The invention discloses a capping beam construction technology which comprises the following steps that S1, the lower half portion of a capping beam is prefabricated in a prefabricating field, a plurality of cast-in-place holes penetrating through the lower half portion of the capping beam need to b...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: YAN HUATANG, LIN YING, LIU ZHIJUN, DAI XIANGUO, ZHONG SHAOMIN, HE LING, ZHANG XIMING, ZHANG GUANGHUI
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator YAN HUATANG
LIN YING
LIU ZHIJUN
DAI XIANGUO
ZHONG SHAOMIN
HE LING
ZHANG XIMING
ZHANG GUANGHUI
description The invention discloses a capping beam construction technology which comprises the following steps that S1, the lower half portion of a capping beam is prefabricated in a prefabricating field, a plurality of cast-in-place holes penetrating through the lower half portion of the capping beam need to be reserved when the lower half portion of the capping beam is prefabricated in the prefabricating field, and the diameter of each cast-in-place hole is equal to that of a corresponding pier column; s2, hoops are installed at the preset positions of the pier columns; s3, the lower half part of the bent cap is transported to a construction site; s4, the lower half portion of the cover beam is hoisted, all the cast-in-place holes in the lower half portion of the cover beam are aligned with the corresponding pier columns in the vertical direction, and then the lower half portion of the cover beam is lowered through a hoisting machine till the lower half portion of the cover beam abuts against the hoop; and S5, a first
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN115807394A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN115807394A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN115807394A3</originalsourceid><addsrcrecordid>eNrjZJB3zi9LLVJISk3MVUjOzysuKSpNLsnMz1MoKMpPTi0u5mFgTUvMKU7lhdLcDIpuriHOHrqpBfnxqcUFicmpeakl8c5-hoamFgbmxpYmjsbEqAEAPmolMA</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Cover beam construction process</title><source>esp@cenet</source><creator>YAN HUATANG ; LIN YING ; LIU ZHIJUN ; DAI XIANGUO ; ZHONG SHAOMIN ; HE LING ; ZHANG XIMING ; ZHANG GUANGHUI</creator><creatorcontrib>YAN HUATANG ; LIN YING ; LIU ZHIJUN ; DAI XIANGUO ; ZHONG SHAOMIN ; HE LING ; ZHANG XIMING ; ZHANG GUANGHUI</creatorcontrib><description>The invention discloses a capping beam construction technology which comprises the following steps that S1, the lower half portion of a capping beam is prefabricated in a prefabricating field, a plurality of cast-in-place holes penetrating through the lower half portion of the capping beam need to be reserved when the lower half portion of the capping beam is prefabricated in the prefabricating field, and the diameter of each cast-in-place hole is equal to that of a corresponding pier column; s2, hoops are installed at the preset positions of the pier columns; s3, the lower half part of the bent cap is transported to a construction site; s4, the lower half portion of the cover beam is hoisted, all the cast-in-place holes in the lower half portion of the cover beam are aligned with the corresponding pier columns in the vertical direction, and then the lower half portion of the cover beam is lowered through a hoisting machine till the lower half portion of the cover beam abuts against the hoop; and S5, a first</description><language>chi ; eng</language><subject>ASSEMBLY OF BRIDGES ; CONSTRUCTION OF BRIDGES ; CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES ; FIXED CONSTRUCTIONS ; OR VIADUCTS</subject><creationdate>2023</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20230317&amp;DB=EPODOC&amp;CC=CN&amp;NR=115807394A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,780,885,25564,76547</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20230317&amp;DB=EPODOC&amp;CC=CN&amp;NR=115807394A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>YAN HUATANG</creatorcontrib><creatorcontrib>LIN YING</creatorcontrib><creatorcontrib>LIU ZHIJUN</creatorcontrib><creatorcontrib>DAI XIANGUO</creatorcontrib><creatorcontrib>ZHONG SHAOMIN</creatorcontrib><creatorcontrib>HE LING</creatorcontrib><creatorcontrib>ZHANG XIMING</creatorcontrib><creatorcontrib>ZHANG GUANGHUI</creatorcontrib><title>Cover beam construction process</title><description>The invention discloses a capping beam construction technology which comprises the following steps that S1, the lower half portion of a capping