Method for making reinforcing steel bar processing site by utilizing solidified drilling slag soil

The invention discloses a method for making a reinforcing steel bar processing site by using solidified drilling slag soil, which comprises the following steps of: measuring and setting out to mark and form a to-be-hardened area; paving drilling sediment and slurry in the to-be-hardened area to form...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: HAO YU, ZHANG JINGE, GE SHUWEN, ZHAO GAOJIE, LIU YUNSHENG, GUO DANGSHENG, ZHENG MAOYU, WANG WULIN, LIANG CHENGHUA, HE SHIMING, DING XIN, HUANG XINFENG, DANG JINZHONG, HUO JIATIAN, YU HEKUN, WU XIAOGANG, YAO HUALI, WANG CE, YANG LEI, WANG HAINING, SI CHENGQING, XU LISHAN, CAO JIANHUI, YUE ZHONGJIE, CHEN HUI, LI SHIXIN, HONG WEI, JIA CHENG, CHEN PENG
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator HAO YU
ZHANG JINGE
GE SHUWEN
ZHAO GAOJIE
LIU YUNSHENG
GUO DANGSHENG
ZHENG MAOYU
WANG WULIN
LIANG CHENGHUA
HE SHIMING
DING XIN
HUANG XINFENG
DANG JINZHONG
HUO JIATIAN
YU HEKUN
WU XIAOGANG
YAO HUALI
WANG CE
YANG LEI
WANG HAINING
SI CHENGQING
XU LISHAN
CAO JIANHUI
YUE ZHONGJIE
CHEN HUI
LI SHIXIN
HONG WEI
JIA CHENG
CHEN PENG
description The invention discloses a method for making a reinforcing steel bar processing site by using solidified drilling slag soil, which comprises the following steps of: measuring and setting out to mark and form a to-be-hardened area; paving drilling sediment and slurry in the to-be-hardened area to form a soil layer; laying a soil stabilizer on the soil layer; the soil curing agent comprises cement and a composite curing agent, the mass percent of the cement is 5%-10%, and the mass percent of the composite curing agent is 0.04%-0.06%; the composite curing agent comprises a first surfactant and a second surfactant in a mass ratio of 1: (0.2-0.5); mixing the soil layer and a soil stabilizer to form a solidified layer; and treating the curing layer to form the reinforcing steel bar processing site. According to the method, the soil stabilizer is utilized, the water content of the soil formed by the drilling slag soil is reduced, the conversion of turning waste into wealth is achieved, the drilling slag soil is utili
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN116446378A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN116446378A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN116446378A3</originalsourceid><addsrcrecordid>eNqNijsOwjAQRNNQIOAOywEookSBFkUgGqjoI3_GZMUSR7Yp4PQQiwNQzZs3My_0Gan3lpwP9FB3Hm4UwMO3moljAoS0CjQGbxBjlpxA-kXPxMLvbLywZcewZAOLZCdqGliWxcwpiVj9clGsj4dre9pg9B3iqAwGpK69lGVT10213e2rfz4ffoQ-ew</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Method for making reinforcing steel bar processing site by utilizing solidified drilling slag soil</title><source>esp@cenet</source><creator>HAO YU ; ZHANG JINGE ; GE SHUWEN ; ZHAO GAOJIE ; LIU YUNSHENG ; GUO DANGSHENG ; ZHENG MAOYU ; WANG WULIN ; LIANG CHENGHUA ; HE SHIMING ; DING XIN ; HUANG XINFENG ; DANG JINZHONG ; HUO JIATIAN ; YU HEKUN ; WU XIAOGANG ; YAO HUALI ; WANG CE ; YANG LEI ; WANG HAINING ; SI CHENGQING ; XU LISHAN ; CAO JIANHUI ; YUE ZHONGJIE ; CHEN HUI ; LI SHIXIN ; HONG WEI ; JIA CHENG ; CHEN PENG</creator><creatorcontrib>HAO YU ; ZHANG JINGE ; GE SHUWEN ; ZHAO GAOJIE ; LIU YUNSHENG ; GUO DANGSHENG ; ZHENG MAOYU ; WANG WULIN ; LIANG CHENGHUA ; HE SHIMING ; DING XIN ; HUANG XINFENG ; DANG JINZHONG ; HUO JIATIAN ; YU HEKUN ; WU XIAOGANG ; YAO HUALI ; WANG CE ; YANG LEI ; WANG HAINING ; SI CHENGQING ; XU LISHAN ; CAO JIANHUI ; YUE ZHONGJIE ; CHEN HUI ; LI SHIXIN ; HONG WEI ; JIA CHENG ; CHEN PENG</creatorcontrib><description>The invention discloses a method for making a reinforcing steel bar processing site by using solidified drilling slag soil, which comprises the following steps of: measuring and setting out to mark and form a to-be-hardened area; paving drilling sediment and slurry in the to-be-hardened area to form a soil layer; laying a soil stabilizer on the soil layer; the soil curing agent comprises cement and a composite curing agent, the mass percent of the cement is 5%-10%, and the mass percent of the composite curing agent is 0.04%-0.06%; the composite curing agent comprises a first surfactant and a second surfactant in a mass ratio of 1: (0.2-0.5); mixing the soil layer and a soil stabilizer to form a solidified layer; and treating the curing layer to form the reinforcing steel bar processing site. According to the method, the soil stabilizer is utilized, the water content of the soil formed by the drilling slag soil is reduced, the conversion of turning waste into wealth is achieved, the drilling slag soil is utili</description><language>chi ; eng</language><subject>EMBANKMENTS ; EXCAVATIONS ; FIXED CONSTRUCTIONS ; FOUNDATIONS ; HYDRAULIC ENGINEERING ; SOIL SHIFTING ; UNDERGROUND OR UNDERWATER STRUCTURES</subject><creationdate>2023</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20230718&amp;DB=EPODOC&amp;CC=CN&amp;NR=116446378A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,776,881,25542,76290</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20230718&amp;DB=EPODOC&amp;CC=CN&amp;NR=116446378A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>HAO YU</creatorcontrib><creatorcontrib>ZHANG JINGE</creatorcontrib><creatorcontrib>GE SHUWEN</creatorcontrib><creatorcontrib>ZHAO GAOJIE</creatorcontrib><creatorcontrib>LIU YUNSHENG</creatorcontrib><creatorcontrib>GUO DANGSHENG</creatorcontrib><creatorcontrib>ZHENG MAOYU</creatorcontrib><creatorcontrib>WANG WULIN</creatorcontrib><creatorcontrib>LIANG CHENGHUA</creatorcontrib><creatorcontrib>HE SHIMING</creatorcontrib><creatorcontrib>DING XIN</creatorcontrib><creatorcontrib>HUANG XINFENG</creatorcontrib><creatorcontrib>DANG JINZHONG</creatorcontrib><creatorcontrib>HUO JIATIAN</creatorcontrib><creatorcontrib>YU HEKUN</creatorcontrib><creatorcontrib>WU XIAOGANG</creatorcontrib><creatorcontrib>YAO HUALI</creatorcontrib><creatorcontrib>WANG CE</creatorcontrib><creatorcontrib>YANG LEI</creatorcontrib><creatorcontrib>WANG HAINING</creatorcontrib><creatorcontrib>SI CHENGQING</creatorcontrib><creatorcontrib>XU LISHAN</creatorcontrib><creatorcontrib>CAO JIANHUI</creatorcontrib><creatorcontrib>YUE ZHONGJIE</creatorcontrib><creatorcontrib>CHEN HUI</creatorcontrib><creatorcontrib>LI SHIXIN</creatorcontrib><creatorcontrib>HONG WEI</creatorcontrib><creatorcontrib>JIA CHENG</creatorcontrib><creatorcontrib>CHEN PENG</creatorcontrib><title>Method for making reinforcing steel bar processing site by utilizing solidified drilling slag soil</title><description>The invention discloses a method for making a reinforcing steel bar processing site by using solidified drilling slag soil, which comprises the following steps of: measuring and setting out to mark and form a to-be-hardened area; paving drilling sediment and slurry in the