Fabricated prestressed UHPC (Ultra High Performance Concrete) composite tunnel lining structure and construction method thereof

The invention discloses a fabricated prestressed UHPC (Ultra High Performance Concrete) composite tunnel lining structure and a construction method thereof, the tunnel lining structure comprises a primary support and a secondary lining, the primary support comprises an anchor rod and a UHPC sprayed...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: CHEN MING, WAN WENZHENG, PENG TANG, OUYANG GUORONG, WANG GE, YANG JIAN, LIU SHASHA, ZENG ZIMIN, WU JIANHAI
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator CHEN MING
WAN WENZHENG
PENG TANG
OUYANG GUORONG
WANG GE
YANG JIAN
LIU SHASHA
ZENG ZIMIN
WU JIANHAI
description The invention discloses a fabricated prestressed UHPC (Ultra High Performance Concrete) composite tunnel lining structure and a construction method thereof, the tunnel lining structure comprises a primary support and a secondary lining, the primary support comprises an anchor rod and a UHPC sprayed concrete layer on the inner surface of surrounding rock; the secondary lining is of a prestress assembly type structure and is composed of a plurality of rings of UHPC duct pieces, each ring of UHPC duct piece comprises four segments, namely a vault segment, a left wall segment, a right wall segment and an inverted arch segment, annular connecting joints arranged among the four segments and longitudinal connecting joints arranged among all the rings of UHPC duct pieces are tongue-and-groove type joints, and the tongue-and-groove type joints are matched with the tongue-and-groove type joints. And prestressed steel beams are arranged in the circumferential direction and the longitudinal direction. The structure is re
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN115898454A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN115898454A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN115898454A3</originalsourceid><addsrcrecordid>eNqNjDEKwkAURNNYiHqHb6eFRTBCLCUYUkkKU4d1M0kWkr_L7k_t1V3QA1gMMzwes07epXp5o5WgI-cRJCbE3VR1QYdmEq-oMsNINXxv_axYgwrL2kNwJG1nZ4MRkCzMmGgybHig-LNoWTxIcRct_gJjmWbIaDuSER623yarXk0Bu19vkn15fxbVCc62CE5pMKQtHml6ya95dslu53-cD9KfSS4</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Fabricated prestressed UHPC (Ultra High Performance Concrete) composite tunnel lining structure and construction method thereof</title><source>esp@cenet</source><creator>CHEN MING ; WAN WENZHENG ; PENG TANG ; OUYANG GUORONG ; WANG GE ; YANG JIAN ; LIU SHASHA ; ZENG ZIMIN ; WU JIANHAI</creator><creatorcontrib>CHEN MING ; WAN WENZHENG ; PENG TANG ; OUYANG GUORONG ; WANG GE ; YANG JIAN ; LIU SHASHA ; ZENG ZIMIN ; WU JIANHAI</creatorcontrib><description>The invention discloses a fabricated prestressed UHPC (Ultra High Performance Concrete) composite tunnel lining structure and a construction method thereof, the tunnel lining structure comprises a primary support and a secondary lining, the primary support comprises an anchor rod and a UHPC sprayed concrete layer on the inner surface of surrounding rock; the secondary lining is of a prestress assembly type structure and is composed of a plurality of rings of UHPC duct pieces, each ring of UHPC duct piece comprises four segments, namely a vault segment, a left wall segment, a right wall segment and an inverted arch segment, annular connecting joints arranged among the four segments and longitudinal connecting joints arranged among all the rings of UHPC duct pieces are tongue-and-groove type joints, and the tongue-and-groove type joints are matched with the tongue-and-groove type joints. And prestressed steel beams are arranged in the circumferential direction and the longitudinal direction. The structure is re</description><language>chi ; eng</language><subject>EARTH DRILLING ; FIXED CONSTRUCTIONS ; GALLERIES ; LARGE UNDERGROUND CHAMBERS ; MINING ; SHAFTS ; TUNNELS</subject><creationdate>2023</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20230404&amp;DB=EPODOC&amp;CC=CN&amp;NR=115898454A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,776,881,25542,76290</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20230404&amp;DB=EPODOC&amp;CC=CN&amp;NR=115898454A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>CHEN MING</creatorcontrib><creatorcontrib>WAN WENZHENG</creatorcontrib><creatorcontrib>PENG TANG</creatorcontrib><creatorcontrib>OUYANG GUORONG</creatorcontrib><creatorcontrib>WANG GE</creatorcontrib><creatorcontrib>YANG JIAN</creatorcontrib><creatorcontrib>LIU SHASHA</creatorcontrib><creatorcontrib>ZENG ZIMIN</creatorcontrib><creatorcontrib>WU JIANHAI</creatorcontrib><title>Fabricated prestressed UHPC (Ultra High Performance Concrete) composite tunnel lining structure and construction method thereof</title><description>The invention discloses a fabricated prestressed UHPC (Ultra High Performance Concrete) composite tunnel lining structure and