beam is prefabricated in a prefabricating field, a plurality of cast-in-place holes penetrating through the lower half portion of the capping beam need to be reserved when the lower half portion of the capping beam is prefabricated in the prefabricating field, and the diameter of each cast-in-place hole is equal to that of a corresponding pier column; s2, hoops are installed at the preset positions of the pier columns; s3, the lower half part of the bent cap is transported to a construction site; s4, the lower half portion of the cover beam is hoisted, all the cast-in-place holes in the lower half portion of the cover beam are aligned with the corresponding pier columns in the vertical direction, and then the lower half portion of the cover beam is lowered through a hoisting machine till the lower half portion of the cover beam abuts against the hoop; and S5, a first</description><subject>ASSEMBLY OF BRIDGES</subject><subject>CONSTRUCTION OF BRIDGES</subject><subject>CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES</subject><subject>FIXED CONSTRUCTIONS</subject><subject>OR VIADUCTS</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2023</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNrjZJB3zi9LLVJISk3MVUjOzysuKSpNLsnMz1MoKMpPTi0u5mFgTUvMKU7lhdLcDIpuriHOHrqpBfnxqcUFicmpeakl8c5-hoamFgbmxpYmjsbEqAEAPmolMA</recordid><startdate>20230317</startdate><enddate>20230317</enddate><creator>YAN HUATANG</creator><creator>LIN YING</creator><creator>LIU ZHIJUN</creator><creator>DAI XIANGUO</creator><creator>ZHONG SHAOMIN</creator><creator>HE LING</creator><creator>ZHANG XIMING</creator><creator>ZHANG GUANGHUI</creator><scope>EVB</scope></search><sort><creationdate>20230317</creationdate><title>Cover beam construction process</title><author>YAN HUATANG ; LIN YING ; LIU ZHIJUN ; DAI XIANGUO ; ZHONG SHAOMIN ; HE LING ; ZHANG XIMING ; ZHANG GUANGHUI</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN115807394A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2023</creationdate><topic>ASSEMBLY OF BRIDGES</topic><topic>CONSTRUCTION OF BRIDGES</topic><topic>CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES</topic><topic>FIXED CONSTRUCTIONS</topic><topic>OR VIADUCTS</topic><toplevel>online_resources</toplevel><creatorcontrib>YAN HUATANG</creatorcontrib><creatorcontrib>LIN YING</creatorcontrib><creatorcontrib>LIU ZHIJUN</creatorcontrib><creatorcontrib>DAI XIANGUO</creatorcontrib><creatorcontrib>ZHONG SHAOMIN</creatorcontrib><creatorcontrib>HE LING</creatorcontrib><creatorcontrib>ZHANG XIMING</creatorcontrib><creatorcontrib>ZHANG GUANGHUI</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>YAN HUATANG</au><au>LIN YING</au><au>LIU ZHIJUN</au><au>DAI XIANGUO</au><au>ZHONG SHAOMIN</au><au>HE LING</au><au>ZHANG XIMING</au><au>ZHANG GUANGHUI</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Cover beam construction process</title><date>2023-03-17</date><risdate>2023</risdate><abstract>The invention discloses a capping beam construction technology which comprises the following steps that S1, the lower half portion of a capping beam is prefabricated in a prefabricating field, a plurality of cast-in-place holes penetrating through the lower half portion of the capping beam need to be reserved when the lower half portion of the capping beam is prefabricated in the prefabricating field, and the diameter of each cast-in-place hole is equal to that of a corresponding pier column; s2, hoops are installed at the preset positions of the pier columns; s3, the lower half part of the bent cap is transported to a construction site; s4, the lower half portion of the cover beam is hoisted, all the cast-in-place holes in the lower half portion of the cover beam are aligned with the corresponding pier columns in the vertical direction, and then the lower half portion of the cover beam is lowered through a hoisting machine till the lower half portion of the cover beam abuts against the hoop; and S5, a first</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN115807394A
source esp@cenet
subjects ASSEMBLY OF BRIDGES
CONSTRUCTION OF BRIDGES
CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
FIXED CONSTRUCTIONS
OR VIADUCTS
title Cover beam construction process
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2024-12-24T13%3A54%3A42IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=YAN%20HUATANG&rft.date=2023-03-17&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN115807394A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true