIAO ZUNQUN ; WANG HUI</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN116556124A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2023</creationdate><topic>ARTIFICIAL STONE</topic><topic>ASSEMBLY OF BRIDGES</topic><topic>CEMENTS</topic><topic>CERAMICS</topic><topic>CHEMISTRY</topic><topic>COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDINGMATERIALS</topic><topic>CONCRETE</topic><topic>CONSTRUCTION OF BRIDGES</topic><topic>CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES</topic><topic>CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, ORTHE LIKE</topic><topic>EMBANKMENTS</topic><topic>EXCAVATIONS</topic><topic>FIXED CONSTRUCTIONS</topic><topic>FOUNDATIONS</topic><topic>HYDRAULIC ENGINEERING</topic><topic>LIME, MAGNESIA</topic><topic>MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR</topic><topic>METALLURGY</topic><topic>OR VIADUCTS</topic><topic>REFRACTORIES</topic><topic>SLAG</topic><topic>SOIL SHIFTING</topic><topic>TREATMENT OF NATURAL STONE</topic><topic>UNDERGROUND OR UNDERWATER STRUCTURES</topic><toplevel>online_resources</toplevel><creatorcontrib>DENG MINGHUI</creatorcontrib><creatorcontrib>LIU HAITAO</creatorcontrib><creatorcontrib>LUO KEQI</creatorcontrib><creatorcontrib>LYU ZHENTAO</creatorcontrib><creatorcontrib>ZHENG YUEPENG</creatorcontrib><creatorcontrib>XU CAIYUN</creatorcontrib><creatorcontrib>CHANG YANBIN</creatorcontrib><creatorcontrib>LIN JIAN</creatorcontrib><creatorcontrib>SHI YINLEI</creatorcontrib><creatorcontrib>LI PUYU</creatorcontrib><creatorcontrib>WANG FUQI</creatorcontrib><creatorcontrib>XIAO ZUNQUN</creatorcontrib><creatorcontrib>WANG HUI</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>DENG MINGHUI</au><au>LIU HAITAO</au><au>LUO KEQI</au><au>LYU ZHENTAO</au><au>ZHENG YUEPENG</au><au>XU CAIYUN</au><au>CHANG YANBIN</au><au>LIN JIAN</au><au>SHI YINLEI</au><au>LI PUYU</au><au>WANG FUQI</au><au>XIAO ZUNQUN</au><au>WANG HUI</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Comprehensive treatment method for solving bridgehead bumping hazard of low roadbed in soft soil area</title><date>2023-08-08</date><risdate>2023</risdate><abstract>The invention belongs to the technical field of geotechnical engineering, and discloses a comprehensive treatment method for solving bridgehead bumping hazards of a low roadbed in a soft soil area. Firstly, a treatment area is determined, a pavement structure layer in the area is cleaned, and pile hole positions are arranged; drilling and soil taking are carried out, and the roadbed soil and the foundation soil are made into flow-state solidified soil; foundation section flow state solidified soil is poured into the pile hole, after the core pile is inserted, the roadbed section flow state solidified soil is poured into the pile hole till the pile hole is filled, and a solidified soil pouring composite pile is formed; and finally, the honeycomb-shaped pavement reinforced panel and the asphalt mixture are laid until the pavement is flush with the bridge floor. The foundation, the roadbed and the pavement structure layer are considered as a whole, the foundation is strengthened through the solidified soil cast-</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN116556124A
source esp@cenet
subjects ARTIFICIAL STONE
ASSEMBLY OF BRIDGES
CEMENTS
CERAMICS
CHEMISTRY
COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDINGMATERIALS
CONCRETE
CONSTRUCTION OF BRIDGES
CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, ORTHE LIKE
EMBANKMENTS
EXCAVATIONS
FIXED CONSTRUCTIONS
FOUNDATIONS
HYDRAULIC ENGINEERING
LIME, MAGNESIA
MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
METALLURGY
OR VIADUCTS
REFRACTORIES
SLAG
SOIL SHIFTING
TREATMENT OF NATURAL STONE
UNDERGROUND OR UNDERWATER STRUCTURES
title Comprehensive treatment method for solving bridgehead bumping hazard of low roadbed in soft soil area
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2024-12-29T17%3A44%3A18IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=DENG%20MINGHUI&rft.date=2023-08-08&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN116556124A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true