Walking erecting and disassembling type trestle construction method

The invention provides a walking erecting and disassembling type trestle construction method. The walking erecting and disassembling type trestle construction method comprises the steps that S100, a trestle and a construction platform are erected; s200, after the trestle and the construction platfor...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: CHEN QINGHUA, SONG JIANGHONG, LIU ZHIJUN, DAI XIANGUO, JING JIACHI, ZENG LINGYE, LIU HUAN, YAN FUSHENG, ZHONG SHAOMIN, ZHANG GUANGHUI
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator CHEN QINGHUA
SONG JIANGHONG
LIU ZHIJUN
DAI XIANGUO
JING JIACHI
ZENG LINGYE
LIU HUAN
YAN FUSHENG
ZHONG SHAOMIN
ZHANG GUANGHUI
description The invention provides a walking erecting and disassembling type trestle construction method. The walking erecting and disassembling type trestle construction method comprises the steps that S100, a trestle and a construction platform are erected; s200, after the trestle and the construction platform are erected, the newly-built bridge structure is constructed according to planned procedures and construction period organizations, and the construction sequence of the bridge structure is compact advancing in the direction of the trestle erecting end; s300, trestle dismantling sections are determined, and trestles of the trestle dismantling sections are dismantled in a span-by-span mode; s400, the trestle materials dismantled from the trestle dismantling section are transferred to the trestle erecting end for trestle erecting; and S500, the steps S100 to S400 are repeated till construction of the bridge is completed. By adopting the construction method of S100-S500, the engineering quantity of turnover materials
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN116289565A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN116289565A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN116289565A3</originalsourceid><addsrcrecordid>eNrjZHAOT8zJzsxLV0gtSk0uATES81IUUjKLE4uLU3OTckAiJZUFqQolRanFJTmpCsn5ecUlRaVAtfl5CrmpJRn5KTwMrGmJOcWpvFCam0HRzTXE2UM3tSA_PrW4IDE5NS-1JN7Zz9DQzMjC0tTM1NGYGDUA0B8zRw</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Walking erecting and disassembling type trestle construction method</title><source>esp@cenet</source><creator>CHEN QINGHUA ; SONG JIANGHONG ; LIU ZHIJUN ; DAI XIANGUO ; JING JIACHI ; ZENG LINGYE ; LIU HUAN ; YAN FUSHENG ; ZHONG SHAOMIN ; ZHANG GUANGHUI</creator><creatorcontrib>CHEN QINGHUA ; SONG JIANGHONG ; LIU ZHIJUN ; DAI XIANGUO ; JING JIACHI ; ZENG LINGYE ; LIU HUAN ; YAN FUSHENG ; ZHONG SHAOMIN ; ZHANG GUANGHUI</creatorcontrib><description>The invention provides a walking erecting and disassembling type trestle construction method. The walking erecting and disassembling type trestle construction method comprises the steps that S100, a trestle and a construction platform are erected; s200, after the trestle and the construction platform are erected, the newly-built bridge structure is constructed according to planned procedures and construction period organizations, and the construction sequence of the bridge structure is compact advancing in the direction of the trestle erecting end; s300, trestle dismantling sections are determined, and trestles of the trestle dismantling sections are dismantled in a span-by-span mode; s400, the trestle materials dismantled from the trestle dismantling section are transferred to the trestle erecting end for trestle erecting; and S500, the steps S100 to S400 are repeated till construction of the bridge is completed. By adopting the construction method of S100-S500, the engineering quantity of turnover materials</description><language>chi ; eng</language><subject>ASSEMBLY OF BRIDGES ; CONSTRUCTION OF BRIDGES ; CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES ; FIXED CONSTRUCTIONS ; OR VIADUCTS</subject><creationdate>2023</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20230623&amp;DB=EPODOC&amp;CC=CN&amp;NR=116289565A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,780,885,25563,76318</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20230623&amp;DB=EPODOC&amp;CC=CN&amp;NR=116289565A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>CHEN QINGHUA</creatorcontrib><creatorcontrib>SONG JIANGHONG</creatorcontrib><creatorcontrib>LIU ZHIJUN</creatorcontrib><creatorcontrib>DAI XIANGUO</creatorcontrib><creatorcontrib>JING JIACHI</creatorcontrib><creatorcontrib>ZENG LINGYE</creatorcontrib><creatorcontrib>LIU HUAN</creatorcontrib><creatorcontrib>YAN FUSHENG</creatorcontrib><creatorcontrib>ZHONG SHAOMIN</creatorcontrib><creatorcontrib>ZHANG GUANGHUI</creatorcontrib><title>Walking erecting and disassembling type trestle construction method</title><description>The invention provides a walking erecting and disassembling type trestle construction method. The walking erecting and disassembling