to-be-hardened area to form a soil layer; laying a soil stabilizer on the soil layer; the soil curing agent comprises cement and a composite curing agent, the mass percent of the cement is 5%-10%, and the mass percent of the composite curing agent is 0.04%-0.06%; the composite curing agent comprises a first surfactant and a second surfactant in a mass ratio of 1: (0.2-0.5); mixing the soil layer and a soil stabilizer to form a solidified layer; and treating the curing layer to form the reinforcing steel bar processing site. According to the method, the soil stabilizer is utilized, the water content of the soil formed by the drilling slag soil is reduced, the conversion of turning waste into wealth is achieved, the drilling slag soil is utili</description><subject>EMBANKMENTS</subject><subject>EXCAVATIONS</subject><subject>FIXED CONSTRUCTIONS</subject><subject>FOUNDATIONS</subject><subject>HYDRAULIC ENGINEERING</subject><subject>SOIL SHIFTING</subject><subject>UNDERGROUND OR UNDERWATER STRUCTURES</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2023</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNijsOwjAQRNNQIOAOywEookSBFkUgGqjoI3_GZMUSR7Yp4PQQiwNQzZs3My_0Gan3lpwP9FB3Hm4UwMO3moljAoS0CjQGbxBjlpxA-kXPxMLvbLywZcewZAOLZCdqGliWxcwpiVj9clGsj4dre9pg9B3iqAwGpK69lGVT10213e2rfz4ffoQ-ew</recordid><startdate>20230718</startdate><enddate>20230718</enddate><creator>HAO YU</creator><creator>ZHANG JINGE</creator><creator>GE SHUWEN</creator><creator>ZHAO GAOJIE</creator><creator>LIU YUNSHENG</creator><creator>GUO DANGSHENG</creator><creator>ZHENG MAOYU</creator><creator>WANG WULIN</creator><creator>LIANG CHENGHUA</creator><creator>HE SHIMING</creator><creator>DING XIN</creator><creator>HUANG XINFENG</creator><creator>DANG JINZHONG</creator><creator>HUO JIATIAN</creator><creator>YU HEKUN</creator><creator>WU XIAOGANG</creator><creator>YAO HUALI</creator><creator>WANG CE</creator><creator>YANG LEI</creator><creator>WANG HAINING</creator><creator>SI CHENGQING</creator><creator>XU LISHAN</creator><creator>CAO JIANHUI</creator><creator>YUE ZHONGJIE</creator><creator>CHEN HUI</creator><creator>LI SHIXIN</creator><creator>HONG WEI</creator><creator>JIA CHENG</creator><creator>CHEN PENG</creator><scope>EVB</scope></search><sort><creationdate>20230718</creationdate><title>Method for making reinforcing steel bar processing site by utilizing solidified drilling slag soil</title><author>HAO YU ; ZHANG JINGE ; GE SHUWEN ; ZHAO GAOJIE ; LIU YUNSHENG ; GUO DANGSHENG ; ZHENG MAOYU ; WANG WULIN ; LIANG CHENGHUA ; HE SHIMING ; DING XIN ; HUANG XINFENG ; DANG JINZHONG ; HUO JIATIAN ; YU HEKUN ; WU XIAOGANG ; YAO HUALI ; WANG CE ; YANG LEI ; WANG HAINING ; SI CHENGQING ; XU LISHAN ; CAO JIANHUI ; YUE ZHONGJIE ; CHEN HUI ; LI SHIXIN ; HONG WEI ; JIA CHENG ; CHEN PENG</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN116446378A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2023</creationdate><topic>EMBANKMENTS</topic><topic>EXCAVATIONS</topic><topic>FIXED CONSTRUCTIONS</topic><topic>FOUNDATIONS</topic><topic>HYDRAULIC ENGINEERING</topic><topic>SOIL SHIFTING</topic><topic>UNDERGROUND OR UNDERWATER STRUCTURES</topic><toplevel>online_resources</toplevel><creatorcontrib>HAO YU</creatorcontrib><creatorcontrib>ZHANG JINGE</creatorcontrib><creatorcontrib>GE SHUWEN</creatorcontrib><creatorcontrib>ZHAO GAOJIE</creatorcontrib><creatorcontrib>LIU YUNSHENG</creatorcontrib><creatorcontrib>GUO