a construction method thereof, the tunnel lining structure comprises a primary support and a secondary lining, the primary support comprises an anchor rod and a UHPC sprayed concrete layer on the inner surface of surrounding rock; the secondary lining is of a prestress assembly type structure and is composed of a plurality of rings of UHPC duct pieces, each ring of UHPC duct piece comprises four segments, namely a vault segment, a left wall segment, a right wall segment and an inverted arch segment, annular connecting joints arranged among the four segments and longitudinal connecting joints arranged among all the rings of UHPC duct pieces are tongue-and-groove type joints, and the tongue-and-groove type joints are matched with the tongue-and-groove type joints. And prestressed steel beams are arranged in the circumferential direction and the longitudinal direction. The structure is re</description><subject>EARTH DRILLING</subject><subject>FIXED CONSTRUCTIONS</subject><subject>GALLERIES</subject><subject>LARGE UNDERGROUND CHAMBERS</subject><subject>MINING</subject><subject>SHAFTS</subject><subject>TUNNELS</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2023</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNjDEKwkAURNNYiHqHb6eFRTBCLCUYUkkKU4d1M0kWkr_L7k_t1V3QA1gMMzwes07epXp5o5WgI-cRJCbE3VR1QYdmEq-oMsNINXxv_axYgwrL2kNwJG1nZ4MRkCzMmGgybHig-LNoWTxIcRct_gJjmWbIaDuSER623yarXk0Bu19vkn15fxbVCc62CE5pMKQtHml6ya95dslu53-cD9KfSS4</recordid><startdate>20230404</startdate><enddate>20230404</enddate><creator>CHEN MING</creator><creator>WAN WENZHENG</creator><creator>PENG TANG</creator><creator>OUYANG GUORONG</creator><creator>WANG GE</creator><creator>YANG JIAN</creator><creator>LIU SHASHA</creator><creator>ZENG ZIMIN</creator><creator>WU JIANHAI</creator><scope>EVB</scope></search><sort><creationdate>20230404</creationdate><title>Fabricated prestressed UHPC (Ultra High Performance Concrete) composite tunnel lining structure and construction method thereof</title><author>CHEN MING ; WAN WENZHENG ; PENG TANG ; OUYANG GUORONG ; WANG GE ; YANG JIAN ; LIU SHASHA ; ZENG ZIMIN ; WU JIANHAI</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN115898454A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2023</creationdate><topic>EARTH DRILLING</topic><topic>FIXED CONSTRUCTIONS</topic><topic>GALLERIES</topic><topic>LARGE UNDERGROUND CHAMBERS</topic><topic>MINING</topic><topic>SHAFTS</topic><topic>TUNNELS</topic><toplevel>online_resources</toplevel><creatorcontrib>CHEN MING</creatorcontrib><creatorcontrib>WAN WENZHENG</creatorcontrib><creatorcontrib>PENG TANG</creatorcontrib><creatorcontrib>OUYANG GUORONG</creatorcontrib><creatorcontrib>WANG GE</creatorcontrib><creatorcontrib>YANG JIAN</creatorcontrib><creatorcontrib>LIU SHASHA</creatorcontrib><creatorcontrib>ZENG ZIMIN</creatorcontrib><creatorcontrib>WU JIANHAI</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>CHEN MING</au><au>WAN WENZHENG</au><au>PENG TANG</au><au>OUYANG GUORONG</au><au>WANG GE</au><au>YANG JIAN</au><au>LIU SHASHA</au><au>ZENG ZIMIN</au><au>WU JIANHAI</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Fabricated prestressed UHPC (Ultra High Performance Concrete) composite tunnel lining structure and construction method thereof</title><date>2023-04-04</date><risdate>2023</risdate><abstract>The invention discloses a fabricated prestressed UHPC (Ultra High Performance Concrete) composite tunnel lining structure and a construction method thereof, the tunnel lining structure comprises a primary support and a secondary lining, the primary support comprises an anchor rod and a UHPC sprayed concrete layer on the inner surface of surrounding rock; the secondary lining is of a prestress assembly type structure and is composed of a plurality of rings of UHPC duct pieces, each ring of UHPC duct piece comprises four segments, namely a vault segment, a left wall segment, a right wall segment and an inverted arch segment, annular connecting joints arranged among the four segments and longitudinal connecting joints arranged among all the rings of UHPC duct pieces are tongue-and-groove type joints, and the tongue-and-groove type joints are matched with the tongue-and-groove type joints. And prestressed steel beams are arranged in the circumferential direction and the longitudinal direction. The structure is re</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN115898454A
source esp@cenet
subjects EARTH DRILLING
FIXED CONSTRUCTIONS
GALLERIES
LARGE UNDERGROUND CHAMBERS
MINING
SHAFTS
TUNNELS
title Fabricated prestressed UHPC (Ultra High Performance Concrete) composite tunnel lining structure and construction method thereof
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-31T06%3A29%3A32IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=CHEN%20MING&rft.date=2023-04-04&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN115898454A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true