Tandem type pre-tensioning method double-T-beam prefabricated pipe pile force transmission device and construction method

The invention belongs to the technical field of civil engineering, and particularly relates to a tandem type pre-tensioning method double-T-beam prefabricated pipe pile force transmission device and a construction method. According to the tandem type pre-tensioning method double-T-beam prefabricated...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: ZHANG LIBIN, WANG XIAOHAO, YUAN HAIJIAO, MA XIAOLONG, JIANG YAFEI, LONG ZHAO, YANG YI, ZHANG YANTAO, LU JINPENG, LI HUABIN
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator ZHANG LIBIN
WANG XIAOHAO
YUAN HAIJIAO
MA XIAOLONG
JIANG YAFEI
LONG ZHAO
YANG YI
ZHANG YANTAO
LU JINPENG
LI HUABIN
description The invention belongs to the technical field of civil engineering, and particularly relates to a tandem type pre-tensioning method double-T-beam prefabricated pipe pile force transmission device and a construction method. According to the tandem type pre-tensioning method double-T-beam prefabricated tubular pile force transmission device and the construction method, by arranging the end cross beams, the force transmission columns and the force column supporting mechanisms, when double-T-beam tensioning construction is conducted, the prefabricated tubular piles capable of being repeatedly used serve as a tensioning force transmission system, the structural size of the tensioning end of the double-T-beam and the damage depth of an original hardened base layer are reduced, and the construction efficiency is improved. The invention has the advantages of simple structure, environmental protection and high efficiency, only needs to input recyclable prefabricated tubular piles, force column supporting mechanisms and
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN115771198A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN115771198A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN115771198A3</originalsourceid><addsrcrecordid>eNqNjU0KwjAUhLtxIeodngfIIohUl1IUV666L2ky1UDzQ_Iq9PY26AFcDXzMfLOu5lZ5A0c8R1BMEAyfbfDWP8mBX8GQCVM_QrSih3KlM6g-Wa0YhqItMzuChpA0iJPy2dlcFGTwtgtbDkgHnzlNmgv_erfValBjxu6Xm2p_u7bNXSCGDjkqDQ_umoeUx7qW8ny6HP7pfABHPUdI</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Tandem type pre-tensioning method double-T-beam prefabricated pipe pile force transmission device and construction method</title><source>esp@cenet</source><creator>ZHANG LIBIN ; WANG XIAOHAO ; YUAN HAIJIAO ; MA XIAOLONG ; JIANG YAFEI ; LONG ZHAO ; YANG YI ; ZHANG YANTAO ; LU JINPENG ; LI HUABIN</creator><creatorcontrib>ZHANG LIBIN ; WANG XIAOHAO ; YUAN HAIJIAO ; MA XIAOLONG ; JIANG YAFEI ; LONG ZHAO ; YANG YI ; ZHANG YANTAO ; LU JINPENG ; LI HUABIN</creatorcontrib><description>The invention belongs to the technical field of civil engineering, and particularly relates to a tandem type pre-tensioning method double-T-beam prefabricated pipe pile force transmission device and a construction method. According to the tandem type pre-tensioning method double-T-beam prefabricated tubular pile force transmission device and the construction method, by arranging the end cross beams, the force transmission columns and the force column supporting mechanisms, when double-T-beam tensioning construction is conducted, the prefabricated tubular piles capable of being repeatedly used serve as a tensioning force transmission system, the structural size of the tensioning end of the double-T-beam and the damage depth of an original hardened base layer are reduced, and the construction efficiency is improved. The invention has the advantages of simple structure, environmental protection and high efficiency, only needs to input recyclable prefabricated tubular piles, force column supporting mechanisms and</description><language>chi ; eng</language><subject>PERFORMING OPERATIONS ; SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS, SLAG, OR MIXTURESCONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER ; TRANSPORTING ; WORKING CEMENT, CLAY, OR STONE</subject><creationdate>2023</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20230310&amp;DB=EPODOC&amp;CC=CN&amp;NR=115771198A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,780,885,25564,76547</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20230310&amp;DB=EPODOC&amp;CC=CN&amp;NR=115771198A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>ZHANG LIBIN</creatorcontrib><creatorcontrib>WANG XIAOHAO</creatorcontrib><creatorcontrib>YUAN HAIJIAO</creatorcontrib><creatorcontrib>MA XIAOLONG</creatorcontrib><creatorcontrib>JIANG YAFEI</creatorcontrib><creatorcontrib>LONG ZHAO</creatorcontrib><creatorcontrib>YANG YI</creatorcontrib><creatorcontrib>ZHANG YANTAO</creatorcontrib><creatorcontrib>LU JINPENG</creatorcontrib><creatorcontrib>LI HUABIN</creatorcontrib><title>Tandem type pre-tensioning method double-T-beam prefabricated pipe pile force transmission device and construction method</title><description>The invention belongs to the technical field of civil engineering, and particularly relates to a tandem type pre-tensioning method double-T-beam prefabricated pipe pile force transmission