DANGSHENG</creatorcontrib><creatorcontrib>ZHENG MAOYU</creatorcontrib><creatorcontrib>WANG WULIN</creatorcontrib><creatorcontrib>LIANG CHENGHUA</creatorcontrib><creatorcontrib>HE SHIMING</creatorcontrib><creatorcontrib>DING XIN</creatorcontrib><creatorcontrib>HUANG XINFENG</creatorcontrib><creatorcontrib>DANG JINZHONG</creatorcontrib><creatorcontrib>HUO JIATIAN</creatorcontrib><creatorcontrib>YU HEKUN</creatorcontrib><creatorcontrib>WU XIAOGANG</creatorcontrib><creatorcontrib>YAO HUALI</creatorcontrib><creatorcontrib>WANG CE</creatorcontrib><creatorcontrib>YANG LEI</creatorcontrib><creatorcontrib>WANG HAINING</creatorcontrib><creatorcontrib>SI CHENGQING</creatorcontrib><creatorcontrib>XU LISHAN</creatorcontrib><creatorcontrib>CAO JIANHUI</creatorcontrib><creatorcontrib>YUE ZHONGJIE</creatorcontrib><creatorcontrib>CHEN HUI</creatorcontrib><creatorcontrib>LI SHIXIN</creatorcontrib><creatorcontrib>HONG WEI</creatorcontrib><creatorcontrib>JIA CHENG</creatorcontrib><creatorcontrib>CHEN PENG</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>HAO YU</au><au>ZHANG JINGE</au><au>GE SHUWEN</au><au>ZHAO GAOJIE</au><au>LIU YUNSHENG</au><au>GUO DANGSHENG</au><au>ZHENG MAOYU</au><au>WANG WULIN</au><au>LIANG CHENGHUA</au><au>HE SHIMING</au><au>DING XIN</au><au>HUANG XINFENG</au><au>DANG JINZHONG</au><au>HUO JIATIAN</au><au>YU HEKUN</au><au>WU XIAOGANG</au><au>YAO HUALI</au><au>WANG CE</au><au>YANG LEI</au><au>WANG HAINING</au><au>SI CHENGQING</au><au>XU LISHAN</au><au>CAO JIANHUI</au><au>YUE ZHONGJIE</au><au>CHEN HUI</au><au>LI SHIXIN</au><au>HONG WEI</au><au>JIA CHENG</au><au>CHEN PENG</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Method for making reinforcing steel bar processing site by utilizing solidified drilling slag soil</title><date>2023-07-18</date><risdate>2023</risdate><abstract>The invention discloses a method for making a reinforcing steel bar processing site by using solidified drilling slag soil, which comprises the following steps of: measuring and setting out to mark and form a to-be-hardened area; paving drilling sediment and slurry in the to-be-hardened area to form a soil layer; laying a soil stabilizer on the soil layer; the soil curing agent comprises cement and a composite curing agent, the mass percent of the cement is 5%-10%, and the mass percent of the composite curing agent is 0.04%-0.06%; the composite curing agent comprises a first surfactant and a second surfactant in a mass ratio of 1: (0.2-0.5); mixing the soil layer and a soil stabilizer to form a solidified layer; and treating the curing layer to form the reinforcing steel bar processing site. According to the method, the soil stabilizer is utilized, the water content of the soil formed by the drilling slag soil is reduced, the conversion of turning waste into wealth is achieved, the drilling slag soil is utili</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN116446378A
source esp@cenet
subjects EMBANKMENTS
EXCAVATIONS
FIXED CONSTRUCTIONS
FOUNDATIONS
HYDRAULIC ENGINEERING
SOIL SHIFTING
UNDERGROUND OR UNDERWATER STRUCTURES
title Method for making reinforcing steel bar processing site by utilizing solidified drilling slag soil
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-30T10%3A08%3A22IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=HAO%20YU&rft.date=2023-07-18&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN116446378A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true