Asynchronous support changing construction method for super-large-area deep foundation pit in complex environment

The invention relates to the technical field of foundation pit support changing, in particular to an asynchronous support changing construction method for an ultra-large-area deep foundation pit in a complex environment. Comprising the steps that S1, a foundation pit is divided into a plurality of a...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: JIN XIAOFEI, LI CHAOLAI, YANG XUDONG, ZHANG TINGAN, TANG ZISEN, ZHAO YANBO, LI ZEBIAO, HU HEXIANG, LI HUANJUN, MIAO YINGJING
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator JIN XIAOFEI
LI CHAOLAI
YANG XUDONG
ZHANG TINGAN
TANG ZISEN
ZHAO YANBO
LI ZEBIAO
HU HEXIANG
LI HUANJUN
MIAO YINGJING
description The invention relates to the technical field of foundation pit support changing, in particular to an asynchronous support changing construction method for an ultra-large-area deep foundation pit in a complex environment. Comprising the steps that S1, a foundation pit is divided into a plurality of areas, the areas are enclosed through surveying and setting out, and the interiors of the areas are cleaned; s2, the elevation is designed, a foundation bed is constructed according to requirements, and a pipeline chamber is poured in the foundation pit; s3, expansive concrete construction is conducted on the main structure pipeline chamber; s4, a support changing platform is installed, and the support changing platform is divided into a first supporting platform, a second supporting platform and a third supporting platform according to the depth of the foundation pit; s5, foam concrete backfilling is conducted after the support changing platform is installed; s6, dismounting a platform plate, a horizontal jack and
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN115787672A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN115787672A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN115787672A3</originalsourceid><addsrcrecordid>eNqNzTEOgkAQBVAaC6PeYTwABRrFlhCNlZU9mSwjbAIz4-yu0duLxgNY_eK_nz_P7lV4setNWFKAkFTFIrgeufPcgRMO0ZKLXhhGir20cBP7QLJ8QOsoRyOElkinJnGLX6s-gudpP-pATyB--OljJI7LbHbDIdDql4tsfTpe63NOKg0FRUdMsakvRbErD-W-3FTbf8wbdk5FHg</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Asynchronous support changing construction method for super-large-area deep foundation pit in complex environment</title><source>esp@cenet</source><creator>JIN XIAOFEI ; LI CHAOLAI ; YANG XUDONG ; ZHANG TINGAN ; TANG ZISEN ; ZHAO YANBO ; LI ZEBIAO ; HU HEXIANG ; LI HUANJUN ; MIAO YINGJING</creator><creatorcontrib>JIN XIAOFEI ; LI CHAOLAI ; YANG XUDONG ; ZHANG TINGAN ; TANG ZISEN ; ZHAO YANBO ; LI ZEBIAO ; HU HEXIANG ; LI HUANJUN ; MIAO YINGJING</creatorcontrib><description>The invention relates to the technical field of foundation pit support changing, in particular to an asynchronous support changing construction method for an ultra-large-area deep foundation pit in a complex environment. Comprising the steps that S1, a foundation pit is divided into a plurality of areas, the areas are enclosed through surveying and setting out, and the interiors of the areas are cleaned; s2, the elevation is designed, a foundation bed is constructed according to requirements, and a pipeline chamber is poured in the foundation pit; s3, expansive concrete construction is conducted on the main structure pipeline chamber; s4, a support changing platform is installed, and the support changing platform is divided into a first supporting platform, a second supporting platform and a third supporting platform according to the depth of the foundation pit; s5, foam concrete backfilling is conducted after the support changing platform is installed; s6, dismounting a platform plate, a horizontal jack and</description><language>chi ; eng</language><subject>EMBANKMENTS ; EXCAVATIONS ; FIXED CONSTRUCTIONS ; FOUNDATIONS ; HYDRAULIC ENGINEERING ; SOIL SHIFTING ; UNDERGROUND OR UNDERWATER STRUCTURES</subject><creationdate>2023</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20230314&amp;DB=EPODOC&amp;CC=CN&amp;NR=115787672A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,309,781,886,25569,76552</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20230314&amp;DB=EPODOC&amp;CC=CN&amp;NR=115787672A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>JIN XIAOFEI</creatorcontrib><creatorcontrib>LI CHAOLAI</creatorcontrib><creatorcontrib>YANG XUDONG</creatorcontrib><creatorcontrib>ZHANG TINGAN</creatorcontrib><creatorcontrib>TANG ZISEN</creatorcontrib><creatorcontrib>ZHAO YANBO</creatorcontrib><creatorcontrib>LI ZEBIAO</creatorcontrib><creatorcontrib>HU HEXIANG</creatorcontrib><creatorcontrib>LI HUANJUN</creatorcontrib><creatorcontrib>MIAO YINGJING</creatorcontrib><title>Asynchronous support changing construction method for super-large-area deep foundation pit in complex environment</title><description>The invention relates to the technical field of foundation pit support changing, in particular to an asynchronous support changing construction method for an