type trestle construction method comprises the steps that S100, a trestle and a construction platform are erected; s200, after the trestle and the construction platform are erected, the newly-built bridge structure is constructed according to planned procedures and construction period organizations, and the construction sequence of the bridge structure is compact advancing in the direction of the trestle erecting end; s300, trestle dismantling sections are determined, and trestles of the trestle dismantling sections are dismantled in a span-by-span mode; s400, the trestle materials dismantled from the trestle dismantling section are transferred to the trestle erecting end for trestle erecting; and S500, the steps S100 to S400 are repeated till construction of the bridge is completed. By adopting the construction method of S100-S500, the engineering quantity of turnover materials</description><subject>ASSEMBLY OF BRIDGES</subject><subject>CONSTRUCTION OF BRIDGES</subject><subject>CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES</subject><subject>FIXED CONSTRUCTIONS</subject><subject>OR VIADUCTS</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2023</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNrjZHAOT8zJzsxLV0gtSk0uATES81IUUjKLE4uLU3OTckAiJZUFqQolRanFJTmpCsn5ecUlRaVAtfl5CrmpJRn5KTwMrGmJOcWpvFCam0HRzTXE2UM3tSA_PrW4IDE5NS-1JN7Zz9DQzMjC0tTM1NGYGDUA0B8zRw</recordid><startdate>20230623</startdate><enddate>20230623</enddate><creator>CHEN QINGHUA</creator><creator>SONG JIANGHONG</creator><creator>LIU ZHIJUN</creator><creator>DAI XIANGUO</creator><creator>JING JIACHI</creator><creator>ZENG LINGYE</creator><creator>LIU HUAN</creator><creator>YAN FUSHENG</creator><creator>ZHONG SHAOMIN</creator><creator>ZHANG GUANGHUI</creator><scope>EVB</scope></search><sort><creationdate>20230623</creationdate><title>Walking erecting and disassembling type trestle construction method</title><author>CHEN QINGHUA ; SONG JIANGHONG ; LIU ZHIJUN ; DAI XIANGUO ; JING JIACHI ; ZENG LINGYE ; LIU HUAN ; YAN FUSHENG ; ZHONG SHAOMIN ; ZHANG GUANGHUI</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN116289565A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2023</creationdate><topic>ASSEMBLY OF BRIDGES</topic><topic>CONSTRUCTION OF BRIDGES</topic><topic>CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES</topic><topic>FIXED CONSTRUCTIONS</topic><topic>OR VIADUCTS</topic><toplevel>online_resources</toplevel><creatorcontrib>CHEN QINGHUA</creatorcontrib><creatorcontrib>SONG JIANGHONG</creatorcontrib><creatorcontrib>LIU ZHIJUN</creatorcontrib><creatorcontrib>DAI XIANGUO</creatorcontrib><creatorcontrib>JING JIACHI</creatorcontrib><creatorcontrib>ZENG LINGYE</creatorcontrib><creatorcontrib>LIU HUAN</creatorcontrib><creatorcontrib>YAN FUSHENG</creatorcontrib><creatorcontrib>ZHONG SHAOMIN</creatorcontrib><creatorcontrib>ZHANG GUANGHUI</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>CHEN QINGHUA</au><au>SONG JIANGHONG</au><au>LIU ZHIJUN</au><au>DAI XIANGUO</au><au>JING JIACHI</au><au>ZENG LINGYE</au><au>LIU HUAN</au><au>YAN FUSHENG</au><au>ZHONG SHAOMIN</au><au>ZHANG GUANGHUI</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Walking erecting and disassembling type trestle construction method</title><date>2023-06-23</date><risdate>2023</risdate><abstract>The invention provides a walking erecting and disassembling type trestle construction method. The walking erecting and disassembling type trestle construction method comprises the steps that S100, a trestle and a construction platform are erected; s200, after the trestle and the construction platform are erected, the newly-built bridge structure is constructed according to planned procedures and construction period organizations, and the construction sequence of the bridge structure is compact advancing in the direction of the trestle erecting end; s300, trestle dismantling sections are determined, and trestles of the trestle dismantling sections are dismantled in a span-by-span mode; s400, the trestle materials dismantled from the trestle dismantling section are transferred to the trestle erecting end for trestle erecting; and S500, the steps S100 to S400 are repeated till construction of the bridge is completed. By adopting the construction method of S100-S500, the engineering quantity of turnover materials</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN116289565A
source esp@cenet
subjects ASSEMBLY OF BRIDGES
CONSTRUCTION OF BRIDGES
CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
FIXED CONSTRUCTIONS
OR VIADUCTS
title Walking erecting and disassembling type trestle construction method
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-11T13%3A00%3A08IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=CHEN%20QINGHUA&rft.date=2023-06-23&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN116289565A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true