device and a construction method. According to the tandem type pre-tensioning method double-T-beam prefabricated tubular pile force transmission device and the construction method, by arranging the end cross beams, the force transmission columns and the force column supporting mechanisms, when double-T-beam tensioning construction is conducted, the prefabricated tubular piles capable of being repeatedly used serve as a tensioning force transmission system, the structural size of the tensioning end of the double-T-beam and the damage depth of an original hardened base layer are reduced, and the construction efficiency is improved. The invention has the advantages of simple structure, environmental protection and high efficiency, only needs to input recyclable prefabricated tubular piles, force column supporting mechanisms and</description><subject>PERFORMING OPERATIONS</subject><subject>SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS, SLAG, OR MIXTURESCONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER</subject><subject>TRANSPORTING</subject><subject>WORKING CEMENT, CLAY, OR STONE</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2023</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNjU0KwjAUhLtxIeodngfIIohUl1IUV666L2ky1UDzQ_Iq9PY26AFcDXzMfLOu5lZ5A0c8R1BMEAyfbfDWP8mBX8GQCVM_QrSih3KlM6g-Wa0YhqItMzuChpA0iJPy2dlcFGTwtgtbDkgHnzlNmgv_erfValBjxu6Xm2p_u7bNXSCGDjkqDQ_umoeUx7qW8ny6HP7pfABHPUdI</recordid><startdate>20230310</startdate><enddate>20230310</enddate><creator>ZHANG LIBIN</creator><creator>WANG XIAOHAO</creator><creator>YUAN HAIJIAO</creator><creator>MA XIAOLONG</creator><creator>JIANG YAFEI</creator><creator>LONG ZHAO</creator><creator>YANG YI</creator><creator>ZHANG YANTAO</creator><creator>LU JINPENG</creator><creator>LI HUABIN</creator><scope>EVB</scope></search><sort><creationdate>20230310</creationdate><title>Tandem type pre-tensioning method double-T-beam prefabricated pipe pile force transmission device and construction method</title><author>ZHANG LIBIN ; WANG XIAOHAO ; YUAN HAIJIAO ; MA XIAOLONG ; JIANG YAFEI ; LONG ZHAO ; YANG YI ; ZHANG YANTAO ; LU JINPENG ; LI HUABIN</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN115771198A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2023</creationdate><topic>PERFORMING OPERATIONS</topic><topic>SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS, SLAG, OR MIXTURESCONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER</topic><topic>TRANSPORTING</topic><topic>WORKING CEMENT, CLAY, OR STONE</topic><toplevel>online_resources</toplevel><creatorcontrib>ZHANG LIBIN</creatorcontrib><creatorcontrib>WANG XIAOHAO</creatorcontrib><creatorcontrib>YUAN HAIJIAO</creatorcontrib><creatorcontrib>MA XIAOLONG</creatorcontrib><creatorcontrib>JIANG YAFEI</creatorcontrib><creatorcontrib>LONG ZHAO</creatorcontrib><creatorcontrib>YANG YI</creatorcontrib><creatorcontrib>ZHANG YANTAO</creatorcontrib><creatorcontrib>LU JINPENG</creatorcontrib><creatorcontrib>LI HUABIN</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>ZHANG LIBIN</au><au>WANG XIAOHAO</au><au>YUAN HAIJIAO</au><au>MA XIAOLONG</au><au>JIANG YAFEI</au><au>LONG ZHAO</au><au>YANG YI</au><au>ZHANG YANTAO</au><au>LU JINPENG</au><au>LI HUABIN</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Tandem type pre-tensioning method double-T-beam prefabricated pipe pile force transmission device and construction method</title><date>2023-03-10</date><risdate>2023</risdate><abstract>The invention belongs to the technical field of civil engineering, and particularly relates to a tandem type pre-tensioning method double-T-beam prefabricated pipe pile force transmission device and a construction method. According to the tandem type pre-tensioning method double-T-beam prefabricated tubular pile force transmission device and the construction method, by arranging the end cross beams, the force transmission columns and the force column supporting mechanisms, when double-T-beam tensioning construction is conducted, the prefabricated tubular piles capable of being repeatedly used serve as a tensioning force transmission system, the structural size of the tensioning end of the double-T-beam and the damage depth of an original hardened base layer are reduced, and the construction efficiency is improved. The invention has the advantages of simple structure, environmental protection and high efficiency, only needs to input recyclable prefabricated tubular piles, force column supporting mechanisms and</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN115771198A
source esp@cenet
subjects PERFORMING OPERATIONS
SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS, SLAG, OR MIXTURESCONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
TRANSPORTING
WORKING CEMENT, CLAY, OR STONE
title Tandem type pre-tensioning method double-T-beam prefabricated pipe pile force transmission device and construction method
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2024-12-28T03%3A03%3A53IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=ZHANG%20LIBIN&rft.date=2023-03-10&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN115771198A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true