ultra-large-area deep foundation pit in a complex environment. Comprising the steps that S1, a foundation pit is divided into a plurality of areas, the areas are enclosed through surveying and setting out, and the interiors of the areas are cleaned; s2, the elevation is designed, a foundation bed is constructed according to requirements, and a pipeline chamber is poured in the foundation pit; s3, expansive concrete construction is conducted on the main structure pipeline chamber; s4, a support changing platform is installed, and the support changing platform is divided into a first supporting platform, a second supporting platform and a third supporting platform according to the depth of the foundation pit; s5, foam concrete backfilling is conducted after the support changing platform is installed; s6, dismounting a platform plate, a horizontal jack and</description><subject>EMBANKMENTS</subject><subject>EXCAVATIONS</subject><subject>FIXED CONSTRUCTIONS</subject><subject>FOUNDATIONS</subject><subject>HYDRAULIC ENGINEERING</subject><subject>SOIL SHIFTING</subject><subject>UNDERGROUND OR UNDERWATER STRUCTURES</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2023</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNzTEOgkAQBVAaC6PeYTwABRrFlhCNlZU9mSwjbAIz4-yu0duLxgNY_eK_nz_P7lV4setNWFKAkFTFIrgeufPcgRMO0ZKLXhhGir20cBP7QLJ8QOsoRyOElkinJnGLX6s-gudpP-pATyB--OljJI7LbHbDIdDql4tsfTpe63NOKg0FRUdMsakvRbErD-W-3FTbf8wbdk5FHg</recordid><startdate>20230314</startdate><enddate>20230314</enddate><creator>JIN XIAOFEI</creator><creator>LI CHAOLAI</creator><creator>YANG XUDONG</creator><creator>ZHANG TINGAN</creator><creator>TANG ZISEN</creator><creator>ZHAO YANBO</creator><creator>LI ZEBIAO</creator><creator>HU HEXIANG</creator><creator>LI HUANJUN</creator><creator>MIAO YINGJING</creator><scope>EVB</scope></search><sort><creationdate>20230314</creationdate><title>Asynchronous support changing construction method for super-large-area deep foundation pit in complex environment</title><author>JIN XIAOFEI ; LI CHAOLAI ; YANG XUDONG ; ZHANG TINGAN ; TANG ZISEN ; ZHAO YANBO ; LI ZEBIAO ; HU HEXIANG ; LI HUANJUN ; MIAO YINGJING</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN115787672A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2023</creationdate><topic>EMBANKMENTS</topic><topic>EXCAVATIONS</topic><topic>FIXED CONSTRUCTIONS</topic><topic>FOUNDATIONS</topic><topic>HYDRAULIC ENGINEERING</topic><topic>SOIL SHIFTING</topic><topic>UNDERGROUND OR UNDERWATER STRUCTURES</topic><toplevel>online_resources</toplevel><creatorcontrib>JIN XIAOFEI</creatorcontrib><creatorcontrib>LI CHAOLAI</creatorcontrib><creatorcontrib>YANG XUDONG</creatorcontrib><creatorcontrib>ZHANG TINGAN</creatorcontrib><creatorcontrib>TANG ZISEN</creatorcontrib><creatorcontrib>ZHAO YANBO</creatorcontrib><creatorcontrib>LI ZEBIAO</creatorcontrib><creatorcontrib>HU HEXIANG</creatorcontrib><creatorcontrib>LI HUANJUN</creatorcontrib><creatorcontrib>MIAO YINGJING</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>JIN XIAOFEI</au><au>LI CHAOLAI</au><au>YANG XUDONG</au><au>ZHANG TINGAN</au><au>TANG ZISEN</au><au>ZHAO YANBO</au><au>LI ZEBIAO</au><au>HU HEXIANG</au><au>LI HUANJUN</au><au>MIAO YINGJING</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Asynchronous support changing construction method for super-large-area deep foundation pit in complex environment</title><date>2023-03-14</date><risdate>2023</risdate><abstract>The invention relates to the technical field of foundation pit support changing, in particular to an asynchronous support changing construction method for an ultra-large-area deep foundation pit in a complex environment. Comprising the steps that S1, a foundation pit is divided into a plurality of areas, the areas are enclosed through surveying and setting out, and the interiors of the areas are cleaned; s2, the elevation is designed, a foundation bed is constructed according to requirements, and a pipeline chamber is poured in the foundation pit; s3, expansive concrete construction is conducted on the main structure pipeline chamber; s4, a support changing platform is installed, and the support changing platform is divided into a first supporting platform, a second supporting platform and a third supporting platform according to the depth of the foundation pit; s5, foam concrete backfilling is conducted after the support changing platform is installed; s6, dismounting a platform plate, a horizontal jack and</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN115787672A
source esp@cenet
subjects EMBANKMENTS
EXCAVATIONS
FIXED CONSTRUCTIONS
FOUNDATIONS
HYDRAULIC ENGINEERING
SOIL SHIFTING
UNDERGROUND OR UNDERWATER STRUCTURES
title Asynchronous support changing construction method for super-large-area deep foundation pit in complex environment
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2024-12-11T16%3A17%3A45IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=JIN%20XIAOFEI&rft.date=2023-03-14&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN115787672A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true